Concrete Construction: Methods and Costs by Gillette and Hill
CHAPTER X.
9823 words | Chapter 57
METHODS AND COST OF CONCRETE PILE AND PIER CONSTRUCTION FOR FOUNDATIONS.
Two general methods of concrete pile construction are available for
engineering work. By one method a hole is formed in the ground by
driving a steel shell or by other special means and this hole is filled
with concrete. By the other method the pile is molded in suitable forms
and after becoming hard is driven as a wood or steel pile is driven.
Piles constructed by the first method may be either plain or reinforced,
but piles constructed by the second method are always reinforced to
strengthen them for handling and driving. Concrete piers for foundation
work are simply piles of enlarged diameter.
~MOLDING PILES IN PLACE.~--Molding piles in place requires the use of
special apparatus, and this apparatus is to a very large degree
controlled by patents. Pile work of this kind is thus generally done by
concerns which control the use of the apparatus employed and the general
contractor can undertake it only by permission of the proprietary
companies. The methods of work followed and the cost of work are thus of
direct interest only as general information.
~Method and Cost of Constructing Raymond Piles.~--The machinery and
processes employed in the construction of Raymond concrete piles are
patented and all piling work by this method is controlled by the Raymond
Concrete Pile Co. As detail costs of construction are not given out by
the company the following figures collected by the authors are subject
to revision. They are believed to be fairly approximate, having in one
case been obtained by personal watch on the work and in the other case
from authentic records of the engineers on the work.
The pile is made as follows: A collapsible steel core 30 ft. long, 20
ins. diameter at the top and 6 ins. diameter at the bottom, encased in
a thin sheet steel shell, is driven into the ground by an ordinary pile
driver. When it has reached the proper depth, a wedge is loosened,
permitting the two sections of the core to come closer together so that
the core can be pulled out of the hole, leaving the steel shell behind
as a casing to prevent the sides from caving in. The shell is made of
No. 20 gage steel, usually in four or more sections, which telescope one
over the other. A nest of sections is slipped over the lower end of the
core as it hangs in the leads, a rope is hitched around the outer
section and the engine hoists away until the sections are
"un-telescoped" and drawn snug onto the core. The rope is then
unfastened and the driving begins. Figure 49 shows the usual pile
driving rig used. The following are examples of pile construction in
actual work:
_Example I._--In this work, for a building foundation in New York City,
the pile driver was mounted on a turntable, the framework of the
turntable in turn resting on rollers traveling on timbers laid on the
ground. The driver was moved along and rotated when necessary by ropes
passing around the winch head of the engine. The driver had 50-ft. leads
and a 3,100-lb. hammer operated by an ordinary friction clutch hoisting
engine. The hammer blow was received by an oak block fitting into a
recess at the top of the steel core. This block was so battered by the
blows that it had to be renewed about every five or six piles driven. A
¾-in. wire rope passing over a 10-in. sheave lasted for the driving of
130 piles and then broke. When the work was first begun the crew
averaged 10 piles per 10-hour day, but the average for the job was 13
piles per day, and the best day's work was 17 piles. The cost of labor
and fuel per pile was as follows:
5 men on driver at $1.75 $ 8.75
2 men handling shells at $1.75 3.50
1 engineman 3.00
6 men mixing and placing concrete 10.50
1 foreman 5.00
Coal and oil 2.50
-------
Total, 13 piles, at $2.55 $33.25
[Illustration: Fig. 49.--Pile Driver Rigged for Constructing Raymond
Concrete Piles.]
Deducting the cost of placing the concrete we get a cost of $1.75 for
driving the cores. The pile, 25 ft. long, 6 ins. at the point and 18
ins. at the head, contains 21¼ cu. ft., or 0.8 cu. yd., of concrete, and
has a surface area of 77 ft. As No. 20 steel weighs 1.3 lbs. per sq.
ft., each shell weighed approximately 100 lbs. The cost per pile may
then be summarized as follows:
1.2 bbls. cement in 0.8 cu. yd., at $1.75 $2.10
0.8 cu. yd. stone at $1.25 1.00
1/3 cu. yd. sand at $1.05 0.35
100 lbs. steel in shell at 3½ cts. 3.50
Labor and fuel as above 2.55
-----
Total per pile (38 cts. per lin. ft.) $9.50
_This cost, it should be carefully noted, does not include cost of
moving plant to and from work or general expenses._
_Example II._--In constructing a building at Salem, Mass., 172
foundation piles, 14 to 37 ft. long, 6 ins. diameter at the point and 20
ins. diameter at the top, were constructed by the Raymond process. The
general contractor made the necessary excavations and provided clear and
level space for the pile driver, braced all trenches and pier holes, set
stakes for the piles and gave all lines and levels. The piles were
driven by a No. 2 Vulcan steam hammer with a 3,000-lb. plunger having a
drop of 3 ft., delivering 60 blows per minute. Figure 49 shows the
driver at work. Sixteen working days were occupied in driving the piles
after the driver was in position. The greatest number driven in one day
was 20, and the average was 11 piles per day. When in position for
driving, the average time required to complete driving was 12 minutes.
The total number of blows varied from about 310 to 360, the average
being about 350. The piles were driven until the penetration produced by
8 to 10 blows equaled 1 in. When in full operation, a crew of 5 men
operated the pile driver. Seven men were engaged in making the concrete
and 5 men working upon the metal shells.
Assuming the ordinary organization and the wages given below, we have
the following labor cost per day:
1 foreman at $5 $ 5.00
1 engineman at $3 3.00
4 laborers on driver at $1.75 7.00
6 laborers making concrete at $1.75 10.50
5 laborers handling shells at $1.75 8.75
------
Total $34.25
As 172 piles averaging 20 ft. in length were driven in 16 days, the
total labor cost of driving, given by the figures above, is 16 × $34.25
= $548, or practically 16 cts. per lineal foot of pile driven.
The concrete used in the piles was a 1-3-5 Portland cement, sand and
1½-in. broken stone mixture. A 20-ft. pile of the section described
above contains about 20 cu. ft. of concrete, or say 0.75 cu. yd. We can
then figure the cost of concrete materials per pile as follows:
0.85 bbl. cement at $1.60 $1.36
0.36 cu. yd. sand at $1 0.36
0.60 cu. yd. stone at $1.25 0.75
-----
Total per pile $2.47
The steel shell has an area of about 72 sq. ft., and as No. 20 gage
steel weighs 1.3 lbs. per sq. ft., its weight for each pile was about 94
lbs. Assuming the cost of coal, oil, etc., at $2.50 per day, we have the
following summary of costs:
Per lin. ft.
of pile.
Labor driving and concreting $0.16
Concrete materials 0.123
94 lbs. steel shell at 3 cts. 0.145
Coal, oil, etc. 0.011
------
Total $0.439
_The cost does not include interest on plant, cost of moving plant to
and from work and general expenses._
[Illustration: Fig. 50.--Sketch Showing Method of Constructing Simplex
Concrete Piles.]
~Method of Constructing Simplex Piles.~--The apparatus employed in driving
Simplex piles resembles closely the ordinary wooden pile driven, but it
is much heavier and is equipped to pull as well as to drive. A 3,300-lb.
hammer is used and it strikes on a hickory block set in a steel drive
head which rests on the driving form or shell. This form consists of a
¾-in. steel shell 16 ins. in diameter made in a single 40-ft. length.
Around the top of the shell a ½-in. thick collar or band 18 ins. deep is
riveted by 24 1-in. countersunk rivets. This band serves the double
purpose of preventing the shell being upset by the blows of the hammer
and of giving a grip for fastening the pulling tackle. The bottom of the
form or shell is provided with a point. Two styles of point are
employed. One style consists of two segments of a cylinder of the same
size as the form, so cut that they close together to form a sort of clam
shell point. In driving, the two jaws are held closed by the pressure of
the earth and in pulling they open apart of their own weight to permit
the concrete to pass them. This point, known as the alligator point, is
pulled with the shell. It is suitable only for driving in firm, compact
soil, in loose soil the pressure inward of the walls keeps the jaws
partly closed and so contracts the diameter of the finished pile. The
second style of point is a hollow cast iron point, 10 ins. deep and 16½
ins. in diameter, having a neck over which the driving form slips and an
annular shoulder outside the neck to receive the circular edge of the
shell. The projected sectional area of this point is 1.4 sq. ft. It is
left in the ground when the form is withdrawn. The form is withdrawn by
means of two 1-in. cables fastened to a steel collar which engages under
the band at the top of the form. The cables pass in the channel leads on
each side over the head of the driver and down in back to a pair of
fivefold steel blocks, the lead line from which passes to one of the
drums of the engine. In this manner the power of the drum is increased
ten times and it is not unusual to break the pulling cables when the
forms are in hard ground. The general method of construction is about as
shown by Fig. 50, being changed slightly to meet varying conditions. The
form resting on a cast iron point is driven to hard ground. A heavy
weight is then lowered into the form to make sure the point is loose.
While the weight is at the bottom of the form a target is placed on its
line at the top of the form, the purpose of which will be apparent
later. The weight is then withdrawn. Given the length of the pile and
sectional area, it is an easy matter to determine the volume of concrete
necessary to fill the hole.
This amount is put into the form by means of a specially designed bottom
dump bucket, which permits the concrete to leave it in one mass,
reaching its destination with practically no disintegration. It will be
noticed that when the full amount of concrete is in the form its surface
is considerably above the surface of the ground. This is due to the fact
that the thickness of the form occupies considerable space that is to be
occupied by the concrete. The weight is now placed on top of the
concrete and the form is pulled. The target previously mentioned now
becomes useful. As the form is withdrawn the concrete settles down to
occupy the space left by the walls of the form. Obviously this
settlement should proceed at a uniform rate, and as it is difficult to
watch the weight, the target on its line further up is of considerable
help. By watching this target in connection with a scale on the leads of
the driver, it can be readily told how the concrete in the form is
acting. As another check, the target, just as the bottom of the form is
leaving the ground should be level with the top of the form. This would
indicate that the necessary amount of concrete has gone into the ground
and that, other conditions being all right, the pile is a good one. In
some grounds where the head of concrete in the form exerts a greater
pressure than the back pressure or resistance of the earth, the concrete
will be forced out into the sides of the hole, making the pile of
increased diameter at that point and necessitating the use of more
concrete to bring the pile up to the required level.
~Method of Constructing Piles with Enlarged Footings.~--A pile with an
enlarged base or footing has been used in several places by Mr. Charles
R. Gow of Boston, Mass., who has patented the construction. A single
pipe or a succession of pipes connected as the work proceeds is driven
by hammer to the depths required. The material inside the shell is then
washed out by a water jet to the bottom of the shell and then for a
further distance below the shell bottom. An expanding cutter is then
lowered to the bottom of the hole and rotated horizontally so as to
excavate a conical chamber, the water jet washing the earth out as fast
as it is cut away. When the chamber has been excavated the water is
pumped out and the chamber and shell are filled with concrete. The
drawings of Fig. 51 show the method of construction clearly. The
chambering machine is used only in clay or other soil which does not
wash readily. In soil which is readily washed the chamber can be formed
by the jet alone. The practicability of this method of construction is
stated by Mr. Gow to be limited to pipe sizes up to about 14 ins. in
diameter.
[Illustration: Fig. 51.--Sketch Showing Method of Constructing Concrete
Piles with Enlarged Footings.]
~Method of Constructing Piles by the "Compressol" System.~--The compressol
system of concrete pile or pillar construction is a French invention
that has been widely used abroad and which is controlled in this country
by the Hennebique Construction Co., of New York, N. Y. The piles are
constructed by first ramming a hole in the ground by repeatedly
dropping a conical "perforator" weighing some two tons. This perforator
is raised and dropped by a machine resembling an ordinary pile driver.
The conical weight gradually sinks the hole deeper and deeper by
compacting the earth laterally; this lateral compression is depended
upon so to consolidate the walls of the hole that they do not cave
before the concrete can be placed. The concrete is deposited loose in
the hole and rammed solid by dropping a pear-shaped weight onto it as it
is placed. The view Fig. 52 shows the "perforator" and the tamping
apparatus at work. Very successful work has been done abroad by this
method.
[Illustration: Fig. 52.--View of Apparatus Used in Constructing
Compressol Piles.]
~Method of Constructing Piers in Caissons.~--For piles or pillars of
diameters larger than say 18 ins. the use of driving shells and cores
becomes increasingly impracticable. Concrete pillars of large size are
then used. They are constructed by excavating and curbing a well or
shaft and filling it with concrete. This construction has been most used
in Chicago, Ill., for the foundations for heavy buildings, but it is of
general application where the sub-soil conditions are suitable. The
method is not patented or controlled by patents in any particular,
except that certain tools and devices which may be used are proprietary.
_General Description._--The caisson method of construction is simple in
principle. A well is dug by successive excavations of about 5 ft. each.
After each excavation of 5 ft. is completed, wood lagging is placed
around the sides and supported by internal steel rings, so that the soft
ground around the excavation is maintained in its former position. The
methods of excavating and removing the soil and of constructing the
lagging are considered in detail further on. The caissons vary in
diameter according to the load; some as large as 12 ft. in diameter have
been sunk, but the usual diameter is 6 ft.; a caisson of 3 ft. in
diameter is as small as a man can get into and work. When the pier goes
to bed rock the caisson is made of uniform diameter from top to bottom,
but where the pier rests on hardpan the bottom portion of the well is
belled out to give greater bearing area. It is customary to load the
piers about 20 tons per square foot.
[Illustration: Fig. 53.--Curbing for Concrete Piers (Usual
Construction).]
_Caisson Construction._--The caisson construction, or more correctly the
form of curbing most commonly used, is that indicated by the sketch,
Fig. 53. The lagging is 2×6 in. or 3×6 in., stuff 5 ft. 4 ins. or 4 ft.
long set vertically around the well and held in place by interior
wrought iron rings. For a 6-ft. diameter caisson these hoops are ¾ by 3
ins.; they are made in two parts, which are bolted together as shown by
Fig. 53. Generally there are two rings for each length of lagging; for
5-ft. lagging they are placed about 9 ins. from each end. In some
cases, however, engineers have specified three rings for the upper
sections in soft clay and two rings for the sections in the hard ground
lower down. The lagging used is not cut with radial edges, but is rough,
square cut stuff; the rings, therefore, take the inward pressure
altogether.
[Illustration: Fig. 54.--Curbing for Concrete Piers (Jackson Patent).]
In some recent work done by the inventor use has been made of the
caisson construction shown by Fig. 54 and patented by Mr. Geo. W.
Jackson. In place of the plain rings a combination of T-beam ribs and
jacks is used; this construction is clearly shown by the drawing. The
advantages claimed for the construction are that it gives absolute
security to the workmen and the work, that the lagging can be jacked
tightly against the outer walls of the well, that the braces form a
ladder by which the workmen can enter and leave the well, and that the
possibility of shifting the bracing easily permits the concrete to be
placed to the best advantage. On the other hand the braces abstruct the
clear working space of the caissons.
[Illustration: Fig. 55.--Layout of Plant for Concrete Pier Construction.
Cook County Court House Foundations.]
_Excavating and Handling Material._--The excavation of the wells is done
by hand, using shovels and picks, and, in the hardpan, special grubs
made by A. J. Pement and George Racky, Chicago blacksmiths. The
excavated material is hoisted out of the well in buckets made by the
Variety Iron Works, of Chicago. For caissons which are not specified to
go to rock it is considered more economical to do the hoisting by
windlass derricks operated by hand. These derricks have four 6×6-in.
legs and a 3×6-in. top piece. When the caissons go to rock the hoisting
is done by power, so-called "cable set-ups" being used in most cases. To
illustrate this method the following account of the foundation work for
the Cook County Court House is given:
The Cook County Court House foundations consist of 126 caissons varying
from 4 ft. to 10½ ft. in diameter and averaging$ 7½ ft. in diameter.
They were sunk to rock at a depth of 115 ft. below street level. The
work involved 22,000 cu. yds. of excavation and the placing in the
caissons of 17,000 cu. yds. of concrete. Over 1,000 piles about 40 ft.
long, that had formed the foundation of the old Court House built in
1875, were removed. These piles were found to be in good condition. The
work was done by the George A. Fuller Co., of Chicago, Ill.,
Contractors, with Mr. Edgar S. Belden Superintendent in Charge. The
details which follow have been obtained from Mr. Belden.
[Illustration: Fig. 56.--Section Showing Arrangement of Hoist for
Concrete Pier Construction.]
The foundation area was 157×375 ft., and was excavated to a depth of 15
ft. below the street surface before the caissons were started. The
caissons, of which there were 126, were arranged in rows across the lot,
there being from six to eight caissons in a row. The arrangement of the
plant for the work is indicated by Fig. 55. One row of caissons formed a
unit. A platform or "stand" was erected over each caisson and carried in
its top a tripod fitted with a "nigger head" operated by a rope sheave.
This arrangement is shown by Fig. 56. An engine on the bank operated by
a rope drive all the tripod sheaves for a row of six or eight caissons.
The arrangement is indicated by Fig. 55. The clay hoisted from the pits
was dumped into 1 cu. yd. hoppers with which the stands were fitted, as
shown by Fig. 56; when a hopper was full it was dumped into a car
running on a 24-in. gage portable track. Side dump Koppel cars of 1 cu.
yd. capacity were used; they dumped their load into an opening connected
with the tracks of the Illinois Tunnel Co., where the material passed
into tunnel cars and was taken to the lake front about one mile away. As
soon as one row of caissons was completed the stands, tripods, etc.,
which were made portable, were shifted to another row. At times as many
as five units were in operation, sinking 40 caissons.
[Illustration: Fig. 57.--Details of Working Platform for Concrete Pier
Construction.
Side Elevation.
End Elevation.
Bottom Plan.
Section.]
Fig. 56 shows the arrangement in detail at one caisson. In this work the
lagging used was 3×6-in. maple, 5 ft. 4 ins. long, and was supported by
3×¾-in. steel hoops. The lagging was matched and dressed. The "nigger
head," as will be seen, is operated by a rope sheave on the same axle.
As stated above, an endless rope drive operated all the "nigger heads"
on a row of caissons. A 26-in. driving sheave was attached to an
ordinary hoisting engine equipped with a governor. The driving rope was
5/8-in. steel. It was wrapped twice around the driving sheave and once
around the "nigger head" sheaves. These latter were 18 ins. in diameter.
For the hoists 1-in. Manila rope was used. The other details, the
bucket, bucket hook, swivel block, etc., are made clear by the drawing.
The platforms, tripods, etc., were of the standard dimensions and
construction adopted by the contractors of the work. Detail drawings of
the standard platform are given by Fig. 57. One of these platforms
contains about 1,000 ft. B. M. of lumber. As will be seen, all
connections are bolted, no nails being used anywhere. A platform can
thus be taken down and stored or shipped and erected again on another
job with very little trouble.
The plant described handled some 22,000 cu. yds. of excavated material
on this work. Work was kept up night and day, working three 8-hour
shifts. It took an average of 35 shifts to excavate one row of caissons.
No figures of the working force or the cost of excavation of this work
are available.
_Mixing and Placing Concrete._--The placing of the concrete in the
excavated wells is done by means of tremies, or, which is more usual, by
simply dumping it in from the top, workmen going down to distribute it.
The manner of mixing the concrete and of handling it to the caisson
varies of course with almost every job. As an example of the better
arranged mixing and handling plants the one used on the Cook County
Court House work may be described. This plant is shown by the sketch,
Fig. 58.
Bins for the sand and stone were built at one side of the lot on the
sloping bank; their tops were level with the street surface and their
bottoms were just high enough to permit their contents to be delivered
by chutes into 1 cu. yd. cars. Wagons dumping through traps in the
platform over the bin delivered the sand and stone. The sketches
indicate the arrangement of the bins and mixer and the car tracks
connecting them. The raw material cars were first run under the stone
bin and charged with the required proportion of stone, and then to the
sand bin, where the required proportion of sand was chuted on top of the
stone. The loaded car was then hauled up the incline and dumped into the
hopper, where cement and water were added. A No. 2½ Smith mixer was used
and discharged into cars which delivered their loads on tracks leading
to the caissons. The same cars and portable tracks were used as had been
used to handle the excavated material. In operation a batch of raw
materials was being prepared in the hopper while the previous batch was
being mixed and while the concrete car was delivering the still previous
batch to the caissons. An average of 40 batches an hour mixed and put
into the caissons was maintained with a force of 25 men. In all some
17,000 cu. yds. of concrete were mixed and deposited.
[Illustration: Fig. 58.--Arrangement of Concrete Making Plant, Concrete
Pier Construction.]
_Cost of Caisson Work._--The following attempt to get at the cost of
caisson work is based largely upon information obtained from Mr. John M.
Ewen, John M. Ewen Co., Engineers and Builders, Chicago, Ill. Mr. Ewen
says:
"My experience has taught me that it is almost impossible to determine
any definite data of cost for this work. This is due to the fact that no
two caisson jobs will average the same cost, notwithstanding the fact
that the cost of material used and the labor conditions are exactly the
same. This condition is due to the great variety in texture of the soil
gone through. For instance, it has come under my experience that in
caissons of the same diameter on the same job it required but fifteen
8-hour shifts to reach bedrock in some of these, while it required as
many as 21 to 25 shifts to reach rock in the others, rock being at the
same elevation. In fact, the digging all the way to rock in some was the
best that could be wished for, while in the others boulders and
quicksand were encountered, and the progress was slower, and the cost
consequently greater.
"Again, we have known it to require eight hours for two men to dig 8
ins. in hardpan in one caisson, while on a job going on at the same time
and on the opposite corner of the street two men made progress of 2 ft.
in 8 hours through apparently the same stuff, the depth of hardpan from
grade being 61 ft. 6 ins. in both instances, and the quality of labor
exactly the same.
"There have been more heavy losses among contractors due to the
unexpected conditions arising in caisson digging than in any other item
of their work, and I predict a loss to some of them that will be serious
indeed if an attempt be made to base future bids for caisson work
entirely upon the data kept by them on past work. If a contractor is
fortunate enough to find the ordinary conditions existing in his caisson
work, and by ordinary conditions I mean few boulders, no quicksand,
ordinary hardpan and no gas, the following items may be considered safe
for figuring caisson work:
"Figure that it will require from 22 to 25 shifts of 8 hours each to
strike bedrock, bedrock being from 90 to 95 ft. below datum, and datum
being 15 ft. below street grade; figure 2 diggers to the shift in all
caissons over 5 ft. in diameter, 45 cts. per hour for each digger;
figure 1 top man at 40 cts. per hour, and 1 mucker or common laborer at
30 cts. per hour for all caissons in which there are two diggers, and 1
top man less if 1 digger is in the caisson, which condition exists
generally in caissons less than 5 ft. in diameter. Add the cost of
5/8-in. cable, tripods, sheaves, 1-in. Hauser laid line, nigger heads,
ball-bearing blocks, etc., for rigging of the job. Lagging, which is 2×6
ins. and 3×6 ins. hemlock or some hard wood, in length of 5 ft. 4 ins.
and 4 ft., is priced all the way from $20 to $22.50 and $21 to $24.50
per M. ft. B. M., respectively. The price of caisson rings is $2.40 per
100 lbs. The cost of specially made grubs for digging in hardpan is
about $26 per dozen. Shovels are furnished by the diggers themselves in
Chicago, Ill. The cost of temporary electric light is $10 per caisson.
This includes cost of cable, lamps, guards, etc. Add the cost of or
rental of engine or motors for power.
"Some engineers specify three rings to be used to each set of lagging
below the top set until hardpan is reached, then two rings for each of
the remaining sets from hardpan to rock. This is, of course, to insure
against disaster from great pressure of the swelling clay above the
hardpan strata, and may or may not be necessary. These rings are ¾×3
ins. wrought iron.
"For caissons which are not specified to go to rock, it is not
considered economical to rig up cable set-ups, but rather to use
windlass derricks. In this case 1-in. Hauser laid line is used as the
means of hoisting the buckets of clay out of the caisson, as is the case
in cable set-ups, hand power being used on the windlass derricks instead
of steam or electricity. The windlass derricks are made with four legs
out of 6×6-in. yellow pine lumber. The top piece is generally a piece of
3×6-in. lagging. The cost of windlass and boxes is about $35 per dozen.
Hooks for caisson buckets cost 45 cts. each. Caisson buckets cost $8
each.
"With the above approximate units as a basis, I have seen unit prices
given per lineal foot in caisson work which ranged all the way from $12
to $16.50 for 6-ft. diameter caissons, larger and smaller sized caissons
being graded in price according to their size. This unit price included
rings, lagging, concrete, power, light, labor, etc."
From the above data the following figures of cost can be arrived at,
assuming a 6-ft. caisson:
Labor. Per day.
2 diggers in caisson, at $3.60 $ 7.20
1 top man, at $3.20 3.20
1 mucker, at $2.40 2.40
------
$12.80
The depth sunk varies from 3½ to 8 ft. per 8-hour day, depending on the
material. Assuming an average of 4 ft., we have then 4 lin. ft. of
caisson, or 2.8 cu. yds. excavated at a labor cost of $12.80, which is
at the rate of $3.20 per lin. ft., or $4.57 per cu. yd. We now get the
following:
Per lin. ft.
Caisson.
40 ft. B. M. (2×6-in. lagging) at $25 $1.00
60 lbs. iron (¾×3-in. rings) at 2½ c. 1.50
0.7 cu. yd. excavation at $4.57 3.20
0.7 cu. yd. muck hauled away at $1 0.70
0.7 cu. yd. concrete at $5 3.50
Electric light 0.10
------
Total $10.00
If 3×6-in. lagging is used add 50 cts. per lin. ft. of caisson.
~MOLDING PILES FOR DRIVING.~--Piles for driving are molded like columns in
vertical forms or like beams in horizontal forms. European constructors
have a strong preference for vertical molding, believing that a pile
better able to withstand the strain of driving is so produced; such
lamination as results from tamping and settling is, in vertical molding,
in planes normal to the axis of the pile and the line of driving stress.
Vertical molding has been rarely employed in America and then only for
molding round piles. The common belief is that horizontal molding is the
cheaper method. In the ordinary run of work, where comparatively few
piles are to be made, it is probably cheaper to use horizontal molds,
but where a large number of piles is to be made, the vertical method has
certain economic advantages which are worth considering.
[Illustration: Fig. 59.--Plant for Vertical Molding of Concrete Piles.]
Vertical molding necessitates a tower or staging to support the forms
and for handling and placing the concrete; an example of such a staging
is shown by Fig. 59. To counterbalance this staging, horizontal molding
necessitates a molding platform of very solid and rigid construction if
it is to endure continued and repeated use. In the matter of space
occupied by molding plant, vertical molding has the advantage. A tower
40 ft. square will give ample space around its sides for 80 vertical
forms for 12-in. piles and leaves 1 ft. of clear working space between
each pair of forms. The ground area occupied by this tower and the forms
is 1,764 sq. ft. With the same spacing of molds a horizontal platform
at least 25 × 160 ft. = 4,000 sq. ft., would be required for the molds
for the same number of piles 25 ft. long. For round piles, vertical
molding permits the use of sectional steel forms; horizontal forms for
round piles are difficult to manage. For square piles vertical molding
requires forms with four sides; horizontal forms for square piles
consist of two side pieces only, the molding platform serving as the
bottom and no top form being necessary. Thus, for square piles
horizontal molding reduces the quantity of lumber per form by 50 per
cent. The side forms for piles molded on their sides can be removed much
sooner than can the forms for piles molded on end, so that the form
material is more often released for reuse. The labor of assembling and
removing forms is somewhat less in horizontal molding than in vertical
molding. Removing the piles from molding bed to storage yard for curing
requires derricks or locomotive cranes in either case and as a rule this
operation will be about as expensive in plant and labor in one case as
in the other. In the ease and certainty of work in placing the
reinforcement, horizontal molding presents certain advantages, the
placing and working of the concrete around the reinforcement is also
easier in horizontal molding. Mixing and transporting the concrete
materials and the concrete is quite as cheap in vertical molding as in
horizontal molding. If anything, it is cheaper with vertical molding,
since the mixer and material bins can be placed within the tower or
close to one side where a tower derrick can hoist and deposit the
concrete directly into the molds. Car tracks, cars, runways and
wheelbarrows are thus done away with in handling the concrete from mixer
to molds. Altogether, therefore, the choice of the method of molding is
not to be decided off-hand.
~DRIVING MOLDED PILES.~--Driving molded concrete piles with hammer drivers
is an uncertain operation. It has been done successfully even in quite
hard soils and it can be done if time is taken and the proper care is
exercised. The conditions of successful hammer driving are: Perfect
alignment of the pile with the line of stroke of the hammer; the use of
a cushion cap to prevent shattering of the pile-head, and a heavy hammer
with a short drop. The pile itself must have become well cured and
hardened. At best, hammer driving is uncertain, however; shattered piles
have frequently to be withdrawn and the builder is never sure that
fractures do not exist in the portion of the pile that is underground
and hidden. The actual records of concrete pile work given in succeeding
sections illustrate successful examples of hammer driving. The plant
required need not vary from that ordinarily used for driving wooden
piles, except that more power must be provided for handling the heavier
concrete pile and that means must be provided for holding the pile in
line and protecting its head.
Sinking concrete piles by means of water jets is in all respect a
process similar to that of jetting wooden piles. Examples of jetting are
given in succeeding section. In rare cases, driving shells, or sheaths
have been used for driving molded piles.
~Method and Cost of Molding and Jetting Piles for an Ocean Pier.~--In
reconstructing in reinforced concrete the old steel pier at Atlantic
City, N. J., some 116 reinforced concrete piles 12 ins. in diameter were
molded in air and sunk by jetting. The piles varied in length with the
depth of the water, the longest being 34½ ft. Their construction is
shown by Fig. 60, which also shows the floor girders carried by each
pair of piles and forming with them a bent, and the struts bracing the
bents together. In molding and driving the piles the old steel pier was
used as a working platform.
[Illustration: Fig. 60.--Concrete Pile for Pier at Atlantic City, N. J.]
The forms for the piles were set on end on small pile platforms located
close to the positions to be occupied by the piles and were braced to
the old pier. The forms were of wood and the bulb point, the shaft and
the knee braces were molded in one piece. Round iron rods were used for
reinforcement. The concrete was composed of 1 part Vulcanite Portland
cement, 2 parts of fine and coarse sand mixed and 4 parts of gravel 1
in. and under in size. The mixture was made wet and was puddled into the
forms with bamboo fishing rods, which proved very efficient in working
the mixture around the reinforcing rods and in getting a good mortar
surface. The concrete was placed in small quantities; it was mostly all
hand mixed. The forms were removed in from 5 to 7 days, depending on the
weather.
The piles were planned to be sunk by water jet and to this end had
molded in them a 2-in. jet pipe as shown. They were sunk to depths of
from 8 ft. to 14 ft. into the beach sand. Water from the city water
mains at a pressure of 65 lbs. per sq. in. was used for jetting; this
water was furnished under special ordinance at a price of $1 per pile,
and a record of the amount used per pile was not kept. The piles were
swung from the molding platforms and set by derricks and block and fall.
The progress of jetting varied greatly owing to obstructions in places
in the shape of logs, old iron pipes, etc. In some cases several days
were required to get rid of a single pipe. In clear sand, with no
obstruction, a 12-in. pile could be jetted down at the rate of about 8
ft. per hour, working 1 foreman and 6 men. The following is the itemized
actual cost of molding and sinking a 26-ft. pile with bulb point and
knee braces complete:
Cost per
Forms-- pile.
Lumber, 340 ft. B. M. @ $30 $10.20
Labor (carpenters @ $2.50 per day) 12.00
Oil, nails, oakum, bolts, clamps, etc. 1.20
-------
$23.40 $ 3.90
Times used 6
Reinforcement--
275 lbs. of plain ¾-in. steel rods @ 2 cts. per lb. $ 5.50
Preparing and setting, 4/10 ct. per lb. 1.10 6.60
Jet Pipe--
26½ ft. of 2-in. pipe @ 10 cts. per ft. in place. 2.65
Setting Forms--
6 men @ $2.50 per day = $15, set 4 piles 3.75
Material--
90/100 Cu. yds. gravel @ $1.50 per yd. 1.35
45/100 cu. yds. sand @ $1.50 per yd. .67
1.50 bbls. cement @ $1.60 2.40 4.42
Labor--
Concrete and labor foreman 3.00
6 laborers, mixing and placing by hand, $1.75
each 10.50
-------
$13.50 3.38
Average number of piles concreted per day 4
Removing Forms--
4 men @ $2.50 remove and clean in half day 4
columns 1.25
1 man @ $2.25 plastering column with cement
grout (4 per day) .56
Jetting 10 ft. into Sand--
Foreman $ 3.00
4 men, $2.25 each, handling hose and traveler 9.00
-------
$12.00 3.00
Average number of piles jetted per day 4
City water pressure used for jetting @ $1 per pile 1.00
Superintendence @ $5.00 per day 1.25
Caring for trestle, traveler, material, etc. 4.84
-------
Total cost per pile $36.60
The pile being 26 ft. long, the cost in place was $1.41 per foot.
Subtracting the cost of sinking amounting to $7.09 per pile, we have the
cost of a 26-ft. pile molded and ready to sink coming to about $1.10 per
foot. It should be noted that this is the cost for a pile of rather
complicated construction; a plain cylindrical pile should be less
expensive.
~Method of Molding and Jetting Square Piles for a Building
Foundation.~--The foundation covered about an acre. The soil was a
deposit of semi-fluid mud and quicksand overlying a very irregular rock
bottom and encircled by a ledge of rock. The maximum depth of the mud
pocket was 40 ft., and interspersed were floating masses of hard pan.
Soundings were made at the locations of all piles; a ½-in. gas pipe was
coupled to a hose fed by city pressure and jetted down to rock, the
depth was measured, the sounding was numbered and the pile was molded to
length and numbered like the sounding. In all 414 piles were required,
ranging in length from 1½ to 40 ft.; all piles up to 6 ft. were built
in place in wooden forms. The piles were 13 ins. square and were of
1-2½-4 concrete reinforced with welded wire fabric. A tin speaking tube
was molded into each pile at the center. This tube was stopped about 10
ins. from the head and by means of an elbow and threaded nipple
projected through the side of the pile to allow of attaching a pressure
hose. The piles were handled to the pile driver, the hose attached and
water supplied at 100 lbs. pressure by a pump. Churning the pile up and
down aided the driving. A hammer was used to force the piles through the
hard pan layers. A wooden follower was used to protect the pile head. A
2,800-lb. hammer falling 20 ft. did not injure the piles. One pile was
given 300 blows with a 2,800-lb. hammer falling 12 ft., and when pulled
was unbroken. It was found that 30 ft. piles and under could be picked
up safely by one end; longer piles cracked at the center when so
handled. These long piles were successfully handled by a long chain, one
end being wrapped around the pile at the center and the other end
similarly wrapped near the head; the hook of the hoisting fall was
hooked into the loop of the chain and as the pile was hoisted the hook
slipped along the chain toward the top gradually up ending the pile. The
piles weighed 175 lbs. per lin. ft. It was attempted to mold the piles
directly on the ground by leveling it off and covering it with tar
paper, but the ground settled and the method proved impracticable.
~Method of Molding and Jetting Piles for Building Foundations.~--In a
number of foundations Mr. Frank B. Gilbreth has used a polygonal pile,
either octagonal or hexagonal, with the sides corrugated or fluted as
indicated in Fig. 61. In longitudinal section these piles have a uniform
taper from butt to point and have flat points. Each pile is cored in the
center, the core being 4 ins. in diameter at the top and 2 ins. at the
bottom end. On each of the octagon or hexagon sides the pile has a
half-round flute usually from 2½ to 3 ins. in diameter. The principal
object of these flutes or "corrugations" is to give passage for the
escape to the surface of the water forced through the center core hole
in driving the pile. They are also for the purpose of increasing the
perimeter of the pile and thereby gaining greater surface for skin
friction.
The piles are reinforced longitudinally and transversely. On this
particular job the reinforcement was formed with Clinton Electrically
Welded Fabric, the meshes being 3 ins.×12 ins.; the longer dimension
being lengthwise with the pile and of No. 3 wire; the horizontal or
transverse reinforcement being of No. 10 wire. The meshes being
electrically welded together, the reinforcement was got out from a wide
sheet taking the form of a cone. No part of the reinforcement was closer
than 1 in. from the outside of the concrete. In general only sufficient
sectional area of material is put in the reinforcement to take the
tensile stresses caused by the bending action when handling the pile
preparatory to driving; more reinforcement than this only being
necessary when the piles are used for wharves, piers or other marine
structures, where a considerable length of pile is not supported
sidewise or when they are subjected to bending stresses.
[Illustration: Fig. 61.--Cross-Section of Corrugated Reinforced Concrete
Pile.]
_Molding._--The forms for molding the piles are made from 2-in. stuff,
gotten out to the required dimensions, the corrugations being formed by
nailing pieces on the inside whose section is the segment of a circle.
The sides of the octagon are fastened to the ends through which the core
projects some 6 or 8 ins. At times while the molding of the pile is in
progress, the central core is given a partial turn to prevent the
setting of the cement holding it fast and thereby preventing the final
removal.
The stripping of the forms from the piles is usually done from 24 to 48
hours after molding, and from this time on great care is taken that
there is a sufficient amount of moisture in the pile to permit of the
proper action for setting of the cement. This is usually accomplished by
covering the piles over with burlaps and saturating with water from a
hose; the operation of driving the pile not being attempted until the
concrete is at least ten days old.
_Driving._--The operation of driving corrugated concrete piles is
somewhat similar to that for driving ordinary wooden piles by water jet,
but a much heavier hammer with less drop is used. The jetting is
accomplished by inserting a 2-in. pipe within the pile. This pipe is
tapered at the bottom end to 1-in. diameter, forming a nozzle, and the
water pressure used is about 120 lbs. per sq. in. As a rule, this
pressure is obtained by the use of a steam pump which may be connected
with the boiler which operates the pile driver, or with a separate steam
supply. At the upper end of this 2-in. pipe an elbow is placed and a
short length of pipe is connected to this and to the hose from the water
supply.
[Illustration: Fig. 62.--Cushion Cap for Driving Gilbreth Corrugated
Pile.]
As it is not practicable to drop the hammer directly on the head of the
concrete piles, the driving is accomplished by the use of a special cap,
Fig. 62. This cap is about 3 ft. in height and the bottom end fits over
the head of the pile. In one side of this cap is a slot from the outside
to the center, which permits the 2-in. pipe, which supplies the water
jet for driving the pile, to project. The outside of this cap is formed
with a steel shell, the inside has a compartment filled with rubber
packing and the top has a wooden block which receives a blow from the
hammer. In this way the head of the pile is cushioned, which prevents
the blow of the hammer from bruising or breaking the concrete.
During the operation of driving, the water from the jet comes up on the
outside of the pile and carries with it the material which it displaces
in driving. This, with the assistance of the hammer, allows the pile to
be driven in place, and, contrary to what might be supposed, after the
operation of driving when the water has saturated into the ground or
been drained away, this operation puddles the earth around the pile, so
that after a few hours' time the skin friction is much more than it
would be with the pile driven into more compact soil without the use of
a jet.
[Illustration: Fig. 63.--View Showing Method of Fabricating
Reinforcement for a Round Pile with Flattened Sides.]
~Method of Molding and Driving Round Piles.~--In constructing a warehouse
at Bristol, England, some 600 spirally-reinforced piles of the Coignet
type were used. Coignet piles are in section circles with two
longitudinal flat faces to facilitate guiding during driving; this
section is the same as would be found by removing two thin slabs from
opposite sides of a timber pile. The reinforcement consists of
longitudinal bars set around the periphery and drawn together to a point
at one end and then inserted into a conical shoe; these longitudinal
bars are wound spirally with a ¼-in. rod wire tied to the bars at every
intersection. This spiral rod has a pitch of only a few inches, but to
bind it in place and give rigidity to the skeleton it is wound by a
second spiral with a reverse twist and a pitch of 4 or 5 ft. As thus
constructed, the reinforcing frame is sufficiently rigid to bear
handling as a unit. The piles used at Bristol were 14 to 15 ins. in
diameter and 52 ft. long, and weighed about 4 tons gross each. The
mixture used was cement, river sand and crushed granite.
_Molding._--In molding Coignet piles the reinforcement is assembled
complete as shown by Fig. 63 and then suspended as a unit in a
horizontal mold constructed as shown by the cross-section Fig. 64. The
concrete is deposited in the top opening and rammed and worked into
place around the steel after which the opening is closed by the piece
A. After 24 hours the curved side pieces B and C are removed and
the pile is left on the sill D until hard enough to be shifted; a pile
is considered strong enough for driving when about six weeks old.
[Illustration: Fig. 64.--Form for Molding Round Pile with Flattened
Sides.]
_Driving._--Coignet piles at the Bristol work were handled by a
traveling crane. The material penetrated was river mud and they were
driven with a hammer weighing 2 tons gross; in driving the pile head was
encircled by a metal cylinder into which fitted a wooden plunger or
false pile with a bed of shavings and sawdust between plunger and pile
head.
~Molding and Driving Square Piles for a Building Foundation.~--The Dittman
Factory Building at Cincinnati, O., is founded on reinforced concrete
piles varying from 8 to 22 ft. in length. The piles were square in
cross-section, with a 2-in. bevel on the edges; a 16-ft. pile was 10
ins. square at the point and 14 ins. square at the head, shorter or
longer piles had the same size of point, but their heads were
proportionally smaller or larger, since all piles were cast in the same
mold by simply inserting transverse partitions to get the various
lengths. Each pile was reinforced by four ¾-in. twisted bars, one in
each corner, bound together by ¼-in hoops every 12 ins.. The bars were
bent in at the point and inserted in a hollow pyramidal cast iron shoe
weighing about 50 lbs. The concrete was a 1-2-4 stone mixture and the
pile was allowed to harden four weeks before driving. They were cast
horizontally in wooden molds which were removed after 30 hours.
_Driving._--Both because of their greater weight and because of the care
that had to be taken not to shatter the head, it took longer to adjust
and drive one of these concrete piles than it would take with a wooden
pile. The arrangement for driving the piles was as follows: A metal cap
was set over the head of the pile, on this was set the guide cap having
the usual wood deadener and on this was placed a wood deadener about 1
ft. long. The metal cap was filled with wet sand to form a cushion, but
as the pile head shattered in driving the sand cushion was abandoned and
pieces of rubber hose were substituted. With this rubber cushion the
driving was accomplished without material damage to the pile head. The
hammer used weighed 4,000 lbs. and the drop was from 4 to 6 ft. The
blows per pile ranged from 60 up. The average being about 90. In some
cases where the driving was hard it took over 400 blows to drive a
14-ft. pile. An attempt to drive one pile with a 16-ft. drop resulted in
the fracture of the pile.
~Method of Molding and Driving Octagonal Piles.~--The piles were driven in
a sand fill 18 ft. deep to form a foundation for a track scales in a
railway yard. They were octagonal and 16 ins. across the top, 16 ft.
long, and tapered to a diameter of 12 ins. at the bottom. They were also
pointed for about a foot. The reinforcement consisted of four ½-in.
Johnson corrugated bars spaced equally around a circle concentric with
the center of the pile, the bars being kept 1½ ins. from the surface of
the concrete. A No. 11 wire wrapped around the outside of the bars
secured the properties of a hooped-concrete column. The piles were cast
in molds laid on the side. They were made of 1:4½ gravel concrete, and
were seasoned at least three weeks before being driven.
An ordinary derrick pile driver, with a 2,500-lb. hammer falling 18 ft.,
was used in sinking them. A timber follower 6 ft. long and banded with
iron straps at both ends was placed over the head of the pile to receive
directly the hammer blows. The band on the lower end was 10 ins. wide
and extended 6 ins. over the end of the follower. In this 6-in. space a
thick sheet of heavy rubber was placed, coming between the head of the
pile and the follower. Little difficulty was experienced in driving the
piles in this manner, although 250 to 300 blows of the hammer were
required to sink each pile. The driving being entirely through fine
river sand there is every probability that any kind of piles would have
been driven slowly. The heads of the first 4 or 5 piles were battered
somewhat, but after the pile driver crew became familiar with the method
of driving, no further battering resulted and the heads of most of the
piles were practically uninjured.
[Illustration: Fig. 65.--Cross-Section of Chenoweth Rolled Pile.]
[Illustration: Fig. 66.--Diagram Showing Method of Rolling Chenoweth
Pile.]
~Method and Cost of Making Reinforced Concrete Piles by Rolling.~--In
molding reinforced concrete piles exceeding 30 or 40 ft. in length, the
problem of molds or forms becomes a serious one. A pile mold 50 or 60
ft. long is not only expensive in first cost, but is costly to maintain,
because of the difficulty of keeping the long lagging boards from
warping. To overcome these difficulties a method of molding piles
without forms has been devised and worked out practically by Mr. A. C.
Chenoweth, of Brooklyn, N. Y. This method consists in rolling a sheet of
concrete and wire netting into a solid cylinder on a mandril, by means
of a special machine. Fig. 65 is a sketch showing a cross-section of a
finished pile, in which the dotted line shows the wire netting, the
hollow circle is the gas pipe mandril, and the solid circles are the
longitudinal reinforcing bars.
[Illustration: Fig. 67.--Machine for Rolling Chenoweth Piles.]
In making the pile the netting is spread flat, with the reinforcing bars
attached as shown at (a), Fig. 66, and is then covered with a layer of
concrete. One edge of the netting is fastened to the platform, the other
edge is attached to the winding mandril. The winding operation is
indicated by sketch (b), Fig. 66. Fig. 67 shows the machine for
rolling the pile. It consists of a platform and a roll. The platform is
mounted on wheels and is so connected up that it moves back under the
roll at exactly the circumferential speed of the roll; thus the forming
pile is under constant, heavy pressure between the roll and platform.
When the pile has been completely rolled it is bound at intervals by
wire ties; the wire for these ties is carried on spools arranged under
the edge of the platform at intervals of 4 ins. for the first 10 ft.
from the point and of 6 ins. for the remainder of the length. The
binding is done by giving the pile two or three extra revolutions and
then cutting and tying the wire; then by means of a long removable shelf
which contains the flushing mortar, as the pile revolves it becomes
coated on the outside with a covering that protects the ties and other
surface metal. Finally the pile is rolled onto a suitable table to
harden.
An exhibition pile rolled by the process described is 61 ft. long and 13
ins. in diameter. This pile was erected as a pole by hoisting with a
tackle attached near one end and dragging the opposite end along the
ground exactly as a timber pole would be erected. It was also suspended
free by a tackle attached at the center; in this position the ends
deflected 6 ins. Neither of these tests resulted in observable cracks in
the pile. The pile contains eight 1-in. diameter steel bars 61 ft. long,
one 2½-in. pipe also 61 ft. long, 366 sq. ft., or 40.6 sq. yds. ½-in.
mesh 14 B. & S. gage wire netting, and 2 cu. yds. loose concrete. Its
cost for materials and labor was as follows:
Materials--
Gravel, 28.8 cu. ft., at $1 per cu. yd. $ 1.05
Sand, 19.8 cu. ft., at $1 per cu. yd. .73
Cement, 3 bbls., at $1.60 per bbl. 4.80
Netting, 40.6 sq. yds., at 17½ cts. per sq. yd. 7.10
Rods, wire, etc., 1,826 lbs., at 2½ cts. per lb. 45.65
--------
Total $59.33
Mixing 2 cu. yds. concrete, four men one hour, at 15 cts.
per hour $ 0.60
Placing concrete and netting, four men 30 mins., at 15
cts. per hour .30
Winding pile, four men 20 mins., at 15 cts. per hour .20
Removing pile, four men 10 mins., at 15 cts. per hour .10
--------
$1.20
Grand total $60.53
This brings the cost of a pile of the dimensions given to about $1 per
lin. ft.
Reading Tips
Use arrow keys to navigate
Press 'N' for next chapter
Press 'P' for previous chapter