Concrete Construction: Methods and Costs by Gillette and Hill

CHAPTER VI.

1185 words  |  Chapter 50

METHODS AND COST OF MAKING AND USING RUBBLE AND ASPHALTIC CONCRETE. Two kinds of concrete which vary in composition and character from the common standard mixtures of cement, sand and broken aggregate are extensively employed in engineering construction. These are rubble concrete and asphaltic concrete. ~RUBBLE CONCRETE.~--In constructing massive walls and slabs a reduction in cost may often (not always) be obtained by introducing large stones into the concrete. Concrete of this character is called rubble concrete, and the percentage of rubble stone contained varies from a few per cent. to, in some cases, over half of the volume. The saving effected comes partly from the reduction in the cement required per cubic yard of concrete and partly from the saving in crushing. The saving in cement may be readily figured if the composition of the concrete and the volume of the added rubble stones be known. A 1-2½-5 concrete requires according to Table X in Chapter II 1.13 bbls. of cement per cubic yard. Assuming a barrel of cement to make 3.65 cu. ft. of paste, we have 3.65 × 1.13 = 4.12 cu. ft. of cement paste per cubic yard of 1-2½-5 concrete. This means that about 15 per cent. of the volume of the concrete structure is cement. If rubble stone be introduced to 50 per cent. of the volume, then the structure has about 7½ per cent. of its volume of cement. It is of interest to note in this connection that rubble masonry composed of 65 per cent. stone and 35 per cent. of 1-2½ mortar would have some 11½ per cent. of its volume made up of cement. The saving in crushing is not so simple a determination. Generally speaking, the fact that a considerable volume of the concrete is composed of what, we will call uncrushed stone, means a saving in the stone constituent of one structure amounting to what it would have cost to break up and screen this volume of uncrushed stone, but there are exceptions. For example, the anchorages of the Manhattan Bridge over the East River at New York city were specified to be of rubble concrete, doubtless because the designer believed rubble concrete to be cheaper than plain concrete. In this case an economic mistake was made, for all the rubble stone used had to be quarried up the Hudson River, loaded onto and shipped by barges to the site and then unloaded and handled to the work using derricks. Now this repeated handling of large, irregular rubble stones is expensive. Crushed stone as we have shown in Chapter IV can be unloaded from boats at a very low cost by means of clam shells. It can be transported on a belt conveyor, elevated by bucket conveyer, mixed with sand and cement and delivered to the work all with very little manual labor when the installation of a very efficient plant is justified by the magnitude of the job. Large rubble stones cannot be handled so cheaply or with so great rapidity as crushed stone; the work may be so expensive, due to repeated handlings, as to offset the cost of crushing as well as the extra cost of cement in plain concrete. On the other hand, the cost of quarrying rock suitable for rubble concrete is no greater than the cost of quarrying it for crushing--it is generally less because the stone does not have to be broken so small--so that when the cost of getting the quarried rock to the crusher and the crushed stone into the concrete comes about the same as getting the quarried stone into the structure it is absurd practice to require crushing. To go back then to our first thought, the question whether or not saving results from the use of rubble concrete, is a separate problem in engineering economics for each structure. In planning rubble concrete work the form of the rubble stones as they come from the quarry deserves consideration. Stones that have flat beds like many sandstones and limestones can be laid upon layers of dry concrete and have the vertical interstices filled with dry concrete by tamping. It requires a sloppy concrete to thoroughly embed stones which break out irregularly. In the following examples of rubble concrete work the reader will find structures varying widely enough in character and in the percentages of rubble used to cover most ordinary conditions of such work. Where the rubble stones are very large it is now customary to use the term "cyclopean masonry" instead of rubble concrete. Many engineers who have not studied the economics of the subject believe that the use of massive blocks of stone bedded in concrete necessarily gives the cheapest form of masonry. We have already indicated conditions where ordinary concrete is cheaper than rubble concrete. We may add that if the quarry yields a rock that breaks up naturally into small sized blocks, it is the height of economic folly to specify large sized cyclopean blocks. Nevertheless this blunder has been frequently made in the recent past. [Illustration: Fig. 35.--Diagram Cross-Section of Rubble Concrete Dam, Chattahoochee River.] ~Chattahoochee River Dam.~--The roll-way portion, 680 ft. long, of the dam for the Atlanta Water & Electric Power Co., shown in section by Fig. 35, was built of a hearting of rubble concrete with a fine concrete facing and a rubble rear wall. The facing, 12 ins. thick of 1-2-4 concrete, gave a smooth surface for the top and face of the dam, while the rubble rear wall enabled back forms to be dispensed with and, it was considered, made a more impervious masonry. The concrete matrix for the core was a 1-2-5 stone mixture made very wet. The rubble stones, some as large as 4 cu. yds., were bedded in the concrete by dropping them a few yards from a derrick and "working" them with bars; a well formed stone was readily settled 6 ins. into a 10-in. bed of concrete. The volume of rubble was from 33 to 45 per cent. of the total volume of the masonry. The 1-2-4 concrete facing was brought up together with the rubble core, using face forms and templates to get the proper profile. The work was done by contract and the average was 5,500 cu. yds. of concrete placed per month. [Illustration: Fig. 36.--Cross-Section of Barossa Dam of Rubble Concrete.] ~Barossa Dam, South Australia.~--The Barossa Dam for the water-works for Gawler, South Australia, is an arch with a radius of 200 ft., and an arc length on top of 422 ft.; its height above the bed of the stream is 95 ft. Figure 36 is a cross-section of the dam at the center. The dam contains 17,975 cu. yds. of rubble concrete in the proportions of 2,215 cu. yds. of rubble stone to 15,760 cu. yds. of concrete; thus about 12.3 per cent. of the dam was of rubble. The concrete was mixed by weight of 1 part cement, 1½ parts sand, and a varying proportion of aggregate composed of 4½ parts 1¼ to 2-in. stone, 2 parts ½ to 1¼-in. stone and 1

Chapters

1. Chapter 1 2. CHAPTER I.--METHODS AND COST OF SELECTING AND PREPARING 3. CHAPTER II.--THEORY AND PRACTICE OF PROPORTIONING CONCRETE. 25 4. CHAPTER III.--METHODS AND COSTS OF MAKING AND PLACING 5. CHAPTER IV.--METHODS AND COST OF MAKING AND PLACING 6. Introduction--Conveying and Hoisting Devices--Unloading with Grab 7. CHAPTER V.--METHODS AND COST OF DEPOSITING CONCRETE 8. Introduction--Depositing in Closed Buckets; O'Rourke Bucket; Cyclopean 9. CHAPTER VI.--METHODS AND COST OF MAKING AND USING RUBBLE 10. Introduction--Rubble Concrete: Chattahoochee River Dam; Barossa 11. CHAPTER VII.--METHODS AND COST OF LAYING CONCRETE IN 12. Introduction--Lowering the Freezing Point of the Mixing Water; Common 13. CHAPTER VIII.--METHODS AND COST OF FINISHING CONCRETE 14. Introduction--Effect of Design on Form Work--Kind of Lumber--Finish and 15. CHAPTER X.--METHODS AND COST OF CONCRETE PILE AND PIER 16. Introduction--Molding Piles in Place; Method of Constructing Raymond 17. CHAPTER XI.--METHODS AND COST OF HEAVY CONCRETE WORK 18. Introduction--Fortification Work: Gun Emplacement, Staten Island, N. Y., 19. CHAPTER XII.--METHODS AND COST OF CONSTRUCTING BRIDGE 20. Introduction--Rectangular Pier for a Railway Bridge--Backing for 21. CHAPTER XIII.--METHODS AND COST OF CONSTRUCTING RETAINING 22. Introduction--Comparative Economy of Plain and Reinforced Concrete 23. CHAPTER XIV.--METHODS AND COST OF CONSTRUCTING CONCRETE 24. Introduction--Mixtures Employed--Distribution of Stock Piles--Hints on 25. CHAPTER XV.--METHODS AND COST OF CONSTRUCTING SIDEWALKS, 26. Introduction--~Cement Sidewalks:~ General Method of Construction--Bonding 27. CHAPTER XVI.--METHODS AND COST OF LINING TUNNELS AND 28. Introduction--Capitol Hill Tunnel, Pennsylvania R. R., Washington, D. 29. CHAPTER XVII.--METHODS AND COST OF CONSTRUCTING ARCH 30. Introduction--Centers--Mixing and Transporting Concrete; Cableway 31. Introduction--Box Culvert Construction, C., B. & Q. R. R.--Arch Culvert 32. CHAPTER XIX.--METHODS AND COST OF REINFORCED CONCRETE 33. Introduction--Construction, Erection and Removal of Forms: Column Forms; 34. CHAPTER XX.--METHOD AND COST OF BUILDING CONSTRUCTION 35. Introduction--Column, Girder and Slab Construction: Warehouses, 36. CHAPTER XXI.--METHODS AND COST OF AQUEDUCT AND SEWER 37. Introduction--Forms and Centers--Concreting--Reinforced Conduit, Salt 38. CHAPTER XXII.--METHODS AND COST OF CONSTRUCTING RESERVOIRS 39. Introduction--Small Covered Reservoir--500,000 Gallon Covered Reservoir, 40. CHAPTER XXIII.--METHODS AND COST OF CONSTRUCTING ORNAMENTAL 41. Introduction--Separately Molded Ornaments: Wooden Molds; Iron Molds; 42. Introduction--Drilling and Blasting Concrete--Bench Monuments, Chicago, 43. CHAPTER XXV.--METHODS AND COST OF WATERPROOFING CONCRETE 44. CHAPTER I. 45. CHAPTER II. 46. CHAPTER III. 47. CHAPTER IV. 48. 15. The trestle work was made of 12×12-in. timbers and was approximately 49. CHAPTER V. 50. CHAPTER VI. 51. part 1/8 to ½-in. stone or screenings. The sand was one-half river sand 52. CHAPTER VII. 53. CHAPTER VIII. 54. CHAPTER IX. 55. Chapter XXI. Despite this considerable use of metal for special forms 56. Chapter XIX, showing the reduction in lumber cost coming from using the 57. CHAPTER X. 58. CHAPTER XI. 59. 75. Three shifts were worked, each composed as specified for the guard 60. 84. The scow was loaded with sufficient sand and cement for a day's work 61. CHAPTER XII. 62. CHAPTER XIII. 63. 102. In fastening the forms with ties the choice is usually between long 64. Chapter VIII. 65. CHAPTER XIV. 66. CHAPTER XV. 67. Chapter II we can estimate the quantity of cement required for any given 68. CHAPTER XVI. 69. CHAPTER XVII. 70. 155. The exact construction of the forms for one of the larger slabs is 71. CHAPTER XVIII. 72. CHAPTER XIX. 73. Chapter IV. 74. CHAPTER XX. 75. 3. One full depth side form and the side of girder No. 2 formed the mold 76. CHAPTER XXI. 77. CHAPTER XXII. 78. CHAPTER XXIII. 79. 289. Referring first to the end posts, it will be seen that they were 80. CHAPTER XXIV. 81. CHAPTER XXV.

Reading Tips

Use arrow keys to navigate

Press 'N' for next chapter

Press 'P' for previous chapter