Concrete Construction: Methods and Costs by Gillette and Hill
CHAPTER XII.
7981 words | Chapter 61
METHODS AND COST OF CONSTRUCTING BRIDGE PIERS AND ABUTMENTS.
The construction of piers and abutments for bridges is best explained by
describing individual examples of such work. So far, in America, bridge
piers have been nearly always of plain concrete and of form and section
differing little from masonry piers; where reinforcement has been used
at all it has consisted of a surface network of bars introduced chiefly
to ensure monolithic action of the pier under lateral stresses. In
Europe cellular piers of reinforced concrete have been much used. Plain
concrete abutments differ little in form and volume from masonry
abutments. Reinforced concrete abutments are usually of L-section with
counterforts bracing the upright slab and bridge seat to the base slab.
Form work for reinforced abutments is somewhat complex; that for plain
abutments and piers is of simple character, the only variations from
plain stud and sheathing construction being in the forms for moldings
and coping and for cut-waters. For piers of moderate height the form is
commonly framed complete for the whole pier, but for high piers it is
built up as the work progresses by removing the bottom boards and
placing them at the top. Opposite forms are held together by wire ties
through the concrete. Movable panel forms have been successfully
employed, but they rarely cheapen the cost much. Sectional forms, which
can be shifted from pier to pier where a number of piers of identical
size are to be built, may frequently be used to advantage. An example of
such use is given in this chapter.
Derricks are the recognized appliances for hoisting and placing the
concrete in pier work; they are the only practicable appliance where the
pier is high and particularly where it stands in water and mixing barges
are employed. For abutment work and land piers of moderate height
derricks and wheelbarrow or cart inclines are both available and where
much shifting of the derricks is involved the apparently more crude
method compares favorably in cost.
The methods of placing concrete under water for pier foundations are
described in Chapter V, and the use of rubble concrete for pier
construction is illustrated by several examples in Chapter VI. The
following examples of pier and abutment construction cover both large
and small work and give a clear idea of current practice.
[Illustration: Fig. 93.--Pier and Cofferdam for a Railway Bridge.]
~COST OF CONSTRUCTING RECTANGULAR PIER FOR A RAILWAY BRIDGE.~--This pier,
Fig. 93, was built in water averaging 5 ft. deep. The cofferdam
consisted of triple-lap sheet piling, of the Wakefield pattern, the
planks being 2 ins. thick, and spiked together so as to give a cofferdam
wall 6 ins thick. The cofferdam enclosed an area 14×20 ft., giving a
clearance of 1 ft. all around the base of the concrete pier, and a
clearance of 2 ft. between the cofferdam and the outer edge of the
nearest pile. The cofferdam sheet piles were 18 ft. long, driven 11 ft.
deep into sand, and projecting 2 ft. above the surface of the water.
The concrete base resting on the foundation piles was 12×18 ft. The
concrete pier resting on this base was 7×13 ft. at the bottom, and 5×11
ft. at the top. The pier supported deck plate girders. There were 100
cu. yds. of concrete in the pier and base.
The cost of this pier, which is typical of a large class of concrete
pier work, has been obtained in such detail that we analyze it in
detail, giving the costs of cofferdam construction and excavation as
well as of mixing and placing the concrete.
Setting up and taking down derrick and platform:
4 days foreman at $5.00 $ 20.00
¾ days engineman at $3.00 2.25
¾ days blacksmith at $3.00 2.25
¾ days blacksmith helper at $2.00 1.50
22 days laborers at $2.00 44.00
-------
Total $ 70.00
Cofferdam--
7 days foreman at $5.00 $ 35.00
4 days engineman at $3.00 12.00
38 days laborers at $2.00 76.00
1 ton coal at $3.00 3.00
-------
Total labor on 7,900 ft. B. M. at $16.00 $126.00
7,900 ft. B. M. at $20.00 158.00
-------
Total for 58 cu. yds. excavation $284.00
Wet Excavation--
1.8 days foreman at $5.00 $ 9.00
1.5 days engineman at $3.00 4.50
9 days laborers at $2.00 18.00
½ ton coal at $3.00 1.50
-------
Total labor on 58 cu. yds. at 57c. $ 33.00
Foundation Piles--
960 lin. ft. at 10c $ 96.00
4 days setting up driver and driving 24 piles at $20 per
day for labor and fuel 80.00
-------
Total $176.00
Concrete--
100 cu yds. stone at $1.00 $100.00
40 cu. yds. sand at $0.50 20.00
100 bbls. cement at $2.00 200.00
5 days foreman at $5.00 25.00
50 days laborers at $2.00 100.00
5 days engineman at $3.00 15.00
2 tons coal at $3.00 6.00
-------
Total, 100 cu. yds. at $4.66 $466.00
8 days carpenters at $3.00 24.00
2,400 ft. B. M. 2-in. plank at $25.00 60.00
1,000 ft. B. M. 4×6-in. studs at $20.00 20.00
Nails, wire, etc 2.00
-------
Total forms for 100 cu. yds. at $1.06 $106.00
Summary--
Setting up derrick, etc. $ 70.00
Cofferdam (7,900 ft. B. M.) 284.00
Wet excavation (58 cu. yds.) 33.00
Foundation piles (24) 176.00
Concrete (100 cu. yds.) 466.00
Forms (3,400 ft. B. M.) 106.00
---------
Total $1,135.00
Transporting plant 20.00
20 days rental of plant at $5.00 100.00
---------
Total cost of pier $1,252.00
Regarding the item of plant rental, it should be said that the plant
consisted of a pile driver, a derrick, a hoisting engine, and sundry
timbers for platforms. There was no concrete mixer. Hence an allowance
$5 per day for use of plant is sufficient.
It will be noted that no salvage has been allowed on the lumber for
forms. As a matter of fact, all this lumber was recovered, and was used
again in similar work.
Referring to the cost of cofferdam work, we see that, in order to
excavate the 58 cu. yds. inside the cofferdam, it was necessary to spend
$284, or nearly $5 per cu. yd. before the actual excavation was begun.
The work of excavating cost only 57 cts. per cu. yd., but this does not
include the cost of erecting the derrick which was used in raising the
loaded buckets of earth, as well as in subsequently placing the
concrete. The sheet piles were not pulled, in this instance, but a
contractor who understands the art of pile pulling would certainly not
leave the piles in the ground. A hand pump served to keep the cofferdam
dry enough for excavating; but in more open material a power pump is
usually required.
The above costs are the actual costs, and do not include the
contractor's profits. His bid on the work was as follows:
Piles delivered 12 cts. per ft.
Piles driven $5 each
Cofferdam $37 per M.
Wet excavation $1.00 per cu. yd.
Concrete $8.00 per cu. yd.
In order to ascertain whether or not these prices yielded a fair profit,
it is necessary to distribute the cost of the plant transportation and
rental over the various items. We have allowed $120 for plant
transportation and rental, and $70 for setting up and taking down the
plant, or $190 in all. The working time of the plant was as follows:
Per cent. Prorated
Days. of time. plant cost.
Cofferdam 7 39 $74
Excavation 2 11 21
Foundation piles 4 22 42
Concrete 5 28 53
-- --- ----
Totals 18 100 $190
As above given, the labor on the 7,900 ft. B. M. in the cofferdam cost
$126, or $16 per M.; but this additional $74 of prorated plant costs,
adds another $9 per M., bringing the total labor and plant to $25 per
M., to which must be added the $20 per M. paid for the timber in the
cofferdam, making a grand total of $45 per M. This shows that the
contractor's bid of $37 per M. was much too low.
The labor on the excavation cost 57 cts. per cu. yd., to which must be
added the prorated plant cost of $21 distributed over the 58 cu. yds.,
or 36 cts. per cu. yd., making a total of 93 cts. per cu. yd. This shows
that the bid of $1 per cu. yd. was hardly high enough.
The labor on the 24 foundation piles cost $80, or $3.33 each. The
prorated plant cost is $42, or $1.75 per pile, which, added to $3.33,
makes a total of $5.08. This shows that the bid of $5 Per pile for
driving was too low. However there was a profit of 2 cts. per ft., or 80
cts. per pile, on the cost of piles delivered.
The concrete amounted to 100 cu. yds. Hence the prorated plant cost of
$53 is equivalent to 53 cts. per cu. yd. Hence the total cost of the
concrete was:
Per cu. yd.
Cement, sand and stone $3.20
Foreman (at $5) 0.25
Labor (at $2) 1.00
Engineman (at $3) 0.15
Coal (at $3) 0.06
Carpenters (at $3) 0.24
Forms (at $23.50, used once) 0.80
Wire, nails, etc 0.02
Prorated plant cost 0.53
-----
Total $6.25
Since the contract price for concrete was $8 per cu. yd., there was a
good profit in this item.
~BACKING FOR BRIDGE PIERS AND ABUTMENTS.~--Six piers and two abutments of
the City Island bridge were constructed in 1906 at New York city, of
masonry backed with 1-2-4 concrete below and 1-3-5 concrete above high
water. The piers and abutments were all sunk to rock or hard material by
means of timber cofferdams. Table XVI gives the labor cost of mixing and
placing the concrete backing for one abutment and three piers, after the
materials were delivered on the scows. The concrete was mixed by a
rectangular horizontal machine mixer and deposited by 2-cu. yd. bottom
dump buckets handled by derrick scows and stiff leg derricks. The high
cost of concreting on Pier 2 was due to the fact that the concrete was
improperly deposited and had to be removed and the higher cost in
Abutment 1 was probably due to the fact that the abutment was so long
and narrow that it was difficult to handle the bucket.
TABLE XVI.--COST OF CONCRETE BACKING FOR MASONRY PIERS.
[Transcriber's note: Table split to be less than 80 column width]
Abutment No. 1. Pier No. 2.
Wages Cost Cost
per No. Total per No. Total per
Hour. hrs. Cost. cu. yd. hrs. Cost. cu. yd.
Superintendent 70 24 $16.80 $0.03 47 $32.90 $0.09
Foreman 35 160 56.00 0.09 128 44.80 0.13
Laborers 15-20 2555 383.25 0.65 2038 313.60 0.92
Engineman 30 365 109.50 0.19 196 58.50 0.19
Timekeeper 40 86 34.40 0.06 46 18.40 0.06
Pier No. 3. Pier No. 4.
Wages Cost Cost
per No. Total per No. Total per
Hour. hrs. Cost. cu. yd. hrs Cost. cu. yd.
Superintendent 70 72 $50.40 $0.05 16 $11.20 $0.03
Foreman 35 324 113.40 0.12 54 18.90 0.06
Laborers 15-20 3513 526.95 0.56 940 141.00 0.44
Engineman 30 244 73.20 0.08 60 18.00 0.06
Timekeeper 40 81 32.40 0.04 10 4.00 0.01
Summary.
Wages Total Total Av.
Hrs. cost. per cu. yd.
Superintendent 70 159 $111.30 $0.05
Foreman 35 666 233.10 0.11
Laborers 15-20 9046 1364.90 0.62
Engineman 30 865 259.50 0.12
Timekeeper 40 223 89.20 0.04
~PNEUMATIC CAISSONS, WILLIAMSBURG BRIDGE.~--Mr. Francis L. Pruyn, Assoc.
M. Am. Soc. C. E., gives the following costs of concreting the pneumatic
caissons for the Brooklyn tower of the Williamsburg bridge at New York
city. The work comprised the mixing and placing of some 13,637 cu. yds.
of concrete in two caissons. Table XVII shows the itemized costs for one
caisson and Table XVIII shows them for the other caisson. The methods of
work were as follows:
After each caisson was built it was towed to its proper site, where it
was held in place by temporary pile dock built completely around it. On
these docks the concrete was placed; a 2 cu. yd. cubical mixer of the
usual pattern being used for mixing. The concrete materials, consisting
of sand, stone and cement was handled direct from barges alongside, into
the mixer. The concrete was placed by a derrick located in the center of
the caisson, which was a bad feature as the caisson was usually out of
level and considerable difficulty was experienced in swinging the
derrick. On the South caisson ¾ cu. yd. bottom dump buckets were used in
placing the concrete, on the North caisson the size of these was
increased to 1½ cu. yd. which reduced the cost of placing 15 cts. per
cu. yd. There were placed in the South caisson 3,827 cu. yds. in 32 days
of actual working time--120 cu. yds. per day of 10 hrs. The gross time
was 2 months. On the North caisson 5,693 cu. yds. were placed in 46 days
worked--124 cu. yds. per day. The gross time was 4 months.
The rates of labor were as follows per 10-hour day:
Foreman $5.00
Assistant foreman 2.50
Hoisters 2.50
Fireman 1.60
Laborer 1.50
Proportions concrete were 1: 2.5: 6.
The low price of sand in the North caisson was brought about by the
finding of good building sand in the excavation for the anchorage, which
work was done by the same contractor.
When the caissons had been sealed the iron material shafts were removed.
This left holes 5 ft.×6 ft. extending from the roof of the caisson up
to Mean H.W. which were filled with concrete. These shaft holes were 80
ft. deep on the South caisson and 100 ft. deep on the North caisson.
They were partially filled with water and the concrete had to be placed
with considerable care. Wooden chutes were used on the South caisson;
they rested on the caisson roof, were filled with concrete and then
raised allowing concrete to flow out at the bottom. The shaft holes were
too deep on the North caisson for chutes and 20 cu. ft. bottom dump
buckets were used. They had to be lowered to bottom of shaft each trip
before dumping, a slow operation, which greatly added to the cost.
Proportion for concrete 1-2.5-6.
The proportion for concrete in working chamber was the same as for all
other concrete. The specifications called for 6 in. of mortar, of 1 part
of cement to 2½ parts of sand, between the concrete and all bearing
areas; that is, under the cutting edge and directly under the roof of
the working chamber. The concrete was mixed in the cubical mixer and
dumped on the bottom door of the material lock, the top door of the lock
was then closed, the bottom door opened and the concrete fell through
the shaft to the working chamber. It was then shoveled by the sand hogs
into place. A 6-in. space was left below all bearing surfaces into which
damp mortar was tightly rammed. Concreting the South caisson took 10¼
working days of 24 hours, the gangs working night and day in twelve
2-hour shifts; 1,566 cu. yds. of concrete and mortar were placed, or at
the rate of 140 cu. yds. per 24 hours. The gross time including Sundays
was 14½ days. The sand hogs worked in shifts of 2 hours each and
received $3.50 for the two hours work. The twelve foremen received 1
dollar more: the average gang consisted of 12 sand hogs.
On the North caisson the organization was much better, owing to the
experience gained on the first caisson; and in spite of the fact that
the sand hogs, on account of the increased depth, received $4.00 for 1½
hours' work, or an increase of $22.00 per man per 24 hrs. over that on
the South caisson, the work was done for less money. There were placed
1,566 cu. yds. of concrete in 7 working days of 24 hrs., or at the rate
of 224 cu. yds. per day. The gross time was 11½ days including Sundays.
The average number of men in the sand hog gangs was 18, with one
foreman, who received $5 for 1½ hours work.
TABLE XVII.--ITEMIZED COST OF CONCRETING SOUTH CAISSON FOR BROOKLYN
TOWER OF THE WILLIAMSBURG BRIDGE: COST OF CONCRETING CAISSONS ABOVE
ROOF.
South Caisson (3,827 cu. yds.).
Materials. Quantity. Rate. Amount.
Cement 4,480 bbls. $1.57 $7,034.00
Sand 1,288 cu. yds. .60 773.00
Broken stone 3,421 cu. yds. 1.50 5,132.00
Water 36.00
------- ------ ---------
Total 3,827 cu. yds. $3.39 $12,975.00
Labor.
Mixing and placing 3,827 cu. yds. $0.90 $3,432.00
Plant charges 2,280.00
Plant labor 742.00
------- ------ ---------
Total plant 3,827 cu. yds. $0.79 $3,022.00
------- ------ ---------
Total cost 3,827 cu. yds. $5.08 $19,429.00
General expenses, 10% 3,827 cu. yds. .51 1,943.00
------- ------ ---------
Grand total 3,827 cu. yds. $5.59 $21,372.00
COST OF CONCRETING SHAFTS.
South Caisson.
Materials. Quantity. Rate. Amount.
Concrete 612½ bbls. $1.57 $962.00
Sand 193 cu. yds. .40 77.00
Stone 493 cu. yds. 1.10 542.00
------- ------ ---------
Total 541 cu. yds. $2.92 $1,581.00
Labor.
Handling, mixing and placing 541 cu. yds. $0.96 $519.00
Plant charges, etc. 541 cu. yds. 1.06 576.00
------- ------ ---------
Total 541 cu. yds. $4.94 $2,676.00
General expenses, 10% 541 cu. yds. .49 267.00
------- ------ ---------
Grand total 541 cu. yds. $5.43 $2,943.00
COST OF CONCRETE IN WORKING CHAMBERS.
South Caisson. (1,435 cu. yds.)
Materials. Quantity. Rate. Amount.
Cement for concrete 1,666 bbls. $1.57 $2,615.00
Cement for mortar 459 bbls. 1.57 720.00
Sand for both 670 cu. yds. .40 268.00
Broken stone 1,181 cu. yds. 1.10 1,299.00
------- ------ ---------
Total materials 1,435 cu. yds. $3.42 $4,902.00
Labor.
Top labor, mixing and placing 1,435 cu. yds. $1.09 $1,575.00
Pneumatic labor 1,435 cu. yds. 4.93 7,117.00
Compressor house labor 1,435 cu. yds. .19 275.00
------- ------ ---------
Total labor 1,435 cu. yds. $6.21 $8,967.00
Plant.
Coal at $2.40 per ton 1,435 cu. yds. .10 140.00
Concrete plant 1,435 cu. yds. .79 1,145.00
Pneumatic plant 1.435 cu. yds. 1.05 1,522.00
-------- ------ ---------
Total plant 1,435 cu. yds. $1.94 $2,807.00
Totals 1,435 cu. yds. $11.57 $16,676.00
General expenses, 10% 1,435 cu. yds. 1.16 1,667.00
-------- ------- ----------
Grand total 1,435 cu. yds. $12.73 $18,343.00
TABLE XVIII.--ITEMIZED COST OF CONCRETING NORTH CAISSON FOR BROOKLYN
TOWER OF THE WILLIAMSBURG BRIDGE:
COST OF CONCRETING CAISSON ABOVE ROOF (5,692 cu. yds.)
Materials. Quantity. Rate. Amount.
Cement 6,707½ bbls. $1.57 $10,531.00
Sand 2,133 cu. yds. .40 845.00
Broken stone 4,938 cu. yds. 1.10 5,432.00
Water 51.00
------- ------ ---------
Total 5,692 cu. yds. $2.96 $16,859.00
Labor.
Mixing and placing 5,692 cu. yds. $0.73 $4,159.00
Plant charges 2,952.00
Plant labor 517.00
------- ------ ---------
Total 5,692 cu. yds. $0.61 $3,469.00
Total cost 5,692 cu. yds. $4.30 $24,487.00
General expenses, 10% 5,692 cu. yds. .43 2,448.00
Grand total 5,692 cu. yds. $4.73 $26,935.00
COST OF CONCRETING SHAFTS.
Materials. Quantity. Rate. Amount.
Cement 614½ bbls. $1.57 $965.00
Sand 204 cu. yds. .40 82.00
Stone 521 cu. yds. 1.10 574.00
------- ------ ---------
Total 576 cu. yds. $2.82 $1,621.00
Labor.
Mixing and placing 576 cu. yds. 1.70 982.00
Plant charges, etc. 576 cu. yds. 1.36 795.00
------- ------ ---------
Total 576 cu. yds. $5.88 $3,398.00
General expenses, 10% 576 cu. yds. .59 339.00
------- ------ ---------
Grand total 576 cu. yds. $6.47 $3,737.00
COST OF CONCRETING WORKING CHAMBERS (1,566 cu. yds.).
Materials. Quantity. Rate. Amount.
Cement for concrete 1,559 bbls. $1.51 $2,446.00
Cement for mortar 442 bbls. 1.51 $694.00
Sand for both 630 cu. yds. .40 252.00
Broken stone 1,380 cu. yds. 1.10 1,518.00
------- ------ ---------
Total 1.566 cu. yds. $3.14 $4,910.00
Labor.
Top labor, mixing and placing 1,566 cu. yds. $0.78 $1,198.00
Pneumatic labor 1,566 cu. yds. 4.91 7,694.00
Compressor house labor 1,566 cu. yds. .11 180.00
------- ------ ---------
Total labor 1,566 cu. yds. $5.80 $9,072.00
Plant.
Coal at $2.40 per ton 1,566 cu. yds. .06 87.00
Concrete plant 1,566 cu. yds. .86 1,352.00
Pneumatic plant 1,566 cu. yds. .81 1,272.00
------- ------ ---------
Total plant 1,566 cu. yds. $1.73 $2,711.00
------- ------ ---------
Totals 1,566 cu. yds. $10.67 $16,693.00
------- ------ ---------
General expenses, 10% 1,566 cu. yds. 1.06 1,669.00
------- ------ ---------
Grand total 1,566 cu. yds. $11.73 $18,362.00
~COST OF FILLING PIER CYLINDERS.~--The following costs were obtained in
mixing and placing concrete in steel cylinder piers. The sand and gravel
were wheeled 100 ft. to the mixing board at the foot of the cylinder,
mixed and shoveled into wooden skips, hoisted 20 ft. by horsepower and
dumped into the cylinder. The foreman worked on the mixing board and the
men worked with great energy. The costs were as follows:
Item-- Per day. Per cu. yd.
6 men wheeling materials and mixing at 15
cts. per hour 9.00 $0.45
2 men dumping skips and ramming at 15 cts.
per hour 3.00 0.15
1 team and driver at 40 cts. per hour 4.00 0.20
1 foreman at 30 cts. per hour 3.00 0.15
----- ----
Totals $19.00 $0.95
~PIERS, CALF KILLER RIVER BRIDGE.~--The following methods and costs of
building two new piers and extending three old piers with concrete are
given by Mr. J. Guy Huff. The work was done by the railway company's
masonry gangs. Figure 94 shows the arrangement of the several piers and
the character of the work on each and Fig. 95 gives the detail
dimensions of the three main piers.
The sand and aggregate, consisting of blast furnace slag, were unloaded
from cars to platforms on a level with the top of rail, placed about 100
ft. south from the south end of the bridge. A cubical 1/6 cu. yd. mixer
was used. This was operated by a gasoline engine, and was located on a
platform about 50 ft. south of the south end pier. A tank near the mixer
to supply water was elevated enough to get the desired head, and was
kept filled by a pump run by another gasoline engine located down by the
river bank. The cement house was located between the mixer platform and
slag pile.
[Illustration: Fig. 94.--Diagram Arrangement of Piers, Calf Killer River
Bridge.]
[Illustration: Fig. 95.--Details of Pier for Calf Killer Elver Bridge.]
Slag and sand were delivered to the mixer by means of wheelbarrows. The
mixer was so placed that it would dump onto a platform, and the concrete
could then be shoveled into a specially designed narrow-gage car. This
car ran on one rail of the main track and an extra rail outside. A
turnout for clearing passing trains was provided at both ends of the
bridge. The track over the bridge from the mixer had a descending grade
of about 1 per cent., so that with a little start the concrete car would
roll alone down to the required points on the bridge. Only in returning
the empty cars to the mixer was it necessary to push them by hand, and
then only for a distance of never more than 400 ft.
Over the piers on the bridge in the center of the concrete car track
openings were sawed to let the concrete pass to the forms below. To get
the concrete into the forms, there were used zig-zag chutes with arms
about 10 ft. long, which sections were removed as the concrete in the
forms was increased. These chutes were a convenience by their ends
alternating from one side to the other as the arms were removed in
coming up.
The cost of the concrete work was as follows:
Unloading Material.
Rate Total days Per cu. yd.
per day. worked. Total. concrete.
Foreman $3.40 5 $17.00 $0.04
11 laborers 1.36-8/10 52 71.14 .15
-----
Total for unloading material $0.19
Building Forms, Bins, Etc.
Foreman $3.40 18 $61.20 $0.14
9 carpenters 2.25 166 373.50 .81
New lumber, 23.7 M. ft.
at $17.80 421.86 .92
Old lumber, 6 M. ft. at
$8.33 49.98 .11
-----
Total for building forms, bins, etc. $1.98
Cofferdam Excavation (45 cu. yds.)
Foreman $3.40 8 $27.20 $0.06
9 laborers 1.15 6/10 74½ 86.12 .19
-----
Total for cofferdam excavation $0.25
Cofferdam Concrete (37 cu. yds.)
Foreman $3.40 8 $27.20 $0.06
11 laborers 1.36 3/10 79 107.68 .23
Cofferdam lumber, 2.25
M. ft. at $20.00 45.00 .09
----
Total for cofferdam concrete $0.38
Concrete Mixing and Placing.
Foreman $3.40 30 $102.00 $0.22
9 laborers 1.15 6/10 282 325.99 .71
Cement, 452 bbls. at
$1.55 701.00 1.52
Slag, 437 cu. yds. at $0.20 87.40 .19
Sand, 220 cu. yds. at
$0.30 66.00 .14
-----
Total for mixing and placing $2.78
Taking Down Forms and Clearing Up.
Foreman $3.40 13 $44.20 $0.09
11 laborers 1.17 1.43 107.31 .36
-----
Total for taking down forms, etc. $200.00 $0.45
Engineering and supervision .43
-----
Grand total, 460 cu. yds. concrete $6.46
The wages given are the average wages. The men worked a 10-hour day. The
concrete was a 1-3-6 mixture. The cofferdam work was done in connection
with the construction of the fourth pier, this pier being the only one
coming in the bed of the river to be built entirely new. The work on
this was started in water about 6 ft. deep. The 37 cu. yds. of concrete
is included in the total of 460 cu. yds. in the above tabulation. By
itself the cost of the cofferdam work, not including cost of cement,
sand and slag was as follows:
Per cu. yd.
Total. Concrete.
Lumber $ 45.00 $1.21
Labor, excavating 113.32 3.06
Labor, concrete 134.88 3.64
-----
Total 37 cu. yds. concrete $7.91
[Illustration: Fig. 96.--Details of Piers for K. C., M. & O. Ry.
Bridge.]
~METHOD AND COST OF CONSTRUCTING 21 BRIDGE PIERS.~--The following account
of the methods and cost of constructing 21 concrete piers for a railway
bridge consisting of 20 50-ft. plate girder spans has been compiled from
records kept by Mr. W. W. Colpitts, Assistant Chief Engineer, Kansas
City, Mexico & Orient Ry. The shape and dimensions of the piers are
shown by Fig. 96 and Fig. 97 shows the construction of the forms. Sheet
pile cofferdams to solid rock were used for constructing the
foundations.
[Illustration: Fig. 97.--Forms for Piers for K. C., M. & O. Ry. Bridge.]
The 1-3-5 concrete was mixed in a Smith mixer having a batch capacity of
9 cu. ft. The mixer was located on the slope of the embankment
approach, with the main track at its rear and facing a temporary
material track. This temporary track turned out from the main track
about 500 ft. beyond the mixer and extended diagonally down the
embankment approach on a 3 per cent. grade and across the river bottom
alongside the pier sites. The portion of the track in the river bottom
was supported on bents of spliced ties, jetted to the rock, and wired to
the cofferdam to avoid the danger of loss in case of high water. The
sand and crushed rock were delivered by cars from the main line track,
immediately above the mixer, and the cement was stored in a shanty at
one side of the mixer. The concrete materials and machinery were, in
this manner, very conveniently located for rapid work and well above the
high water line. The concrete was transported to the pier sites in
improvised dump boxes, set on push cars. These dump boxes were hinged
longitudinally and discharged directly into the cofferdams. The grade of
the temporary track carried the push cars by gravity to the cofferdams
and they were returned by teams, for which purpose a straw and brush
road had been built paralleling the track. As the work progressed
farther into the stream, more cars were added properly to balance the
work. While the concrete in the base was still fresh, a number of steel
reinforcing bars, 8 ft. in length, were set in place along each end to
insure a good bond between the base and shaft.
In general, the work of putting in the bases was organized so that about
the same time was required in filling a cofferdam with concrete, in
excavating the sand from the next, and in driving the sheet piling for
the third. These three operations were thus carried on simultaneously
and, although interruptions in one part of the work or the other
occurred frequently, the gangs were interchangeable and no appreciable
loss was suffered, except in time, because of such delays.
In piers 19 and 20, where the rock was from 17 to 19 ft. below the
surface, some difficulty was encountered due to the presence of fissures
in the rock, from which it was necessary to remove the sand to fill with
concrete. In such cases, the larger leaks were stopped as much as
possible by driving sheet piles against the outside face of the
cofferdam and into the fissures, and the smaller leaks by manure in
canvas bags rammed into the openings.
Upon the completion of all the bases, the forms for several shafts were
set in position and the work of filling with concrete proceeded as in
the case of the bases, except that a derrick erected on a flat car and
stationed at the pier was utilized to raise the dump boxes in depositing
the concrete in the forms. As soon as the concrete in one shaft had set
sufficiently to permit of it, the forms were removed and placed on the
pier ahead. Four sets of forms were used for the shafts.
The following are the average prices paid for materials and labor:
Materials.--Lumber for forms, etc., $16.50 per M. ft., B. M.; cement,
Kansas Portland, $1.50 per bbl.; broken limestone, 45c per cu. yd.;
sand, Arkansas River, 15c per ton.
Labor.--General foreman, $110 per month; assistant foreman, $75 per
month; timekeeper, $60 per month; riveters, 35c per hour; blacksmith,
30c per hour; blacksmith assistant, 20c per hour; carpenters, 22½c and
25c per hour; enginemen, 25c per hour; firemen, 20c per hour; night
watchman, 20c per hour; laborers, 17½c and 20c per hour; team (including
driver), 40c per hour. The prices quoted for lumber, cement, limestone
and sand are prices f. o. b., Louisiana, Iola, Kan., El Dorado, Kan.,
and Wichita, Kan.
The total and unit cost of constructing the concrete piers and abutments
and of erecting the steel superstructure are given in the following
tabulation. Altogether there was about 2,300 cu. yds. of concrete in the
substructure, most of which, as stated above, was a 1-3-5 mixture.
Machinery and Supplies.
Concrete mixer, 20% of cost $ 152.10
Supplies, freight, hauling, setting up 505.04
--------
Total $ 657.14
Centrifugal sand pump, 20% of cost $ 27.00
Supplies, freight, hauling, setting up 277.50
Rent of traction engine to operate 83.25
--------
Total $ 387.75
Water pump and pipe, 20% of cost $ 29.00
Supplies, freight, hauling, setting up 177.32
--------
Total $ 206.32
Pile driver engine, 20% of cost $ 100.00
Supplies, freight, hauling, setting up 243.65
--------
Total $ 343.65
--------
Grand total $1,594.86
Cofferdams.
Materials, lumber and nails $1,285.26
Freight and train haul 306.33
Labor making piles 696.82
Labor driving piles 1,384.05
---------
Total $3,672.46
The sheet piling took 63,500 ft. B. M. of lumber; the cost per 1,000 ft.
B. M. for the sheet piling was then:
Materials, lumber and nails $ 20.08
Freight and haulage 4.82
Labor making piles 10.97
Labor driving piles 21.80
--------
Total $ 57.67
Forms, Platforms and Runways.
Lumber, hardware, etc. $ 224.59
Freight and train haul. 40.20
Labor making, removing and placing. 556.51
---------
Total $ 821.30
Concrete Materials.
Cement, freight, unloading and storing. $4,617.48
Sand, freight, unloading, etc. 1,336.05
Broken stone, freight, unloading, etc. 2,026.92
---------
Total $7,980.45
This gives us for 2,300 cu. yds. of concrete a cost of $3.47 per cu. yd.
for materials, including freight, storage, and unloading charges of all
kinds. A line on the proportion of the cost contributed by these latter
items may be got by taking the prices of the materials f. o. b. at the
places of production and assuming the proportions for a 1-3-5 concrete.
According to tables in Chapter II, a 1-3-5 broken stone concrete
requires per cubic yard 1.13 bbls. cement, 0.48 cu. yd. sand and 0.80
cu. yd. broken stone. We have then:
1.13 bbls. cement, at $1.50 $1.69
0.48 cu. yd. sand, at 20c .10
0.80 cu. yd. stone, at 45c .36
-----
Total $2.15
This leaves a charge of $1.32 per cubic yard of concrete for freight and
handling materials. The cost of mixing concrete and placing it in the
forms was $3,490.87, or $1.52 per cu. yd. We have then:
Cost of concrete materials per cu. yd. $3.47
Cost of mixing and placing concrete. 1.52
-----
Total. $4.99
The miscellaneous expenses of the work comprised:
Watchman, tools, telephone, etc. $ 722.48
Shanties, furnishings, supplies, etc. 829.04
---------
Total. $1,551.52
To this has to be added $1,134.28, the cost of excavating the
cofferdams. The total and unit costs of the different items of the
concrete substructure work can now be summarized as follows:
Item. Total. Per cu. yd.
Machinery and supplies 1,594.86 $ .69
Cofferdams 3,672.49 1.60
Forms, etc 821.30 .36
Concrete materials 7,980.45 3.47
Mixing and placing concrete 3,490.87 1.53
Excavating cofferdams 1,134.28 .49
Miscellaneous 1,551.52 .67
---------- -----
Total $20,245.74 $8.81
~COST OF PERMANENT WAY STRUCTURES KANSAS CITY OUTER BELT & ELECTRIC
RY.~--The following cost of concrete work including retaining walls,
abutments and box culverts, for the permanent way of the Kansas City
Outer Belt & Electric Ry., is given by Mr. W. W. Colpitts. These figures
are of particular interest, for the variation in prices of materials
during the two-year period while work was in progress and as giving the
average cost of the work on the whole line as well as for individual
structures. The culverts were all box culverts with wing walls and the
abutments were for girder bridges. Walls and abutments were of L section
with triangular or trapezoidal counterforts at the back between base
slab and coping. The form work was thus rather complex.
All work was reinforced concrete, and was done by contract under the
following conditions: The work of preparing foundations, including
excavation, pile driving, diversions of streams, etc., was done by the
railroad company, which also bore one-half the cost of keeping
foundations dry while forms were being built and concrete placed. The
railroad company also furnished the reinforcing bars at the site of each
opening. The concrete work was let at $9 per cu. yd., which figure
covered all the labor and materials necessary to complete the work,
other than the exceptions mentioned. The concrete proportions were
1-3-5. The cement used was Iola Portland and Atlas Portland. The sand
was obtained from the bed of the Kansas River in Kansas City. The rock
used was crushed limestone, passing a 2-in. ring and freed from dust by
screening. Corrugated reinforcing bars, having an elastic limit of from
50,000 to 60,000 lbs. per sq. in., manufactured by the Expanded Metal &
Corrugated Bar Co. of St. Louis, Mo., were used exclusively. The
concrete in the smaller structures was mixed by hand, in the larger by a
No. 1 Smith mixer. In the first structures built 2-in. form lumber was
used, with 2 by 6-in. studs placed 3 ft. on centers. This was abandoned
later for 1-in. lumber with 2 by 6-in. studs, 12 ins. on centers, and
was found to be more satisfactory in producing a better face. The
structures were built in the period from April, 1905, to May, 1907.
The cost of materials and the wages paid labor were as follows:
Cement--
Per barrel at structure, April, 1905 $1.25
Per barrel at structure, April, 1907 1.92
Average cost per barrel at mill 1.42
Freight per barrel 0.21
Hauling 1½ miles and storage 0.12
Average cost at structure 1.75
Average cost per cu. yd. concrete (1.1 bbls.) 1.93
Sand--
Per cu. yd. at structure, April, 1905 $0.625
Per cu. yd. at structure, April, 1907 0.75
Average cost per cu. yd., river bank 0.30
Freight per cu. yd 0.22
Hauling 1½ miles 0.20
Average cost at structure 0.72
Average cost per cu. yd. concrete (½ cu. yd.) 0.36
Stone--
Per cu. yd. at structure, April, 1905 $1.10
Per cu. yd. at structure, April, 1907 1.75
Average cost per cu. yd. at crusher 0.65
Hauling 4 miles 0.84
Average cost at structure 1.49
Average cost per cu. yd. concrete (0.9 cu. yd.) 1.34
Lumber--
Per M. ft. at structure, April, 1905 $15.00
Per M. ft. at structure, April, 1907 22.50
Average cost per M. at structure 19.00
Average cost per cu. yd. concrete 0.49
Labor-- Max. Min.
Common labor, cts. per hour 20 17
Carpenters, cts. per hour 40 30
With these prices and wages the average cost of concrete work for the
whole line was:
Item. Per cu. yd.
Form building and removing $1.98
Mixing and placing concrete 0.74
Placing reinforcement 0.10
Wire, nails, water, etc. 0.20
1.1 bbls. cement at $1.75 1.93
½ cu. yd. sand at $0.72 0.36
0.9 cu. yd. stone at $1.49 1.34
Lumber for forms 0.49
------
Total $7.14
The following are the costs of specific structures built at different
times:
Example I.--Indian Creek Culvert. 14×15 ft., 250 long, completed
November, 1905:
Per cu. yd.
Cement $1.37
Sand .34
Stone 1.10
Labor 2.48
Lumber .76
Miscellaneous .18
Total $6.23
Example II.--Third Street Abutments and Retaining Wall. Completed
November, 1906:
Per cu. yd.
Cement $1.78
Sand .35
Stone 1.35
Lumber .74
Labor 2.75
Miscellaneous .16
-----
Total $7.13
Example III.--Abutments, Overhead Crossing with Union Pacific and Rock
Island. Completed May, 1907:
Per cu. yd.
Cement $1.92
Sand .32
Stone 1.74
Lumber .98
Labor 2.96
Miscellaneous .16
-----
Total $8.08
~COST OF PLATE GIRDER BRIDGE ABUTMENTS.~--The following record of the
construction of 20 abutments for 10 four-track plate girder bridges over
streets in Chicago, Ill., are given by Mr. W. A. Rogers. The work was
done between May 1 and Oct. 1, 1898, in which time 8,400 cu. yds. of
concrete were placed, all the work being done by company labor. The
forms were made of 2-in. plank and 6×6-in. posts bolted together at the
top and bottom with ¾-in. rods. The lumber was used over and over again.
When the dressed plank became too poor for the face it was used for the
back. The concrete was 1 Portland cement, 3 gravel and 4 to 4½ limestone
(crusher run up to 3-in. size). A mortar face 1½ ins. thick was built up
with the rest of the concrete. The concrete was made quite wet, and each
man ramming averaged 18 cu. yds. a day rammed. The concrete was mixed by
a machine of the Ransome type, operated by a 12-HP. portable gasoline
engine. The load was very light for the engine, and 8 HP. would have
been sufficient. The engine made 235 revolutions per minute, and the
pulley wheels were proportioned so that the mixer made 12 revs, per
minute. One gallon of gasoline was used per hour, and the mixing was
carried on day and night so as not to give the concrete time to set. The
time required for each batch was 2 to 3 mins., and about ½ cu. yd. of
concrete was delivered per batch. The average output was 70 cu. yds. per
10-hr, shift, with a crew of 28 men; but as high as 96 cu. yds. were
mixed in 10 hrs. The concrete was far superior to hand mixed concrete.
The water for the concrete was measured in an upright tank and
discharged by a pipe into the mixer. The sand and stone were delivered
to the mixer in wheelbarrows, and the concrete was taken away in
wheelbarrows. No derricks were used at all. Each wheelbarrow of concrete
was raised by a rope passing over a pulley at the top of a gallows
frame, one horse and a driver serving for this raising. A small gasoline
hoisting engine would have been more satisfactory than the horse which
was worked to its full capacity. After the barrows were raised (12 ft.),
they were wheeled to the abutment forms and dumped. The empty
wheelbarrows were lowered by hand, by means of a rope passing over a
sheave and provided with a counterweight to check the descent of the
barrow. The cost of the concrete (built by company labor) was as
follows:
Per cu. yd.
Cement, gravel and stone delivered $3.28
Material in forms (used many time) .11
Carpenters building and taking down forms .34
Labor 1.18
-----
Total per cu. yd $4.91
The labor cost includes moving plant from one bridge to the next,
building runways, gasoline for engine, oil for lights at night and
unloading materials, as well as mixing, transporting and placing
concrete. Wages were $1.75 per 10-hour day for laborers and $2.50 for
carpenters.
~COST OF ABUTMENTS AND PIERS, LONESOME VALLEY VIADUCT.~--Mr. Gustave R.
Tuska gives the following on the concrete substructure of the Lonesome
Valley Viaduct, near Knoxville, Tenn. There were two U-shaped abutments
and 36 concrete piers made of a light limestone that deteriorates
rapidly when used for masonry. Derricks were not needed as would have
been the case with masonry piers, and colored labor at $1 for 11 hrs.
could be used. The piers were made 4 ft. square on top, from 5 to 16 ft.
high, and with a batter of 1 in. to the foot. The abutments average 26
ft. high, 26 ft. long on the face, with wing walls 27 ft. long; the wall
at the bridge seat is 5 ft. thick, and the wing walls are 3½ ft. wide on
top. Batters are 1 in. to the foot.
The forms were made of 2-in. tongued and grooved plank, braced by posts
of 2×10-in. plank placed 3 ft. c. to c. for the abutments, and at each
corner for the piers. At the corners one side was dapped into the other,
so as to prevent leakage of cement. The posts were braced by batter
posts from the earth. For the piers a square frame was dropped over the
forms and spiked to the posts. The abutment forms were built up as the
concreting progressed. The north abutment forms were made in sections 6
ft. high, held by ¾-in. bolts buried in the concrete. The lower sections
were removed and used again on the upper part of the work, thus saving
plank. The inside of forms was painted with a thin coat of crude black
oil. The same form was used for several piers.
The concrete was 1-2-5, the barrel being the unit of measure, making
about ¾ cu. yd. of concrete per batch. The mortar was mixed with hoes,
but shovels were used to mix in the stone. By passing the blade of a
shovel between the form and the concrete, the stone was forced back and
a smooth mortar face was secured. Rammers weighing 30 to 40 lbs. were
used for tamping. Two days after the completion of a pier the forms were
removed. The concrete was protected from the sun by twigs, and was
watered twice a day for a week. It was found by actual measurement that
1 cu. yd. Of concrete (1-2-5), the ingredients being measured in
barrels, consisted of 1¼ bbls. of Atlas cement, 10 cu. ft. of sand, and
26½ cu. ft. of stone. The total amount of concrete was 926 cu. yds. of
which two-thirds was in the two abutments. The work was done (in 1894)
by contract, for $7 per cu. yd., cement costing $2.80 per bbl., sand 30
cts. per cu. yd., and wages $1 a day. A slight profit was made at this
price. A gang of 15 men and a foreman would mix and lay about 40 cu.
yds. in 11 hrs. when not delayed by lack of materials. The cost of
making the concrete, with wages at $1 a day, was:
Cts. per cu. yd.
1 man filling sand barrels and handling water 2.7
2 men filling rock barrels 5.4
4 men mixing sand and cement 10.6
4 men mixing stone and mortar 10.6
2 men wheeling concrete 5.3
1 man spreading concrete 2.7
1 man tamping 2.7
1 foreman 5.0
----
Total labor 45.0
~COST OF HAND MIXING AND WHEELBARROW WORK FOR FOUR BRIDGE PIERS.~--The
following figures of the cost of hand-mixed concrete for bridge piers
and abutments are given by Mr. Fred R. Charles of Richmond, Ind. The
figures cover three jobs. All concrete was mixed by hand and with one
exception noted below was moved to place in wheelbarrows. The concrete
was a 1-2½-5½ mixture. In this connection it is well to note that in one
or two of the jobs where the proportion of the aggregate seems too small
for the yardage of concrete the difference is accounted for by the fact
that large stones were placed in the foundations, these stone being on
the ground and costing nothing but the labor to throw them in.
_Job I._--The first job consisted of the construction of one abutment
and six piers for a bridge over the Miami River at Fernald, O. The stone
was procured on the site and crushed by a portable crusher run by a
traction engine. The rough stone cost 10 cts. a cubic yard, and this,
with the cost of handling, fuel and hire of engine and crusher, made the
cost of crushed stone about $1 per cu. yd. Sand was obtained close to
the work, but the cement had to be teamed 10 miles. Labor was paid $1.75
per day. The cost of materials and labor per cubic yard of concrete in
place was as follows:
Item. Per cu. yd.
1.16 bbls. cement at $2.10 $1.58
Sand 0.35
Stone 0.75
Lumber 0.64
Tools, hardware, etc. 0.20
Labor (including 15 cts. per cu. yd. for pumping) 2.78
-----
Total materials and labor $6.30
_Job II._--The second job was the construction of two abutments
containing 434 cu. yds. of concrete for a viaduct at Ernst Street,
Cincinnati, O. The abutments were constructed at the street and the
excavation was clay and shale. Labor received $1.75 per day. The cost of
materials and labor per cubic yard of concrete in place was as follows:
Materials-- Per cu. yd.
376 bbls. cement at $1.70 $1.48
224 cu. yds. sand at $1.20 0.64
255 cu. yds. stone at $1.55 1.00
Lumber 0.40
Tools, hardware, etc. 0.06
Total materials $3.58
Labor--
Clearing and excavating $1.12
Mixing and placing concrete 1.13
Building forms, etc. 0.25
-----
Total labor $2.50
Total labor and materials $6.08
_Job III._--This job consisted in placing 570 cu. yds. of concrete in
the pedestals for a viaduct at Quebec Avenue, Cincinnati, O. The
pedestals were 5 ft. square on top and from 8 to 20 ft. high. The
location of the work was very inconvenient for the delivery of
materials, all materials having to be teamed or wheeled. Labor was paid
$1.75 per day. The cost of labor and materials per cubic yard of
concrete in place was as follows:
Item. Per cu. yd.
500 bbls. cement at $1.60 $1.40
239 cu. yds. sand at $1.25 0.53
560 cu. yds. stone at $1.88 1.84
Lumber 0.38
Tools, hardware, etc. 0.05
Labor 2.96
-----
Total labor and materials $7.16
_Job IV._--This job consisted in placing 2,111 cu. yds. of concrete in a
railway viaduct at Cincinnati, O. For one pier 56 ft. high the concrete
was raised to place by a derrick; for the remainder of the work it was
wheeled or teamed to place. Labor was paid $1.75 per day. The cost of
labor and materials per cubic yard of concrete in place was as follows:
Item. Per cu. yd.
1,908 bbls. cement at $1.60 $1.44
1,105 cu. yds. sand at $1.95 0.50
1,468 cu. yds. stone at $1.48 1.03
Lumber 0.54
Tools, hardware, etc. 0.25
Water 0.03
Labor 3.44
-----
Total labor and materials $7.23
Reading Tips
Use arrow keys to navigate
Press 'N' for next chapter
Press 'P' for previous chapter