Concrete Construction: Methods and Costs by Gillette and Hill
CHAPTER VI.
1185 words | Chapter 50
METHODS AND COST OF MAKING AND USING RUBBLE AND ASPHALTIC CONCRETE.
Two kinds of concrete which vary in composition and character from the
common standard mixtures of cement, sand and broken aggregate are
extensively employed in engineering construction. These are rubble
concrete and asphaltic concrete.
~RUBBLE CONCRETE.~--In constructing massive walls and slabs a reduction in
cost may often (not always) be obtained by introducing large stones into
the concrete. Concrete of this character is called rubble concrete, and
the percentage of rubble stone contained varies from a few per cent. to,
in some cases, over half of the volume. The saving effected comes partly
from the reduction in the cement required per cubic yard of concrete and
partly from the saving in crushing.
The saving in cement may be readily figured if the composition of the
concrete and the volume of the added rubble stones be known. A 1-2½-5
concrete requires according to Table X in Chapter II 1.13 bbls. of
cement per cubic yard. Assuming a barrel of cement to make 3.65 cu. ft.
of paste, we have 3.65 × 1.13 = 4.12 cu. ft. of cement paste per cubic
yard of 1-2½-5 concrete. This means that about 15 per cent. of the
volume of the concrete structure is cement. If rubble stone be
introduced to 50 per cent. of the volume, then the structure has about
7½ per cent. of its volume of cement. It is of interest to note in this
connection that rubble masonry composed of 65 per cent. stone and 35 per
cent. of 1-2½ mortar would have some 11½ per cent. of its volume made up
of cement.
The saving in crushing is not so simple a determination. Generally
speaking, the fact that a considerable volume of the concrete is
composed of what, we will call uncrushed stone, means a saving in the
stone constituent of one structure amounting to what it would have cost
to break up and screen this volume of uncrushed stone, but there are
exceptions. For example, the anchorages of the Manhattan Bridge over the
East River at New York city were specified to be of rubble concrete,
doubtless because the designer believed rubble concrete to be cheaper
than plain concrete. In this case an economic mistake was made, for all
the rubble stone used had to be quarried up the Hudson River, loaded
onto and shipped by barges to the site and then unloaded and handled to
the work using derricks. Now this repeated handling of large, irregular
rubble stones is expensive. Crushed stone as we have shown in Chapter IV
can be unloaded from boats at a very low cost by means of clam shells.
It can be transported on a belt conveyor, elevated by bucket conveyer,
mixed with sand and cement and delivered to the work all with very
little manual labor when the installation of a very efficient plant is
justified by the magnitude of the job. Large rubble stones cannot be
handled so cheaply or with so great rapidity as crushed stone; the work
may be so expensive, due to repeated handlings, as to offset the cost of
crushing as well as the extra cost of cement in plain concrete. On the
other hand, the cost of quarrying rock suitable for rubble concrete is
no greater than the cost of quarrying it for crushing--it is generally
less because the stone does not have to be broken so small--so that when
the cost of getting the quarried rock to the crusher and the crushed
stone into the concrete comes about the same as getting the quarried
stone into the structure it is absurd practice to require crushing. To
go back then to our first thought, the question whether or not saving
results from the use of rubble concrete, is a separate problem in
engineering economics for each structure.
In planning rubble concrete work the form of the rubble stones as they
come from the quarry deserves consideration. Stones that have flat beds
like many sandstones and limestones can be laid upon layers of dry
concrete and have the vertical interstices filled with dry concrete by
tamping. It requires a sloppy concrete to thoroughly embed stones which
break out irregularly. In the following examples of rubble concrete work
the reader will find structures varying widely enough in character and
in the percentages of rubble used to cover most ordinary conditions of
such work.
Where the rubble stones are very large it is now customary to use the
term "cyclopean masonry" instead of rubble concrete. Many engineers who
have not studied the economics of the subject believe that the use of
massive blocks of stone bedded in concrete necessarily gives the
cheapest form of masonry. We have already indicated conditions where
ordinary concrete is cheaper than rubble concrete. We may add that if
the quarry yields a rock that breaks up naturally into small sized
blocks, it is the height of economic folly to specify large sized
cyclopean blocks. Nevertheless this blunder has been frequently made in
the recent past.
[Illustration: Fig. 35.--Diagram Cross-Section of Rubble Concrete Dam,
Chattahoochee River.]
~Chattahoochee River Dam.~--The roll-way portion, 680 ft. long, of the dam
for the Atlanta Water & Electric Power Co., shown in section by Fig. 35,
was built of a hearting of rubble concrete with a fine concrete facing
and a rubble rear wall. The facing, 12 ins. thick of 1-2-4 concrete,
gave a smooth surface for the top and face of the dam, while the rubble
rear wall enabled back forms to be dispensed with and, it was
considered, made a more impervious masonry. The concrete matrix for the
core was a 1-2-5 stone mixture made very wet. The rubble stones, some as
large as 4 cu. yds., were bedded in the concrete by dropping them a few
yards from a derrick and "working" them with bars; a well formed stone
was readily settled 6 ins. into a 10-in. bed of concrete. The volume of
rubble was from 33 to 45 per cent. of the total volume of the masonry.
The 1-2-4 concrete facing was brought up together with the rubble core,
using face forms and templates to get the proper profile. The work was
done by contract and the average was 5,500 cu. yds. of concrete placed
per month.
[Illustration: Fig. 36.--Cross-Section of Barossa Dam of Rubble
Concrete.]
~Barossa Dam, South Australia.~--The Barossa Dam for the water-works for
Gawler, South Australia, is an arch with a radius of 200 ft., and an arc
length on top of 422 ft.; its height above the bed of the stream is 95
ft. Figure 36 is a cross-section of the dam at the center. The dam
contains 17,975 cu. yds. of rubble concrete in the proportions of 2,215
cu. yds. of rubble stone to 15,760 cu. yds. of concrete; thus about 12.3
per cent. of the dam was of rubble. The concrete was mixed by weight of
1 part cement, 1½ parts sand, and a varying proportion of aggregate
composed of 4½ parts 1¼ to 2-in. stone, 2 parts ½ to 1¼-in. stone and 1
Reading Tips
Use arrow keys to navigate
Press 'N' for next chapter
Press 'P' for previous chapter