Concrete Construction: Methods and Costs by Gillette and Hill
3. One full depth side form and the side of girder No. 2 formed the mold
4385 words | Chapter 75
for girder No. 4. Girder No. 5 was then molded between girders No. 3 and
No. 4.
[Illustration: Fig. 241.--Arrangement for Molding Four Four-Bracket
Columns and Four Roof Girders]
[Illustration: Fig. 242.--Forms for 50-ft. Roof Girders.]
The construction of the girder forms is shown by Fig. 242. This drawing
shows one of the four main sections making up a complete form. A full
size form of this construction contained about 1,100 ft. B. M. of
lumber, and three were built, so that 3,300 ft. B. M. of form lumber
were used for molding 20 girders, or 33 ft. B. M. per cubic yard of
concrete. A full size column form contained about 225 ft. B. M. of
lumber, and eight were constructed, so that 1,800 ft. B. M. of form
lumber were used for molding 56 columns, or about 16 ft. B. M. per cubic
yard of concrete.
The following was the cost of erecting a full column form including
lining, plumbing, bracing and yoking, but excluding lumber and original
construction:
1 carpenter, 3 hrs., at $0.25 $0.750
1 helper, 3 hrs., at $0.175 0.525
1 helper, 1 hr., at $0.175 0.175
1-5 boss carpenter, 3 hrs., at $0.30 0.180
------
Total $1.630
This gives a cost of $7.25 per M. ft. B. M. for erecting column forms.
The cost of erecting a full size girder form including lining, plumbing,
bracing and setting six bolts was as follows:
2 carpenters, 5 hrs., at $0.25 $2.50
2 helpers, 5 hrs., at $0.175 1.75
2 laborers, ½ hr., at $0.15 0.15
¼ boss carpenter, at $0.30 0.375
------
Total $4.775
This gives a cost of $4.35 per M. ft. B. M. for erecting girder forms.
The reinforcement was erected inside the forms for both columns and
girders. The cost of erection for one column was:
2 laborers, 4 hrs., at $0.15 $1.20
1/3 foreman, 4 hrs., at $0.225 0.30
-----
Total $1.50
This gives a cost of about 0.22 cts. per pound for erecting column
reinforcement, including the bending of the horizontal ties or hoops.
The girder reinforcement was erected by piece work at a cost of $1.80
per girder--or about 0.08 ct. per pound.
The concrete used was a 1-6 mixture of Portland cement and crusher run
stone all passing a ½-in. sieve and 10 per cent. passing a 200 mesh
sieve. No trouble was had in handling this fine aggregate. It was mixed
in a Ransome mixer, elevated so as to deliver the batches into cars on a
standard gage track. This track ran between the base slabs on which the
molding was done. Each car held about 3 cu. yds. and discharged through
a side gate and spout directly into the forms, the mixture being made so
wet that it would flow readily. The company used its own cement and
stone for concrete and charged up the cement at $1 per barrel and the
stone at 60 cts. per cubic yard. At these prices, and assuming that a
cubic yard of concrete of the mixture above described would contain
about 1.25 bbl. of cement and 1.5 cu. yd. of stone, we have the
following cost of materials per cubic yard of concrete:
1.25 bbls. of cement, at $1 $1.25
1.5 cu. yds. stone, at $0.60 0.90
-----
Total $2.15
The actual cost of mixing the concrete and delivering it to the cars was
as follows:
Item. Per cu. yd.
1 foreman, at 20 cts per hour $0.0300
3 men shoveling stone, at 15 cts. per hour 0.0675
3 men filling hopper, at 15 cts. per hour 0.0675
1 man bringing cement, at 18 cts. per hour 0.0225
1 man dumping cement, at 15 cts. per hour 0.0225
9 h.p., at ½ ct. per h.p. hour 0.0450
Superintendence, repairs, etc. 0.0270
-------
Total $0.2820
The cost of hauling the concrete from mixer to forms ran about 2.7 cts.
per cubic yard, so that we have a cost for concrete in place of:
Concrete materials, per cu. yd. $2.150
Mixing concrete, per cu. yd. 0.281
Hauling concrete, per cu. yd. 0.027
------
Total cost, per cu. yd. $2.458
The cost, then, per column or girder molded, assuming that it was
necessary to erect a full form, was about as follows:
Columns:
2 cu. yds. concrete, at $2.46 $ 4.92
675 lbs. steel, at 2½ cts. 16.77
Erecting steel, at 0.22 ct. per lb. 1.50
Erecting forms 1.63
------
Total $24.82
Girders:
5 cu. yds. concrete, at $2.46 $12.30
2,260 lbs. steel, at 2½ cts. 56.50
Erecting steel, at 0.08 ct. per lb. 1.80
Erecting forms 4.77
-----
Total $75.37
[Illustration: Fig. 243.--View Showing Method of Hoisting Molded
Columns.]
These figures give a unit cost of $12.41 per cu. yd. for molded columns,
and of $15.07 per cu. yd. for molded girders, The columns were erected
by a Browning locomotive crane, which lifted and carried them to the
work and up-ended them into place. To facilitate lifting the columns
from the molding bed a 1½-in. pipe 8 ins. long was cast into both ends;
pins inserted into these sockets provided hitches for the tackle. The
column was lifted off the molding bed and blocked up, then iron clamps
were attached, one at each end, as shown by Fig. 243. A gang of 1
foreman and 14 men erected from 5 to 7, or an average of 6 columns per
10-hour day. The average wages of the erecting gang were 21 cts. per
hour. The cost then of column erection was (14 × $2.10) ÷ 6 = $5.25 per
column, or $2.63 per cu. yd. of concrete.
[Illustration: Fig. 244.--Sketch Showing Sling for Erecting 50-ft. Roof
Girders.]
The roof girders had 1-in. eye-bolts 24 ins. long cast into them
vertically about 4 ft. from the ends. They were lifted off the molding
bed by tackle by the locomotive crane to these eye-bolts and blocked up
to permit the adjustment of the sling. This sling is shown by the
sketch, Fig. 244, and as will be observed acts as a truss. At first it
was used without the vertical, but the cantilever action of the
unsupported ends caused cracks. The girders were loaded onto cars by the
locomotive crane and taken to the work, where they were hoisted and
placed by a gin pole. The girder erecting gang consisted of 1 foreman
and 14 men, working a 10-hour day at 21 cts. per hour. This gang erected
four girders per day, at a cost of (15 × $2.10) ÷ 4 = $7.87 per girder,
or $1.57 per cu. yd. of concrete.
The cost of girders and columns in place was thus about as follows:
Columns: Per unit. Per cu. yd.
Molding $25.00 $12.50
Erecting 5.25 2.63
------ ------
Totals $30.25 $15.13
Girders:
Molding $75.00 $15.00
Erecting 7.87 1.57
------ ------
Totals $82.87 $16.57
[Illustration: Fig. 245.--View Showing Method of Handling Roof Slabs.]
In this same building the roof was composed of 12×6¼ ft.×4-in. slabs
molded in tiers; a slab was molded and when hard was carpeted with paper
and the form moved up and a second slab molded on top of the first. This
operation was repeated until a tier of slabs had been molded. By molding
each slab with a 3-in. overlap, as shown by Fig. 245, they could be
easily separated by lifting on hooks inserted under the overhanging
ends. Each slab contained 0.925 cu. yd. of concrete and about 116¾ lbs.
of reinforcement. The cost of molding one roof slab, including
materials, forms and labor, was as follows:
Materials: Per slab. Per cu. yd.
1 bbl. cement, at $1 $1.000 $1.081
1.06 tons stone, at $0.60 0.636 0.687
116¾ lbs. steel, at 2¼ cts. 2.647 2.862
------ ------
Total $4.283 $4.630
Forms:
Lumber and making $0.104 $0.112
92 sq. ft. paper, at 33-1/3
cts. per 500 sq. ft. 0.055 0.059
Labor erecting and removing 0.5625 0.608
------- ------
Total $0.7215 $0.779
Mixing, Hauling and Placing:
Mixing $0.222 $0.240
Hauling 0.025 0.027
Placing concrete and steel 0.170 0.183
------ ------
Total $0.417 $0.450
General Expenses:
Housing and heating $0.700 $0.757
Superintendence, power, etc. (10%) 0.612 0.661
------ ------
Total $1.312 $1.418
Grand totals $6.7335 $7.277
The roof slabs were raised from the casting beds by means of the
locomotive crane and hooks, as shown by Fig. 245, and loaded onto cars;
eight slabs made a carload. The cars were run to the work, where the gin
poles hoisted the slabs one at a time to cars running on a track built
on timbers laid on top of the roof girders. A small derrick on rafters
picked the slabs from the hand car and set them in place. A gang of 15
men erected from 18 to 20 slabs per 10-hour day. With average wages at
21 cts. per hour the cost of erection was (15 × $2.10) ÷ 19 = $1.66 per
slab, or $1.79 per cu. yd. The total cost of slabs in place was thus:
Item. Per slab. Per cu. yd.
Molding $6.73 $7.27
Erecting 1.66 1.79
----- -----
Total $8.39 $9.06
In studying these cost figures their limitations must be kept in mind.
Because of the character of the available data quantities had in several
cases to be estimated from the working drawings. The cost of lumber for
and of framing column and girder forms is not included, but this is
partly balanced at least by the assumption that each form was erected
complete for each column and girder, which was not the case, as has been
stated. Cost of plant is not included nor is cost of shoring the columns
until girders and struts were placed, nor are several minor
miscellaneous items.
~HOLLOW BLOCK WALL CONSTRUCTION.~--Three general processes of molding
hollow wall blocks of concrete are employed: (1) A dry mixture is
heavily tamped into a mold and the block is immediately released and set
aside for curing; (2) a liquid is poured into molds, where the block
remains until hard: (3) a medium wet mixture is compressed into a mold
by hydraulic presses or other means of securing great pressure. The
molds used may be simple wooden boxes with removable sides or mechanical
molds of comparative complexity. Generally mechanical molds, or concrete
block machines as they are commonly called, will be used. There are a
score or more kinds of block machines all differing in construction and
mode of operation. None of them will be described here, but those
interested may consult "Concrete Block Manufacture" by H. H. Rice or
"Manufacture of Concrete Blocks and Their Use in Building Construction"
by H. H. Rice, Wm. M. Torrance and others.
~Factory Buildings, Grand Rapids, Mich.~--The buildings ranged from one to
four stories high and altogether occupied some 74,000 sq. ft. of ground.
The owners installed a block making plant fully equipped with curing
racks, two Ideal machines, two National concrete mixers, 5 h.p. gasoline
engine, platens, tools and a Chase industrial railway.
The walls were constructed of 24-in. square pilasters of blocks arranged
as shown by Fig. 246, connected by curtain wall belt courses of single
blocks. The blocks were 8×8×16 ins., and after molding the faces were
bush hammered and the edges tooled. The pilasters, consisting of four
blocks laid around an 8×8-in. hollow space, were solidified by pouring
the 8×8-in. space and all but the three outside block cavities with wet
concrete. The interior of the building was of regulation mill
construction, and as the pilasters reached the heights for beam supports
cast iron plates with downward flanges were set in the concrete. These
plates had a cast pin projecting upward to fasten the beam end.
[Illustration: Fig. 246.--Concrete Block Pilaster for a Factory
Building.]
The materials used for the block were Sandusky Portland cement and ¾-in.
bank gravel well balanced from fine to coarse. The blocks were molded
with 1-3 mortar faces, the mortar being waterproofed by a mixture of
Medusa waterproofing compound. All concrete was machine mixed. The men
operating the block machines were paid 1 ct. for each block molded, so
that their pay depended upon the energy with which they worked. The men
handling materials and engaged in handling and curing the blocks were
paid $1.75 per day. The gravel was shoveled from the railway cars onto
the screens and from the screen piles to the mixers. The gang was
organized as follows:
Item. Per day.
8 men handling materials, at $1.75 $14.00
5 men operating molds, at 1 ct. per block 15.00
1 man mixing facing mortar, at $1.75 1.75
2 men loading blocks onto trucks, at $1.75 3.50
2 men unloading blocks from trucks, at $1.75 3.50
3 men sprinkling blocks, at $1.75 5.25
------
Total, 21 men molding and curing blocks $43.00
The average daily run was 1,500 blocks, or 300 blocks per machine.
This output was easily maintained after the gang got broken in;
sometimes it ran higher and sometimes lower, but the average was as
given. The men operating the block machines thus earned $3 each per day.
The labor cost of molding and curing per block was thus 2.87 cts. As the
blocks had about 25 per cent. hollow space, each block 8×8×16 ins.
contained 0.45 cu. ft. of concrete; a cubic yard of concrete, therefore,
made 60 blocks, so that the labor cost of making the blocks was 60 ×
2.87 cts. = $1.72 per cubic yard. This cost does not include foreman's
time, materials, interest, depreciation or general expenses. It was
estimated by the owners that the blocks cost them 9 cts. apiece cured,
or about $5.40 per cubic yard of concrete. This 9 cts. evidently
includes materials and labor alone.
Upon removal from the molds the blocks were loaded onto cars, taken to a
large shed and there unloaded onto shelving arranged to hold five rows
of blocks one above the other, two blocks opposite each other on each
shelf. The blocks were left in the shed 24 to 48 hours to get the
preliminary set, then they were loaded on small cars and taken to the
yard, where they were removed from the cars and stacked. They were
sprinkled every day for six days, being kept covered meanwhile with
oiled cotton cloth. The labor costs given above include molding,
sprinkling and handling the blocks up to this point.
To lay the blocks they were again loaded on cars and run to an elevator
in a wooden tower outside the building. The elevator lifted the car to
the floor on which the blocks were to be used, where it was run off onto
a track reaching the full length of the building. The blocks were
unloaded directly behind the masons. Where the walls were high enough
for scaffolding the blocks were unloaded directly onto the first
scaffold and, when necessary, handed up to the scaffolds above. The
masons employed were regular stone masons receiving the regular scale of
wages of $3.50 per day. The number of blocks laid by each mason was 125
per day in building pilasters and 200 per day in building plain wall.
Sometimes 250 blocks per day per man were laid in plain wall work. The
cost per block of laying above was thus 2.8 cts. pilasters and 1.75 cts.
in plain wall. This cost does not include transporting the blocks from
yard or of handling them to the scaffold behind the masons, nor does it
include the cost of materials and labor for mixing and delivering
mortar.
One of the features of this work was the method of transporting the
blocks by cars. A complete system of tracks was provided covering the
block plant and yard, the building sites and the several floors of the
buildings themselves. All blocks and other materials were transported by
cars running on these tracks, both cars and tracks being of the type
made by the Chase Foundry & Manufacturing Co. of Columbus, Ohio.
~Residence, Quogue, N. Y.~--The following record of methods and cost of
constructing a concrete block residence is furnished by Mr. Noyes F.
Palmer: A mixture of sand and pebbles was had on the site; screening was
necessary merely to sort out the odd size stones. A mixture of 1 cement
and 5 sand was really a 1-2-3 mixture, the 2 being the finest grades of
sand and the 3 being various gravel sizes--none too large, none too
small--so that the proportion was 2/5 fine sand and 3/5 gravel.
The concrete was hand mixed, and as the gravel had always just been
excavated it contained moisture and did not have to be wetted. The sand
and gravel were mixed and turned three or four times and spread out
thin, and the cement was carefully spread over them in a uniform layer.
The mass was then turned three or four times until the eye could detect
no difference in color; that is, each grain large enough for the eye to
discern seemed to be coated with cement. After this dry mixing, water
was added in a fine spray--not a deluge from a pail--but only enough to
moisten the mixture. The mass was then turned three or four times. The
mixture was then shoveled into the mold, no special face mixture being
used, so as to about half fill it, and was then tamped by two men, one
standing on each side of the machine. Altogether three layers of
material were so placed and tamped and then a shovelful of sand and
cement mixture was spread over the top to permit an even "strike-off."
As each block was molded it was carried on the working plate and set
down on skids properly spaced to fit the marks on the plate. This is an
important detail and Mr. Palmer comments on it as follows: "The writer
saw inexperienced men careless about it and who would break the backs of
many blocks by not having the skids properly placed. After the blocks
have been at rest for half an hour commence to spray them with a
revolving garden sprinkler or by carefully wetting with a sprinkling pot
on the center of the block only. The blocks should not be allowed to dry
out for at least ten days after removal from the working plate. The
removal from the working plate can be done the morning after molding and
should never be done before even if the block was made in the morning.
In removing the green block from the skids let there be cones of sand
between the rows of blocks and up-end each working plate so as to let
the end of the block come upon the sand cushion. Don't twist and turn
the block, and to remove the working plate pass a stick through the core
holes in both block and plate so that the plate will not fall when
loosened. A slight rap on the center of the plate will loosen it. As
soon as the blocks are up-ended commence the spraying and soak the sand
underneath the block. It may seem unnecessary to dwell on these points
so long, but barrels of cement and barrels of money have been wasted by
neglecting to supply the hardening block with water. Curing is just as
important as molding in making concrete blocks."
The block construction had been detailed by the architect from cellar to
roof, so that it was known beforehand how many blocks of given size were
to be made. The unit of length was 32 ins.; this afforded fractional
parts of 8 ins., 16 ins. and 24 ins., therefore all openings were in
multiples of 8 ins. Odd sizes were made, by inserting "blanks" in the
mold box, to inches or fractions of an inch if desired. This unit
length was less mortar joints, while the unit of height was 9 ins., or
the same as four ordinary bricks with joints. The floor levels were
calculated in multiples of 9 ins., so that the wall could be finished
all around where the beams were to be seated. This beam course was made
of solid blocks; that is, no cores were used in molding them. With the
machine used no change was required to mold these solid blocks except to
remove the cores. The core holes in the working plate were simply
covered with pieces of tin. The shape of the block was the same and the
same materials were used.
The best record in making blocks for this work was 30 blocks, 8×9×32
ins., in one hour, working six men, three mixing and three on the
machine, and using one barrel of cement for 16 blocks. This was a record
run, however, a fair average being 20 blocks per hour, or 200 per ten
hours, which was the day worked. We have then the cost of making blocks
as follows:
1 foreman, at $2.50 $ 2.50
5 helpers, at $2 10.00
13 barrels cement, at $2 26.00
10 cu. yds. sand and gravel, at $1 10.00
Interest and depreciation on machine 2.00
------
Total for 200 blocks $50.50
This gives a cost per block of $50.50 ÷ 200 = 25¼ cts. The displacement
in the wall of each block is 1.75 cu. ft., or the same as 30 bricks.
The cost of laying blocks is the most uncertain item in the whole
industry. Mr. Palmer states that he has known of instances where it cost
only 5 cts. per block and of other instances where, because of the
difficulty of getting help and its inexperience, it cost 15 cts. per
block. In this particular building one mason and three helpers laid 100
blocks per day. The building had no long walls, but it did have many
turns. The cost of laying, then, was as follows:
1 mason, at $4 $ 4.00
3 helpers, at $2 6.00
-----
Total for 100 blocks $10.00
This gives a cost for laying of 10 cts. per block. We have, then:
Making 2,000 blocks $505
Laying 2,000 blocks 200
----
Total $705
This gives a cost of 35¼ cts. per block for making and laying.
The use of a derrick for laying the blocks proved a considerable item of
economy in this work. This derrick cost $50 and two men could mount and
move it on the floor beams. It had a boom reaching out over the wall and
was operated by a windlass. A plug and feather to fit the center 6-in.
hole in the block was used for hoisting the blocks. By this means blocks
only seven days old were laid without trouble. It may be noted that the
walls were kept drenched with water to make sure that the blocks did not
dry out until they were at least 28 days old. In laying the blocks a
thin lath was used to keep the mortar back about one inch from the face.
This precaution will prevent much labor in cleaning the walls from
mortar slobber.
~Two-Story Building, Albuquerque, N. M.~--The following record of cost of
making 9×10×32-in. hollow blocks in a Palmer machine and of laying 2,000
of them in two-story building walls is given by Mr. J. M. Ackerman. Sand
cost 60 cts. per cu. yd., and cement cost $3 per barrel. Lime cost 30
cts. per bushel. One barrel of cement made 20 blocks, using a 1-4 sand
mixture. In making 2,000 blocks about 100 blocks, or 5 per cent., were
lost by blocks breaking in hauling from yard to building or by cutting
blocks to fit the work. The blocks were molded by piece work for 5 cts
per block, all materials, tools and plant being supplied to the molders.
Three men with one machine made from 100 to 150 blocks per day. The cost
was as follows:
Item. Per block.
Cement, at $3 per bbl. $0.15
Molding, at 5 cts. per block 0.05
Sand, at 60 cts. per cu. yd. 0.03
Carting, yard to building 0.02
Lime and sand for mortar 0.03
Laying in wall 0.10
Loss in making and cutting 0.01
-----
Total $0.39
As each block gave 9 × 32 = 288 sq. ins., or 2 sq. ft., of wall surface,
the cost of the wall per square foot was 19.5 cts. Assuming 40 per cent.
hollow space, each block contained 1 cu. ft. of concrete, which cost 23
cts., or $6.21 per cu. yd., for materials and molding. Blocks in the
wall cost $10.55 Per cu. yd. of concrete.
~General Cost Data.~--The following data are given by Prof. Spencer B.
Newberry. The average weights of three sizes of hollow blocks are as
follows:
Size, ins. P. C. Hollow Space. Weight, lbs.
8×9×32 33-1/3 120
10×9×32 33-1/3 150
12×9×32 33-1/3 180
Costs of materials are assumed as follows:
Item. Per 100 lbs.
Cement, at $1.50 per bbl. $0.40
Hydrated lime, at $5 per ton $0.25
Sand, gravel or screenings, at 25 cts. per ton $0.012
Mixed in batches of 750 lbs., sufficient for six 8-in. or four 12-in.
blocks, the cost of materials per batch and per block will be for a 1-4
mixture as follows:
Item. Per Batch. 8-in. Block. 12-in. Block.
150 lbs. cement $0.60 $0.10 $0.15
600 lbs. sand 0.072 0.012 0.018
------ ------ ------
Total $0.672 $0.112 $0.168
In general a factory producing 600 8-in. blocks per day will require 25
men to operate it. At an average wage of $1.80 per day the following is
considered as a fair estimate of cost:
Item. Per Day. Per Block.
Materials for 600 blocks $ 60 $0.10
25 men, at $1.80 45 0.075
Repairs 10 0.017
Office and miscellaneous 20 0.034
---- ------
Total $135 $0.226
This gives for 8×9×32-in. blocks a cost of about $6.78 per cu. yd. of
concrete for materials and molding or of 11.3 cts. per sq. ft. of face.
Mr. L. L. Bingham gives the following as the average cost per square
foot of face for 10-in. wall from data collected from a large number of
block manufacturers operating in Iowa in 1905:
Cement at $1.60 per bbl. 4.5 cts.
Sand 2.0 cts.
Labor at $1.83 per day 3.8 cts.
---------
Total cost per square foot 10.3 cts.
Assuming one-third hollow space, the cost for materials and molding was
$5.05 per cu. yd. of concrete not including interest, depreciation,
repairs, superintendence or general expenses.
Reading Tips
Use arrow keys to navigate
Press 'N' for next chapter
Press 'P' for previous chapter