Concrete Construction: Methods and Costs by Gillette and Hill
Chapter IV.
8553 words | Chapter 73
[Illustration: Fig. 218--Bucket Hoist for Building Work (Ransome).]
In constructing a 9-story store at St. Paul, Minn., the concrete was
hoisted by continuous bucket elevators. A lay-out of the construction
plant is shown by Fig. 219. In the alley near the center of the north
side of the building the surface grade was about 6 ft. above the third
story level. A hopper was constructed at grade and provided with two
chutes running to the basement. These chutes discharged on opposite
sides of a vertical partition separating the sand and stone bins, and by
closing either chute at its top by a suitably arranged deflector plate
either sand or stone could be dumped into the same hopper and chuted to
its proper bin. Cement was brought to the work in cars over the tracks
shown and was wheeled from the cars over runways leading to the charging
platforms near each mixer. Other runways connecting with these platforms
provided for wheeling the sand and stone to the mixers. The runways were
placed at the proper height to permit the barrows to be emptied directly
into the charging hoppers. Two Smith mixers were used, located as shown,
and each discharged through a chute into one of the bucket elevator
boots. There were two elevators which were "raised" two stories at a
move as the work progressed. Each elevator discharged into a hopper
holding 1½ batches, and from these hoppers the concrete was fed into
wheelbarrows and wheeled to the forms. The bucket elevators were carried
no higher than the eighth floor. When this floor had been completed the
hoppers were moved down to the fifth floor and the wheelbarrows were
taken to platform elevators and carried to the remaining floors and
roof. Special 4-cu. ft. wheelbarrows were used for handling the
concrete. A maximum of 155 cu. yds. of concrete was mixed, transported
and placed in a 10-hour day with a gang of 28 men.
~Platform Hoists.~--The common builders' hoist or elevator, operating
single or double platforms or cages, needs no special description. The
wheelbarrow, cart or car containing the concrete is run onto the
platform, hoisted and then run to the forms. The chief advantage of this
device in concrete work is that it will handle all classes of material
without any change of carriage or arrangement, it can thus be used for
handling form lumber and reinforcing steel as well as for handling
concrete.
[Illustration: Fig. 219.--Plan of Concrete Mixing and Handling Plant for
9-Story Building.]
~Derricks.~--The use of derricks for hoisting in concrete building work is
limited by the necessity of supporting them independently of the
structure being built; the formwork or the completed concrete work
cannot be utilized to carry derricks during construction. For low
structures the derrick can be set on the ground, but for high buildings
a supporting tower or staging is necessary. The arrangement of such
falsework can be illustrated best by specific examples.
In constructing a 7-story factory at Cincinnati, O., concrete was mixed
on the ground and hoisted by a derrick with an 80-ft. boom mounted on a
tower 55 ft. high. The derrick was located to one side of the building.
For the lower floors the boom swing covered so large an area that the
bucket was dumped at various places, but for the upper floors it was
found more economical to dump buckets into a hopper from which
wheelbarrows were filled. By this plan less time was consumed in placing
the bucket and no tag rope man was required, as the engineman could
swing the boom to a certain point on the wall which would bring the
bucket directly over the hopper. A Smith mixer discharged directly into
derrick buckets, which rested on a track long enough to hold two
buckets. The buckets were filled and emptied alternately by shuttling
the truck and attaching first one and then the other to the derrick.
In constructing an 11-story and basement office building in New York
City a four-legged tower starting from the bottom of the excavation was
erected at about the center of the lot. It was built of timber and
extended upward as the progress of the work demanded until it overtopped
the roof 11 stories above the street. The tower was square in plan and
was divided into stories corresponding approximately to the several
stories of the building. A floor was constructed in the tower at each
story to be used in storing materials. For hoisting a 75-ft. boom was
swung from each leg of the tower, each boom being operated by a separate
engine and having a nominal capacity of 5 tons. The four booms covered
the whole building area and were kept about two stories above the work
by being shifted upward as the work progressed. This arrangement of
derricks was used to handle the steel, lumber and concrete, the building
being built up around the tower, which was so located that its only
interference with the building structure was in the shape of square
holes left in the floor slabs to accommodate the tower legs.
In constructing an 8-story warehouse covering some three acres of ground
in Chicago, Ill., the derrick plant shown by Figs. 220 to 222 was
installed. Some 7,500 tons of reinforcing steel, 125,000 cu. yds. of
concrete and 4,000,000 ft. of form lumber had to be handled.
Incidentally it is worth noting that there were about 120 lbs. of
reinforcing steel and 32 ft. B. M. of form lumber used per cubic yard of
concrete.
The controlling conditions governing the arrangement and character of
the construction plant were as follows: The building, to be built
entirely of reinforced concrete, was 135 ft. high. Its west front
abutted on the river and its south front on the street; at the north
end there was some ground available for plant and along the east front
there was a strip about 20 ft. wide between the building wall and the
main line tracks of a railway. At best, therefore, the area outside of
the building and available for plant and storage was limited, while
inside the building area the contractor was confronted by the insistence
of the architect that an unbroken monolithic construction be obtained as
nearly as possible, by reducing the floor openings for construction work
to a minimum. The sketch plan, Fig. 220, shows the plant designed to
meet the conditions.
To get the large amount of construction material onto the work a side
track was built along the 20-ft. area on the east side of the building
and another was turned into the area at the north end of the building.
These side tracks handled all construction materials coming onto the
work. Over the first there were built two sets of storage bins for sand
and gravel and all concrete materials brought in in carload lots are
unloaded at these two points, as will be described further on. Lumber
for forms and steel for reinforcement shipped in similar manner were
taken by the second siding to the lumber yard and steel mill at the
north end of the building.
[Illustration: Fig. 220.--Plan of Concrete Mixing and Handling Plant for
Large Warehouse Building.]
The raw materials after being worked up in the mixer plants and the saw
and steel mills were distributed over the work by an industrial railway.
The track system of this railway is shown by the dotted lines; it was
located on the basement floor, with rampes leading to the No. 1 mixer
plant and to the saw and steel mill tracks. The two main lines of track
passed close to or under the elevator and stairway shaft openings in the
several floors. This permitted the derrick buckets, lowered and hoisted
through the shafts, to be loaded directly from the car tracks. All mixed
concrete, forms and reinforcing frames were distributed by this railway
to the several shafts and thence hoisted and placed by the derrick
plant.
[Illustration: Fig. 221.--Derrick for Handling Concrete for Large
Warehouse Building.]
The derrick plant consisted of four derricks arranged as shown by the
circles in Fig. 220. The view, Fig. 221 shows the first derrick
installed and illustrates the general construction quite clearly.
Briefly the derrick consisted of a vertical steel-work tower 10 ft.
square and 85 ft. high, within which operated a steel mast 135 ft. high
and carrying an 80-ft. boom connected just above the tower. The mast was
pivoted at the bottom and had rollers turning against a horizontal ring
inside the tower at the top. It was operated by a bull wheel above the
top of the tower, the turning ropes running down inside the mast to the
foot block and thence horizontally to the operating motor. The topping
and hoisting lines also followed this route. The top of the tower was
guyed by four ropes to anchorages in the basement floor. The boom
commanded a circle 170 ft. in diameter and could lift 150 ft. above the
base of the mast. The derrick was operated by a 25-HP. double drum
electric hoist with a derrick swinging spool; this hoist was set on the
basement floor. It will be noted that the guys are below the bull wheel
so that the boom has a clear swing through a complete circle.
As stated above, four of these derricks were employed. Together they did
not cover the entire building area, but by the use of a derrick bucket
so designed that it could be used as a storage bin for feeding
wheelbarrows, it was found possible to keep the number of derricks down
to four.
This derrick plant possessed several advantages of importance. In the
first place the derricks would handle all classes of material--concrete,
forms, steel frames--equally well and could be transferred from one
class of work to the other with practically no delay. In the second
place, for a large area of the building, they handled the material from
the basement direct to the place it was to occupy in the work, and did
it in one operation. Finally they permitted the handling and erection
of the forms and reinforcement in large units. Thus a column form would
be assembled complete at the mill, moved as a unit by car to the proper
shaft and then hoisted and set in place as a unit by the derrick. Girder
forms, floor slab forms, girder and column reinforcing, etc., could be
similarly assembled and handled. The derricks occupied only the area of
four floor panels, the remainder of the area of each floor was left
unobstructed for the work to be done. No materials or supplies needed be
stored on the floors until they were in perfect condition to accommodate
them, and not then, even, so far as the prosecution of form erection and
concreting were concerned.
The sand and gravel for concrete were brought in by bottom or side dump
gondola cars from pits located about 30 miles out on the Chicago,
Milwaukee & St. Paul Ry. The cars were switched onto the main side track
and unloaded under the bins which straddle this track. A receiving
hopper, with its top at rail level and long enough to permit two cars to
be unloaded at once, received the sand or gravel and distributed it
through twelve gate openings onto an 18-in. horizontal belt conveyor 65
ft. long. This conveyor discharged into a second conveyor, 133 ft. long,
which ran up a 22° incline, extending away from the bins and discharged
onto a third conveyor 117 ft. long, which doubled back on a 22° incline
reaching to and over the top of the bins. This third conveyor had two
fixed trippers and an end discharge to distribute its cargo. All three
conveyors were operated by a 35-HP. motor located at the junction of the
two inclined conveyors, both of which were driven from the same shaft. A
chain belt from the idler shaft of the first incline conveyor to the
driving shaft of the horizontal conveyor operated that unit of the
plant. This belt was operated as a cross belt by reversing alternate
links. No manual labor was required to handle the sand and gravel from
the cars to the storage bins.
The mixer arrangement at the two bins differed. At the No. 1 bins the
mixer was located as shown in Fig. 220, close to the bin. Chutes led
directly from the sand and gravel bins to the charging hopper and the
bags of cement were stacked alongside this hopper. The mixer discharged
either directly into the bucket of the first derrick or into cars for
transportation on the railways. At the No. 2 bins a belt conveyor took
the concrete materials down into the basement to a mixer located close
enough to one of the distribution tracks to permit it to discharge
directly into the cars.
[Illustration: Fig. 222.--Special Concrete Bucket for Large Warehouse
Building.]
The derrick buckets by which the concrete was hoisted and handled to the
work were of special construction. A bucket was desired which would
serve several distinct purposes. It must first be able to hold a full
mixer batch of material, since, with the derrick arrangement, economy in
hoisting necessitated hoisting in large units and also because storage
capacity was required of the bucket for wheelbarrow work. The four
derricks did not command the entire area of a floor; there were corners
and other irregular areas outside of the circles covered by the several
booms over which the concrete must be distributed by barrows or carts.
A bucket large enough to supply the barrows, while a second bucket was
being lowered, charged from the mixer and hoisted, was required. In the
second place, a bucket was required whose contents could be discharged
all at once or in smaller portion at will. Finally a bucket was desired
which could be made to distribute its load along a narrow girder form or
in a thin sheet for a floor slab.
To meet these requirements the bucket shown in Fig. 222 was designed. It
held 42 cu. ft., or about 1.55 cu. yds. of concrete. It had a hopper
bottom terminating in a short rectangular discharge spout closed by a
lever operated under cut gate, which could be opened as much or as
little as desired. To the underside of the bucket there was attached a
four-leg frame in which the bucket stood when not suspended. Ordinarily,
that is within the circles commanded by the derricks, the buckets were
discharged suspended and directly into the forms, the character of the
discharge gate permitting a thin sheet to be spread for floor slabs or a
narrow girder or wall form to be filled without spilling or shock. For
wheelbarrow work outside the reach of the derricks the mode of procedure
was as follows: A timber platform about 3 ft. high and having room for
standing two buckets was set just on the edge of the circle commanded by
the derrick boom. Two buckets were used. A full bucket was hoisted and
set on the platform, with its spout overhanging. This bucket served as a
storage bin for feeding the wheelbarrows while the second bucket was
being lowered, charged and hoisted to take its place on the platform,
and serve in turn as a storage hopper.
~PLACING AND RAMMING.~--A wet concrete is usually used in building work
except on occasions, for exterior wall work and except for pitch roof
work, where a wet mixture would run down the slope. Placing and tamping
are therefore, essentially pouring and puddling operations. The pouring
should be done directly from the barrows, carts, or buckets if possible;
dumping onto shoveling boards and shoveling makes an extra operation and
increases the cost by the wages of the shoveling gang. Where shoveling
boards are necessary, take care that they are placed close to the forms
being filled, as it is wasteful of time to carry concrete in shovels,
even for a half dozen paces. Before pouring any concrete, the inside of
the forms should be wet down thoroughly with a hose or sprinkler, if a
hose stream is not available. The final inspection of forms and
reinforcement just before concreting will have made certain that they
are ready for the concrete, so far as line and level of forms and
presence and proper arrangement of the reinforcement are concerned, but
the concrete foreman must watch that no displacement occurs in pouring
and puddling, and must make certain particularly that the forms are
clean.
In pouring columns it is essential that the operation be continuous to
the bottom of the beam or girder. It is also advisable to pour columns
several hours ahead of the girders. Puddling should be thorough, as its
purpose is to work the concrete closely around the reinforcement and
into the angles of the mold and to work out air bubbles. A tool
resembling a broad chisel is one of the best devices for puddling or
slicing. In slab and girder construction, the pouring should be
continuous from bottom of girder to top of slab. Work should never be
stopped-off at horizontal planes. As in columns, careful puddling is
essential in pouring beams. In slab work, the concrete is best compacted
by tamping or rolling. A broad faced rammer should be used for tamping
wet concrete, or a wooden roller covered with sheet steel, weighing
about 250 lbs., and having a 30-in. face.
Theoretically, concreting should be a continuous operation, but
practically it cannot be made so. Bonding fresh concrete to concrete
that has hardened, though it has been done with great perfection by
certain methods as described in Chapter XXIV, must still be held as
uncertain. Ordinarily, at least, a plane of weakness exists where the
junction is made and in stopping off work it should be done where these
planes of weakness will cause the least harm. Experts are by no means
agreed on the best location of these planes, but the following is
recognized good practice. Work once started, pouring a column, should
not be stopped until the column is completed to the bottom of the
girder. For beams and girders; stop concrete at center of girder with a
vertical face at right angles to the girder, or directly over the center
of the columns; in beams connecting with girders, stop concrete at
center of span, or directly over center of connecting girder; stop
always with a vertical face and never with a sloping face, and never
with a girder partly filled. For slabs; stop concrete at center of span,
or directly over middle of supporting girder or beam; stop always with
vertical joints. If for any cause work must be stopped at other points,
than those stated, the fresh concrete and the hardened concrete must be
bonded by one of the methods described in Chapter XXIV.
~CONSTRUCTING WALL COLUMNS FOR A BRICK BUILDING.~--The columns, 12 in
number, were constructed to strengthen the brick walls of a power
station and were built as shown by Figs. 223 and 224, one at a time. The
staging, 50 ft. high and 4×6 ft. in plan, was erected against the wall
which had been shored, a portion of the wall was cut out and forms
erected and the concrete column substituted for the section of wall
which was removed. The staging was then moved into position for another
column.
[Illustration: Fig. 223.--Section of Rectangular Wall Column.]
Two men, with sledge and drill, cut out the brick work amounting to
about 12 cu. yds. for each column in 15 hours, at a cost of about 70
cts. per cu. yd., including removal to the street. The cost of moving
and re-erecting the scaffolding was $2.94 per each move. The character
of the reinforcement is shown by Fig. 223; it was erected as the
concreting progressed, the main bars being in sections 15 ft. long,
spliced with and distanced by side bars and cross bolts at the splices.
[Illustration: Fig. 224.--Staging and Forms Used in Building Column
Shown by Fig. 223.]
The concrete was hand mixed in 6-cu. ft. batches at the foot of the
column, by three men with a fourth turning over and filling the buckets.
The buckets, 12 ins. in diameter and 16 ins. high, were hoisted by a
pulley line arranged as shown and pulled by a mule driven by a man, at
$1 per day for the mule and $1.50 for the man, the cost of hoisting
being 25 to 40 cts. per cu. yd., depending on the rapidity of the man
inside the form. This man tamped the concrete which was emptied from the
buckets by a man on the scaffolding. Each batch raised the level in the
form 15 ins., and between batches a set of ties for the column rods was
placed by the man during the tamping. It took from 1½ to 2 days to
concrete a column of 12 cu. yds. The concrete was a 1-3.8-5.7 limestone
screenings mixture, mixed wet enough to be easily pushed into the forms
and worked around the reinforcement. The form construction is shown by
Fig. 224. The form for one column required 650 ft. B. M. of lumber, and
on an average, each form was used twice. As a matter of fact, the side
strips and outside braces were used three times, while much of the
7/8-in. sheathing was destroyed by being used once. The lumber for
shoring cost $23 per M. ft. B. M., and the light lumber for forms cost
$18 per M. ft. B. M. All lumber was yellow pine. All labor was negro, at
15 cts. per hour; foremen who worked. 22½ cts. per hour. The cost of the
several parts of the work compiled from records furnished by Mr. Keith
O. Guthrie, engineer in charge, was as follows:
Cost per Cost per
Concrete. column cu. yd.
Lumber for forms $ 4.81 $0.40
Setting up and removing forms 11.32 0.95
Cement, 10.17 bbls. at $2.40 24.40 2.03
Sand, 5.87 yds. at $0.90 5.28 0.44
Stone, 8.75 yds. at $1.35 10.94 0.91
Mixing and wheeling 15.73 1.31
Hoisting by mule with driver 4.80 0.40
Handling bucket on scaffold 2.93 0.25
Tamping inside column 2.93 0.25
Painting with grout 3.89 0.32
Clearing away rubbish 1.97 0.16
Rigging, etc. 2.64 0.21
Tools 0.59 0.05
Moving scaffold 2.94 0.25
Moving mix board and rigging hoist 1.62 0.14
------ -----
Total cost of concrete $96.79 $8.07
Cost per Cost cts. per
Reinforcement. column. lb. of bars.
Iron bars, 1,034 lbs. $20.68 $2.00
Drilling iron bars 1.44 0.14
Setting iron bars in place 1.23 0.12
Bolts for splicing and spacing 3.98 0.40
Wire cross ties at 2½, cts. lb. 1.39 0.14
Labor forming 130 cross ties 1.13 0.11
------ -----
Total cost of iron and steel $29.85 $2.91
Summary of Cost.
Per column. Per cu. yd.
Concrete in place $96.79 $8.07
Steel in place 29.85 2.49
Cutting out and removing brick 8.36 0.70
Shoring floors and roof, labor 5.87 0.49
Ditto for lumber used 3 times 3.44 0.29
------- ------
Total $144.31 $12.04
[Illustration: Fig. 225.--Girder Plan for 6-Story Building.]
~FLOOR AND COLUMN CONSTRUCTION FOR SIX-STORY BUILDING.~--The building was
91×112 ft.; 56 columns spaced 16 ft. apart carried the girder system
shown by Fig. 225, which in turn supported a 3½-in. floor slab. The
walls and partitions were not concrete. The following records were kept
by the authors:
_Forms._--The column forms were built as shown by Fig. 226. The boards
were 1½-in. stuff, surfaced on four sides; the yokes were spaced 2 ft.
apart. The 1×6-in. pieces were nailed to the 2×4's with 8-d. nails with
heads left projecting for easy pulling. The girder forms, Fig. 227,
rested on the column forms and on intermediate posts half-way between
columns. These intermediate posts were 3×4's with 4×4×12-in. head blocks
nailed to their tops and wedges under their bottoms. The girder molds
were 1½-in. stuff, and to the side pieces were nailed 1×4-in. cleats;
the bottom and side pieces were connected by 3/8×4-in. lag screws spaced
28 ins. apart. The floor slab stringers were carried on the 1×4-in.
cleats; they were spaced 28 ins. apart and were not nailed; neither were
the 1×6-in. lagging boards nailed to the stringers. The point to be
noted is the design and construction of the forms so that they could be
put together and taken apart easily. The lumber required for forms for
one floor 91×112 ft., or, say, 10,200 sq. ft., was as follows:
Lumber for columns, ft. B. M. 9,000
Lumber for 10×10-in. beams, ft. B. M. 7,600
Lumber for 5×10-in. beams, ft. B. M. 2,700
Intermediate 3×4-in. posts, ft. B. M. 1,000
Lagging, 1×6-in. boards, ft. B. M. 9,000
Stringers, 3×4 ins., ft. B. M. 4,500
------
Total ft. B. M. 33,800
[Illustration: Fig. 226.--Column Form for 6-Story Building.]
In round numbers, we can say that 34,000 ft. B. M. of lumber were used
for 10,000 sq. ft. of floor area, or 3.4 ft. B. M. per 1 sq. ft. Enough
forms were provided to erect two complete floors; the forms for the
lower floor being removed and erected again for the second floor above,
thus using all the lumber three times. With carpenters at $3.50 for 8
hours, the forms were framed ready for erection for $4 per M. ft. B. M.
The lumber framed ready to erect cost them:
Lumber, cost per M. ft. B. M. $26.00
Labor, framing per M. ft. B. M. 4.00
------
Total per M. ft. B. M. $30.00
[Illustration: Fig. 227.--Girder and Slab Forms for 6-Story Building.]
Since the lumber was used three times, $30 ÷ 3 = $10 is the charge
against each 1,000 ft. B. M. needed to encase the concrete on a floor.
There were nearly 34,000 ft. B. M. per floor, hence the cost of lumber
ready for erection was $340 per floor. There were as shown below, 200
cu. yds. of concrete per floor, so that the cost was $340 ÷ 200 = $1.70
per cu. yd. of concrete for forms ready for erection. It took a gang of
5 men 7 days to tear down and carry up the forms for one floor; hence 5
× $2 × 7 = $70 per floor, or practically $2 per M. ft. B. M., or $0.35
per cu. yd. of concrete for taking down and carrying forms two stories.
It took a gang of 10 carpenters 7 days to erect these forms, which at
$3.50 per day was $245 per floor, or $7 per M. ft. B. M., or $1.20 per
cu. yd. of concrete.
_Concrete._--The amount of concrete per floor was as follows:
Floor slab 3½ ins. thick, 10,200 sq. ft. 110 cu. yds.
Beams, 10×10 ins. 40 cu. yds.
Beams, 5×10 ins. 20 cu. yds.
Columns, 15×15 ins. (average) 30 cu. yds.
-----
Total concrete per floor 200 cu. yds.
A concrete mixer, a hoist and a gang of 14 men mixed and placed the
concrete for a floor in 7 days. At $2 per day for labor this gives 14 ×
7 × $2 = $196, or say $1 per cu. yd. for mixing and placing the
concrete.
_Reinforcement._--In each of the 10×10-in. beams there were 4, 1-in.
round rods, 2 straight and 2 bent, and stirrups of 1/8×1-in. straps
spaced 5 ins. apart at columns and 15 ins. at the center. In each
5×10-in. beam there was half as much steel as in a 10×10-in. beam. The
floor slab reinforcement consisted of ¼-in. rods spaced 5 ins. apart and
2 cross-rods in 7-ft. panel. The column reinforcement consisted of 4
rods averaging 1 in. in diameter. In round numbers the amount of steel
required for each floor was, therefore, as follows:
Lbs. steel rods in 10×10-in. beams 16,200
Lbs. steel rods in 5×10-in. beams 4,000
Lbs. stirrups in beams 3,000
Lbs. steel rods in floor slabs 3,800
Lbs. steel rods in columns 1,400
------
Total pounds steel per floor 28,400
This is equivalent to 142 lbs. of steel per cubic yard of concrete, or
about 1 per cent of the total volume of reinforced concrete was steel.
The steel in the beams was about 3 per cent. It required a gang of 5
laborers 7 days at $2.25 per day, to bend and place the steel for each
floor or $86 for labor on 28,400 lbs. of steel. This is equivalent to
0.3 ct. per lb., or 45 cts. per cu. yd. of concrete.
_Summary of Costs._--Summarizing the figures given we have the following
cost per cubic yard of concrete in floors and columns:
Per cu. yd.
142 lbs. steel at 2½ cts. $ 3.55
1 bbl. cement 2.50
1 cu. yd. gravel 1.10
½ cu. yd. sand 0.55
170 ft. B. M. lumber ready to erect at $10 (1/3 of $30) 1.70
170 ft. B. M. torn down at $2 0.35
170 ft. B. M. erected by carpenters at $7 1.20
Mixing and placing concrete 1.00
Shaping and placing steel 0.45
Superintendence 0.25
------
Total $12.65
~WALL AND ROOF CONSTRUCTION FOR ONE-STORY CAR BARN.~--The barn was 50 ft.
wide and 190 ft. long, divided into three rooms by two transverse
partitions and covered with a 4-in. roof having a pitch of ½ in. per
foot. The main walls were 12 ins. thick and the partition walls 10 ins.
thick. The main room 110 ft. long had four car tracks its whole length
with pits under each and a 6-in. reinforced concrete floor slab between.
The floor girders, one under each rail, were 12 ins. square, each
reinforced by three 1¾-in. rods, and were carried on 12×12-in. pillars.
The total yardage of concrete was 874 cu. yds. divided as follows:
Walls and foundations, cu. yds. 614
Pillars and girders in track pits, cu. yds. 44
Reinforced floors, cu. yds. 55
Roof 160
---
Total, cu. yds. 873
A 1-2½-5 concrete was used for floors, roofs and girders and a 1-3-6
concrete for foundations and walls. There were 26½ tons of reinforcing
steel, or 61 lbs. per cu. yd., or 0.45 per cent. of the volume of the
concrete was steel. The wages paid were: Foreman, $2.50; blacksmith, $2;
engineer, $1.75; laborers, $1.50; two-horse team and driver, $3.67;
one-horse team and driver, $2.92; carpenter, $2.25; carpenters worked 9
hours; all others 10 hours.
_Forms._--Carpenters framed and erected forms and common laborers under
foreman carpenter took them down. Lagging was all 2-in. stuff and
uprights 3×4-in. stuff. Props for roof forms were 18-ft. round timber
procured on the job. They were 6 ins. in diameter at the top and cost 50
cts. each, 91 being used. These props are not included in the lumber
listed below, but their cost is included in the costs given. No record
was kept of the number of times the lumber was used, but as 54,643 ft.
B. M. were bought and about twice this much would be needed to enclose
the concrete if used only once, we will assume that all lumber was used
twice. Including the props there were about 60,000 ft. B. M., or 70 ft.
B. M. per cu. yd. of concrete. The cost of the lumber was $1,520.86, and
the cost of labor on the forms was $1,660.60, so that the cost of forms
was:
Item. Per cu. yd. Per M. ft. Per sq. ft.
Lumber $1.74 $13.50 $0.038
Labor 1.90 14.07 0.041
----- ------ ------
Total $3.64 $27.57 $0.079
If the lumber had been used only once the cost per cubic yard would have
been $5.38, and per M. ft. B. M., $41.07.
_Concrete._--A railway track was run the full length of the building
upon what was eventually the fourth track of the car barn and a Ransome
mixer was set up as close to the track as possible allowing a platform
to be built between it and the track. Cars were brought up to this
platform and the materials handled by wheelbarrows direct from cars to
mixer. Both platform and mixer were moved twice as the work progressed.
The concrete was taken by wheelbarrows on runways to the side walls. For
the roof it was hoisted by a horse by means of a mast having an arm with
a three-quarters swing; the barrows were hoisted direct using a hook for
the wheel and two rings for the handles.
The cost of the concrete for materials was:
1.1 bbl. cement at $1.21, per cu. yd. $1.33
¾ ton sand at 75 cts., per cu. yd. 0.55
Aggregate, per cu. yd. 0.88
61 lbs. steel at 1.9 cts., per cu. yd. 1.15
Lumber, 70 ft. B. M. at $27, per cu. yd. 1.74
-----
Total per cu. yd. $5.65
The cost of labor per cubic yard was:
Forms, per cu. yd. $1.900
Mixing, per cu. yd. 0.210
Placing, per cu. yd. 0.310
Finishing, per cu. yd. 0.143
Handling cement, per cu. yd. 0.017
Handling sand, per cu. yd. 0.104
Handling steel, per cu. yd. 0.270
Handling aggregate, per cu. yd. 0.222
Coal, at $4.25 per ton, per cu. yd. 0.010
Foreman, per cu. yd. 0.133
Teams and laying pipe line, per cu. yd. 0.087
------
Total, per cu. yd. $3.406
Summarizing, we have the following cost per cubic yard:
Concrete materials, per cu. yd. $2.76
Labor mixing and placing concrete 1.01
Forms, materials and labor 3.64
Reinforcement, materials and labor 1.42
Fuel, foreman and pipe line labor 0.23
-----
Total, per cu. yd. $9.06
The cost for handling steel, making stirrups, welding, etc., was $8.90
per ton, or 0.45 ct. per lb.
_CONSTRUCTING WALL COLUMNS FOR A ONE-STORY MACHINE SHOP._--The building
was 53×600 ft.; each side wall consisted of 40 columns of channel
section carried on footings of channel section somewhat heavier than
that of the column. The columns were spaced 15 ft. on centers and each
was 7½ ft. wide so that there were 7½ ft. spaces between columns, which
were filled with 3-in. curtain walls extending 7½ ft. above the floor.
Figures 228 and 229 show the column and footing construction. Each
column contained 125 cu. ft., or 4.63 cu. yds. of 1-3-5 1-in. crushed
slag concrete above the footing and the costs given here relate only to
the columns above footings. In the 80 columns there were 370 cu. yds. of
concrete.
_Forms._--A column form is shown by Fig. 230; it contains approximately
1,000 ft. B. M. of lumber. Ten of these forms were used, so that 10,000
ft. B. M. of form lumber were required for 370 cu. yds. of concrete, or
27 ft. B. M. per cu. yd. of concrete. Each column had a superficial area
excluding ends of about 420 sq. ft., so that 420 × 80 = 33,600 sq. ft.
was the superficial area of all the columns and 10,000 ft. B. M. ÷
33,600 sq. ft. = 0.3 ft. B. M., or, say, 1/3 ft. B. M., of form lumber
was used per square foot of concrete enclosed. The cost of the forms per
1,000 ft. B. M., and, therefore, per form, was:
Lumber, 1,000 ft. B. M., at $31.75 $31.75
Labor constructing form 16.39
------
Total per 1,000 ft. B. M. $48.14
[Illustration: Fig. 228.--Channel Section Wall Column for Factory
Building.]
This gives us a cost per cubic yard of concrete for materials and labor
constructing forms of $480 ÷ 370 = $1.30, and per square foot of outside
wall area of $480 ÷ (146 × 80) = 4.1 cts.
The erection and taking down of the forms, owing to the weight of some
of the pieces, was done by means of special derricks. The footings were
brought to within ½ in. of grade and a tenon form of the exact shape of
the channel section of the column was placed on top and filled with
grout to a depth of 1 in. These tenons served as guides in setting the
column forms, and proved to be much quicker and more accurate than
points.
[Illustration: Fig. 229.--Footing for Wall Column Shown by Fig. 228.]
The forms were assembled on the ground and erected by a 35-ft. A-frame
derrick mounted on wheels. The construction is shown by Fig. 231. This
derrick had a capacity of about 4 tons and carried a Ransome friction
crab hoist driven by a 5 h.p. Meitz & Weiss kerosene oil engine. It was
the practice to set a number of forms before filling any. This enabled
the carpenter gang to be plumbing up the first form while the erecting
gang were setting others. The forms had to be very securely guyed and
braced to withstand the impact of the falling concrete. Very little
trouble was had in keeping them well lined up.
[Illustration: Fig. 230.--Form for Molding Wall Column Shown by Fig.
228.]
Two gangs were employed in assembling forms and a portion of the men in
each gang also shaped and placed the reinforcement and placed and tamped
the concrete in the forms so that no exact division of labor is
possible. The organization of these gangs and the wages paid were as
follows:
Derrick Gang:
1 foreman, at 36 cts. per hour $ 3.94
1 crabman, at 30 cts. per hour 2.70
2 topmen, at 27 cts. per hour 4.86
2 bottom men, at 23 cts. per hour 4.14
------
Total per 9-hour day $15.64
Assembling Gang:
1 boss carpenter, at 47 cts. per hour $ 4.23
2 carpenters, at 36 cts. per hour 6.48
2 carpenters, at 30 cts. per hour 5.40
2 carpenters' helpers, at 25 cts. per hour 4.50
4 men forming and placing reinforcing steel
and rethreading bolts, at 23 cts. per hour 8.28
------
Total per 9-hour day $28.89
------
Grand total $44.53
These gangs assembled and erected the molds and concreted 80 columns in
22 working days, including 2 days lost on account of cold weather, so
that 4 columns were completed per day of 9 hours. We can subdivide the
cost as follows:
Item. Per cu. yd.
Erecting forms and concreting $0.81
Assembling forms and reinforcement 1.56
-----
Total $2.37
Charging the 4 men placing reinforcement and rethreading bolts to
forming and placing reinforcement alone we can figure the cost of
fabrication and erection of reinforcement very closely. There were 160
lbs. of reinforcing steel in each column, hence $8.28 ÷ (160 × 4) = 1.3
cts., was the cost per pound of forming and placing it. This includes
handling.
The stripping of the forms was carried on by another gang using a
derrick similar to the first one described, except it could be of
lighter construction as it had to handle only the separate parts of each
form and not the forms assembled. The derrick shown in Fig. 232 was a
33-ft. A-frame, with wheels at the bottom of each leg. It had a friction
crab hoist driven by an electric motor, both of which were fastened to
the derrick frame between the shear legs.
[Illustration: Fig. 231.--Derrick for Erecting Wall Column Forms Shown
by Fig. 230.]
The operation of stripping required only four men and the crabman. The
outside flat panel was removed first, and left leaning up against the
concrete while the inside trough shaped panel was pried loose and
lowered onto the ground with its inside face uppermost. The side panels
being comparatively light, were stripped without the use of the derrick,
and these panels were assembled on the ground with the inside piece. The
derrick then picked up the outside panel again, and placed it in its
proper place. After the bolts were put in place, the assembled form was
moved on rollers to another point in the line of columns where it was
again erected. The arrangement of derricks for erecting and stripping
forms is shown in Fig. 233.
The gang stripping forms was made up as follows:
1 foreman, at 30 cts. per hour $ 2.70
1 crabman, at 27 cts. per hour 2.43
1 topman, at 27 cts. per hour 2.43
2 bottom men, at 23 cts. per hour 4.14
------
Total per 9-hour day $11.70
[Illustration: Fig. 232.--Derrick for Stripping Wall Column Forms Shown
by Fig. 230.]
This gang of five men stripped 4 columns containing 18.52 cu. yds. of
concrete each day, so that the cost of stripping was $11.70 ÷ 18.52 =
62.7 cts. per cu. yd.
_Concrete._--The concrete was mixed in a No. 2 Ransome mixer and
delivered to the work in Ransome concrete carts. These carts were pushed
along a runway which terminated in a slight incline under the derrick so
that their contents could be emptied into the derrick buckets.
The concrete was hoisted in an 8-ft. bottom dump bucket, using the
derrick described above. It was necessary to stir up the concrete
thoroughly with long-handled slicers as it was being deposited in order
to prevent segregation. This expedient combined with a wet mixture and
tight molds was found to overcome this difficulty very effectually.
The gang mixing and wheeling concrete was made up as follows:
1 mixer foreman and engineer at 27 cts. per hour $ 2.43
4 laborers charging mixer at 18 cts per hour 6.48
4 laborers wheeling concrete at 18 cts. per hour 6.48
------
Total per 9-hour day $15.39
This gang mixed and wheeled concrete for four columns, or 18.52 cu.
yds., hence the cost per cubic yard was 82.6 cts.
With cement at $1.60 per bbl., sand at $1 per cu. yd. and slag at $1.10
per cu. yd. the cost of materials per cubic yard of concrete was $3.
[Illustration: Fig. 233.--Arrangement of Derricks for Erecting and
Stripping Forms.]
Summarizing the above figures we have the following cost per cubic yard
of concrete in place:
Item. Per cu. yd.
Concrete materials $3.00
Reinforcing steel 0.73
Forms, lumber and framing 1.30
Forms, erecting and concreting 0.81
Forms, assembling and reinforcement 1.56
Forms, stripping 0.63
Mixing and wheeling concrete 0.83
-----
Total $8.86
~CONSTRUCTING ONE-STORY WALLS WITH MOVABLE FORMS AND GALLOWS FRAMES.~--In
constructing the walls for an 85×30-ft. factory building at Old Bridge,
N. J., Mr. A. E. Budell made use of movable forms and gallows frames to
construct the curtain walls and columns in one piece. Each side wall was
built its full height in successive 50-ft. lengths by depositing the
concrete between two forms which were moved upward as the concreting
progressed. Fig. 234 indicates the mode of procedure. The form was
raised and lowered by means of two gallows frames fitted with blocks and
tackle. A steel cable, with a trolley affixed, extending from one frame
to the other, provided a convenient mode of hoisting material to the
form, and the gallows frames took the place of ladders for climbing onto
the structure. No scaffolding whatever was used and only one man was
required overhead to dump the buckets and tamp the concrete into place.
[Illustration: Fig. 234.--Gallows Frame Supporting Wall Form Panels for
One-Story Building.]
[Illustration: Fig. 235.--Details of Wall Form Panel for One-Story
Building.]
The two walls were carried up simultaneously, one form being shifted
into place and filled while the other was left in place until the
concrete was sufficiently hard. It was found that 18 hours was amply
sufficient to allow the concrete to set hard, after which the form was
removed and lifted to a higher level. Thus the men were continuously
engaged in lifting and filling first one form and then the other. The
average length of time required to remove, raise and fill one form was 5
to 6 hours. Thus, two forms could be raised and filled almost every day.
The construction of the forms and of the gallows frames is shown by
Figs. 234 and 235. The cost of one set of forms and gallows frames was
as follows:
320 ft. B. M. of 2×10 in.×10 ft. plank at $34 $ 10.88
150 ft. B. M. of 3×4 in.×16 ft. spruce at $33 5.25
135½ ft. B. M. 1×8 in. yellow pine at $30 4.08
335 ft. B. M. 1¼×6 in. spruce at $33 11.05
4 posts 6×8 in.×26 ft. = 416 ft. B. M. at $30 12.48
4 sills 6×8 ins.×16 ft., 2 caps 6×6 ins.×9 ft.,
4 braces 6×6 ins.×16 ft. = 490 ft. B. M. at $30. 14.70
3 pieces 3×10 ins.×20 ft. = 150 ft. B. M. at $30 4.50
-------
Total lumber (1,996.5 ft. B. M.) $ 62.94
Accessories:
Bolts for trussing, 675 lbs. at 2 cts. $ 13.50
Iron guy rope and clips 7.00
Blocks 8.00
One coil of ¾-in. rope 28.00
-------
Total accessories $ 56.50
Labor making one outfit:
2 men, 8 days, at $2.75 per 9 hrs. $ 44.00
-------
Grand total $163.44
This sum covered the cost of forms for one side of the building 85 ft.
long and containing 150 cu. yds. of concrete, hence the cost of forms
was in round figures $1.10 per cu. yd. of concrete. Each cubic yard of
concrete required 1,997 ÷ 150 = 13-1/3 ft. B. M. of form lumber.
The concrete was a 1-2½-4½ mixture. A careful record for 15 days, showed
an average of 2.8 cu. yds. of concrete placed in 6 hours by a gang of
6.3 men. From this we can figure the cost of concrete in place to be
about as follows:
2.8 cu. yds. concrete at $3 for materials $ 8.40
6.3 men 6 hours at 15 cts. 5.67
1 foreman 6 hours at $4 per day 2.00
------
Total per cu. yd. $16.07
Thus the cost of concrete in place was $16.07 ÷ 2.8 = $5.73 per cu. yd.
Adding the cost of forms we get $5.73 + $1.10 = $6.83 per cu. yd. as the
cost for labor and materials in constructing forms and mixing and
placing concrete.
[Illustration: Fig. 236.--Detail of Column and Cantilever Column Footing
for Four-Story Garage.]
Offsets and molding decorations were easily made, although they were
quite numerous on the building in question, at least more so than would
ordinarily be the case in mill building construction. The offset of 1
ft. at every column was made very readily by sliding wooden shoulder
pieces into place on the inner face of the form, which pieces in turn
received 2-in. faced planking, the latter being slid into place from
above. Thus the entire system was collapsible and small alterations were
easily made whenever the form was shifted. Flat surfaces or offsets
could be obtained at will by either removing or setting in the shoulder
pieces. Molding effects were made on the front face of the wall by
tacking molding strips to the form wherever necessary. The entire work
was done with common labor and the finished building presented a smooth,
homogeneous surface which required very little dressing.
[Illustration: Fig. 237.--Details of Cantilever Girders for Mezzanine
Floor for Four-Story Garage.]
~FLOOR AND ROOF CONSTRUCTION FOR FOUR-STORY GARAGE.~--The building was
53×200 ft., and 4 stories high, with provision for 2 additional stories
in the design of footings and columns. Two rows of wall columns
connected by transverse girders carrying the floor and roof slabs made a
comparatively simple construction, except for a mezzanine floor carried
on cantilever beams and except for the use of cantilever footings;
these two special details are shown by Figs. 236 and 237. The amount of
concrete in the building was 1,910 cu. yds., distributed as follows:
Cu. yds.
Footings, reinforced 190
Columns, reinforced 450
Floors and roof, reinforced 1,100
Floor on ground, not reinforced 170
-----
Total 1,910
The amount of reinforcing metal used was 237 tons, distributed as
follows:
Item. Tons. Lbs. per cu. yd.
Footings 42 442
Columns 20 90
Floors and roof 175 318
--- ---
Total and average 237 272
This is equivalent to 2 per cent. of steel in 1,910 - 170 = 1,740 cu.
yds.
_Forms._--The total area of concrete covered by forms (1,740 cu. yds.)
was 94,000 sq. ft., distributed as follows:
Footings, sq. ft. 4,000
Columns, sq. ft. 20,000
Floors and girders, sq. ft. 70,000
------
Total, sq. ft. 94,000
For the work 50,000 ft. B. M. of old lumber was used and 170,000 ft. B.
M. of new lumber was bought, the cost being as follows:
50 M. ft. B. M. at $13 per M. $ 650
170 M. ft. B. M. at $26 per M. 4,420
------
220 M. ft. B. M. at $23 $5,070
This is equivalent to 126 ft. B. M. per cu. yd. of concrete. New forms
were made for each floor except the sides of the girder molds which were
re-used so far as they would fit, but the roof forms were made from
lumber used for the floors. In all no more than 20 per cent of the form
lumber was used a second time. In round figures new lumber was required
for 80,000 sq. ft. of concrete; this gives a cost for lumber of 6.4 cts.
per sq. ft. The construction of the column and floor forms is shown by
Fig. 238. A force of 15 carpenters at $4.40 per day under a foreman at
$35 per week erected and tore down forms; the carrying was done by
laborers at $1.70 per day working under a foreman at $35 per week;
carpenters worked an 8-hour and laborers a 10-hour day. Forms for one
floor were framed and erected in 8 to 10 days. The cost of forms for
1,740 cu. yds. and 80,000 sq. ft. of concrete and per M. ft. B. M. was
as follows:
Item. Per cu. yd. Per sq. ft. Per M. ft.
Lumber $2.90 $0.064 $23.00
Framing, erecting and removing. 2.00 } 15.67
} 0.057
Handling lumber 1.10 } 8.70
----- ------ ------
Totals $6.00 $0.121 $47.37
[Illustration: Fig. 238.--Column and Floor Forms for Four-Story Garage.]
The lumber had a considerable salvage value which is not allowed for in
the above figures.
_Concrete._--The concrete was a Portland cement, ¾-in. trap rock
mixture, mixed wet in two Chicago Improved Cube Mixers equipped with
charging buckets. The mixers were located on the ground floor, one at
the rear and one at the front of the building, both discharging directly
to a hoist. With a gang of 30 men at $1.70 per 10-hour day under a
foreman at $35 per week a floor was concreted in 2 days, the columns
being concreted the first day and the floor being concreted the second
day. The labor cost for mixing and placing concrete and for fabricating
and setting reinforcement was as follows:
Item. Per cu. yd.
Mixing and placing concrete $1.95
Erecting and setting steel 2.05
-----
Total $4.00
The cost of concreting includes the cost of granolithic surface for the
floor slabs. The girder reinforcement was made up into unit frames and
the frames were set as a unit, horses set over the molds being used to
suspend and lower them into place. The cost of $2.05 per cu. yd. is
equivalent to ¾ ct. per lb. Summarizing, we have the following cost for
materials and labor on forms and for labor mixing and placing concrete
and reinforcement:
Per cu. yd.
Lumber for forms $ 2.90
Labor on forms 3.10
Labor on concrete 1.95
Labor on steel 2.05
-----
Total $10.00
This $10 total does not include the cost of the concrete nor of the
steel.
Reading Tips
Use arrow keys to navigate
Press 'N' for next chapter
Press 'P' for previous chapter