Concrete Construction: Methods and Costs by Gillette and Hill
Chapter XIX, showing the reduction in lumber cost coming from using the
5065 words | Chapter 56
same material over a second or third time, should be studied in this
connection. The leading firms of engineering-contractors which both
design and construct reinforced concrete buildings fully realize these
opportunities and take advantage of them, but the general practitioner,
particularly if he be an architect, does not do so. The authors have
personal knowledge of one building in which a slight change in spacing
and dimensions of beams--a change that would have been of no
architectural or structural significance--would have reduced the
successful contractor's bid for the work by $10,000. The designing
engineer should hold it as a cardinal point in design that form work,
and we will add here reinforcement also, should so far as possible be
made interchangeable from bay to bay and from floor to floor.
~KIND OF LUMBER.~--The local market and the character of the work
generally determine the kind of lumber to be used for forms. The
hardwoods are out of the question for form construction because they
cost too much and are too hard to work. Among the soft woods white pine
costs too much for general use and hemlock is unreliable when exposed to
the weather. This reduces the list generally available to spruce, Norway
pine and the southern pines. Neither green nor kiln-dried lumber is so
good as partially dry stuff, since the kiln-dried lumber swells and
crushes or bulges the joints and green lumber does not swell enough to
close the joints. Forms have to withstand, temporarily, very heavy
loads, therefore, knots, shakes and rot must be watched after. The
choosing of good lumber is a simple process and the contractor who wants
to be able to rely on his forms will look after it carefully, without
going to extremes which the work does not warrant.
~FINISH AND DIMENSIONS OF LUMBER.~--Dressing the lumber serves four
important purposes: It permits the forms to be constructed more nearly
true to line and surface; it permits tighter joint construction; it
gives a smoother surface finish to the concrete, and it facilitates the
removal and cleaning of the forms. Undressed lumber may be used for the
backs of walls and abutments, for work below ground and wherever a
smooth and true surface is unimportant; there are some contractors,
however, who prefer lumber dressed on one side even for these purposes
because of the smaller cost of cleaning. For floor and wall forms the
lumber should always be dressed on one side; where the work is very
particular both sides should be dressed, and in special cases the sides
of the joists or studs against which the lagging lies may be dressed.
For ordinary work a square edge finish does well enough but for fine
face work a tongue and groove or bevel edge finish is preferable. The
tongue and groove finish gives a somewhat tighter joint on first laying
but it does not take up swelling or resist wear so well as the bevel
edge finish.
When ordering new lumber for forms the contractor will save much future
work and waste if he does it from plans. Timber cut to length and width
to go directly into the forms reduces both mill and carpenter work on
the site, and in many cases it can be so ordered if ordered from plans.
Waste is another item that is reduced by ordering from plans; with
lumber costing its present prices crop ends run into money very rapidly.
When old lumber from a previous job is to be used the contractor can
only make the best of his stock, but even here form plans will result in
saving. Sort and pile the old lumber according to sizes and make a
schedule of the quantity of each size on hand; this schedule in the
hands of the man who designs the forms and of the head carpenter will
materially reduce waste and carpenter work. It is often possible
especially in making concrete foundations for frame buildings to use
lumber for forms which is subsequently used for floor beams, etc., in
the building.
Contractors differ greatly in their ideas of the proper thickness of
lumber to use for various parts of form work. Generally speaking 1¼ to
2-in. stuff is used for wall lagging held by studding and 1-in. stuff
when built into panels; for floor lagging 1-in stuff with joists spaced
up to 24 ins. or when built into panels; for column lagging 1¼ to 2-in.
stuff; for sides of girders 1, 1¼, 1½ and 2-in. stuff are all used; and
for bottoms of girders, 1½ and 2-in. stuff. These figures are by no
means invariable as a study of the numerous examples of actual form work
given throughout this book will show.
~COMPUTATION OF FORMS.~--If the minimum amount of lumber consistent with a
given deflection is to be used in form work the sizes and spacing of the
supporting members must be actually computed for the loading. As a
practical matter of fact the amount of material used and the arrangement
of the supports are often subject to requirements of unit construction,
clearance, staging, etc., which supersede the matter of economical
adaptation of material to loading. The designing of form work is at
best, therefore, a compromise between rules of thumb and scientific
calculation. In wall work empirical methods are nearly always followed.
In girder and floor slab work, on the other hand, design is commonly
based on computation.
In the matter of loads the general practice is to assume the weight of
concrete as a liquid at some amount which it is considered will also
cover the weight of men, barrows, runways and current construction
materials. The assumed weights vary. One prominent engineering firm
assumes the load to be the dead weight of concrete as a liquid and the
load due to placing and specifies that the forms shall be designed to
carry this load without deflection. Mr. W. J. Douglas, Engineer of
Bridges, Washington, D. C, assumes for lateral thrust on wall forms that
concrete is a liquid of half its own weight, or 75 lbs. per cu. ft. Mr.
Sanford E. Thompson, Consulting Engineer, Newton Highlands, Mass.,
assumes for dead load, weight of concrete including reinforcement as 154
lbs. per cu. ft., and for live load, 75 lbs. per sq. ft. on slabs and 50
lbs. per sq. ft. in figuring beam and girder forms and struts.
The assumed safe stresses in form work may be taken somewhat higher than
is usual in timber construction, because of the temporary character of
the load. In calculating beams the safe extreme fiber stress may be
assumed at 750 lbs. per sq. in. The safe stress in pounds per square
inch for struts or posts is shown by Table XV, compiled by Mr. Sanford
E. Thompson. The sizes of struts given are those most commonly used in
form work.
TABLE XV.--SAFE STRENGTH OF TIMBER STRUTS FOR FRAME WORK.
--Dimensions of Strut.--
Length Strut. 3×4-in. 4×4-in. 6×6-in. 8×8-in.
Feet. Lbs. Lbs. Lbs. Lbs.
14 ..... 700 900 1,100
12 600 800 1,000 1,200
10 700 900 1,100 1,200
8 850 1,050 1,200 1,200
6 1,000 1,200 1,200 1,200
In using this table it must be borne in mind that bracing both ways
reduces the length of a long strut. For example, if a strut 24 ft. long
be divided into three panels by bracing the length of strut so far as
the table is concerned is 8 ft.
As stated above wall forms are rarely computed. Experience has shown
that the maximum spans of various thicknesses of lagging between
supports are: 1-in. boards, 24 ins.; 1½-in. plank, 4 ft., and 2-in.
plank, 5 ft. Studding will vary in size from 2×4 to 4×6 ins., strutted
and braced horizontally to meet conditions. Column forms, like wall
forms, are rarely computed, yokes being spaced 2 ft. apart for 1¼-in.
lagging up to 3 to 3½ ft. apart for 2-in. lagging.
Floor forms, including girder and slab forms, are computed on the basis
of a maximum deflection and not on the basis of strength. Sagging forms
are liable to rupture the beam or slab. The amount of deflection
considered allowable varies from no deflection up to 3/8 to ½ in.
Assuming the deflection, permissible thickness of the timber necessary
to carry the load is determined by the formulas:
d = 5 W l³ ÷ 384 E I (1)
and
bh³
I = --- (2)
12
Formula (1) is the familiar one for computing deflection for a beam
supported (not fixed) at the ends. Mr. Sanford F. Thompson suggests
using the constant {3/384}, which is an approximate mean between {1/384}
that for beams with fixed ends and {5/384} that for beams with ends
supported. Formula (1) then becomes
d = 3 W l³ ÷ 384 E I,
in which as above:
d = maximum deflection in inches.
W = total load on plank or joist.
l = length between supports in inches.
E = modulus of elasticity of lumber.
I = moment of inertia of cross-section.
b = breadth of lumber.
h = depth of lumber.
The deflection, d, being assumed formula (1) is solved for I, moment
of inertia. Substituting the value of I in formula (2) we can readily
estimate the size of joist or thickness of plank to use.--For spruce,
yellow pine and the other woods commonly used in form work E may be
taken equal to 1,300,000 lbs. per sq. in.
~DESIGN AND CONSTRUCTION.~--The main points to be kept in mind in the
original design and construction of forms are: Economy in lumber,
economy in carpenter work, and economy in taking down, carrying and
re-erecting. Economy in lumber is not merely the matter of using the
least amount of lumber that will serve the purpose considering the form
as an isolated structure. It may be possible to build a column form, for
example, of very light material which will serve to mold a single
column, but it is evident that we could better afford to use twice this
amount of lumber if by doing so we obtained a form which could be used
over again to mold a second column; no more lumber per column would be
used while the cost of erecting a form already framed is less than the
cost of framing a new form. Economy in lumber in form construction
involves, therefore, recognition of the economies to be gained by
repeated use of the lumber. A certain amount of additional sturdiness is
required in the shape of heavier form lumber and stronger framing to
provide for the wear and tear of repeated use, and it is always economy
to provide it when repeated use is possible. The thing can be overdone,
however; there is an economical limit to repeated use, as we demonstrate
further on. In the matter of economy in carpenter work, a certain amount
of extra work put into framing the forms to withstand the stress of
repeated use is economically justifiable. Also carpenter work put into
framing which substitutes clamps and wedges for nails is sound economy;
generally speaking a skillful form carpenter is recognized by the
scarcity of nails he uses. The possibility of reducing carpenter work by
ordering lumber to length and width from plans has already been
mentioned. It is possible often to go a step further by having certain
standard panels, boxes, etc., made in regular shops. Piece work is often
possible and will frequently reduce framing costs. In designing for
economy in taking down, carrying and re-erecting forms a cardinal point
should be that the work be such that it can be executed by common
laborers. This result can be very nearly approached by careful design,
even for form work that is quite complex, if a special gang is devoted
to the work and trained a little in the various operations. Design the
forms so that they come apart in units by simply removing bolts, clamps
and wedges. They can then be taken down, carried and erected by common
laborers with a skilled man in charge to meet emergencies and to true
and line up the work.
In the matter of details the joints deserve particular attention. In
column and girder forms, generally, joints will be square or butt
joints, and to get them tight the lumber must be dressed true to edge.
Tight joints are considered essential by many not only to avoid joint
marks but for the more important reason that otherwise, with wet
mixtures, a honeycombed concrete is produced by leakage. Where tight
joints are desired tongue and groove stock or stock cut with one edge
beveled and the other square give the best results. The authors believe
that the best general satisfaction will be got from the bevel edge stock
placed so that the bevel edge of one board comes against the square edge
of the next board; undue swelling then results in the bevel edge cutting
into the adjacent square edge without bulging. Tongues and grooves
suffer badly from breakage. As a matter of fact square edged stock, if
well dressed and sized and well filled with moisture, can be used and is
used with entire success in nearly all kinds of work. The leakage will
be very slight with ordinarily good butt joints and so far as surface
appearance goes joint marks are more cheaply and more satisfactorily
eliminated by other means than attempting to get cabinet work in form
construction. Where girder forms join columns or beams connect with
girders and at the angles of floor slabs with beams the edges or corners
of the forms should be rounded. The edges of beams and column corners
will appear better if beveled; a triangular strip in the corners of the
forms will provide this bevel. Forms and mold construction for
ornamental work call for and are given special consideration in Chapter
XXIII. In conclusion, the reader should study the specific examples of
form construction for different purposes that are given throughout the
book for hints as to special practice and details.
~UNIT CONSTRUCTION OF FORMS.~--Unit construction has a somewhat variable
meaning in form work. In wall and tank work and in some other kinds of
work unit construction means the use of form units which are gradually
moved ahead or upward as the concreting progresses or of form units
which are used one after another in continuous succession as the
concreting progresses. In column, girder and floor work unit
construction means the division of the form work as a whole and also of
the individual forms into independent structural units; thus in forms
for a building the column forms may be independent of the girder forms
and also each column and girder form be made up of several separate
units. In all cases unit construction has for its purpose the use of the
same form or at least the same form lumber over and over for molding
purposes. Every time the use of the same form is repeated, the cost of
form work per cubic yard of concrete placed is reduced. The theoretical
limit of economical repetition is then the limit of endurance of the
form, the practical limit, however, is something quite different. Most
concrete work varies in form or dimensions often enough to prevent the
use of the same forms more than a few times, and even if these
variations did not exist the time element would enter to prevent the
same form or form lumber being used more than a certain number of times.
Unit construction to give repeated use of forming has, therefore, its
economic limits. The significance of this conclusion does not lie in any
novelty that it possesses but in the fact that for any piece of work it
determines the labor that may profitably be expended in working out and
constructing form units.
~LUBRICATION OF FORMS.~--All forms for concrete require a coating of some
lubricant to prevent the concrete from adhering to the wood with which
it comes in contact. Incidentally this coating tends to give a smoother
surface to the concrete and to preserve the wood against damage by its
alternate wetting and drying. The great value of lubrication is,
however, that it reduces the cost of removing forms. The requisite of a
good coating material is that it shall be thin enough to spread evenly
and to fill the pores and grain of the wood. Crude oil or petroline
makes one of the best coatings, but various other greasy substances will
serve. Where the forms are not to be removed until the concrete has set
hard a thorough wetting of the wood just before the concrete is placed
is all the coating necessary. Any concrete adhering to forms should be
thoroughly cleaned off before they are used again and the wood
underneath given a special heavy coating.
~FALSEWORKS AND BRACING.~--The falseworks which support the forms proper
and stagings for workmen, runways, material hoists, etc., do not call
for any striking differences in construction and arrangement from such
work elsewhere. For wall forms inclined props reaching from ground to
studding are used for walls of moderate height such as retaining walls,
wing walls, and abutments. For building walls of some height a gallows
frame arrangement or the common braced staging used by masons and
carpenters is used. In building construction, however, movable forms are
commonly employed for walls more than one story high and should always
be employed above one story to save staging timber. Column forms are
seldom braced unless erected without connecting girder or floor forms at
their tops, and then only by diagonal props to the floor or ground.
Girder and floor supports usually consist of uprights set under the
girder form at intervals and occasionally under floor slab forms. The
spacing of props and uprights will be regulated by the judgment of the
foreman and boss carpenter; no general rule is applicable, except that
enough lumber must be used to hold the forms rigid and true to line and
level. The various illustrations of actual formwork which follow are the
best guides to good practice.
~TIME FOR AND METHOD OF REMOVING FORMS.~--No exact time schedule for
removing forms is wise in concrete work. Concrete which is mixed wet
sets slower than dry concrete and concrete sets slower in cold weather
than it does in warm weather. Again the time of removal is influenced by
the risk taken by too early removal, and also by the nature of the
stresses in the member to be relieved of support. In all cases the forms
should be removed as soon as possible so that they can be used over
again and so that the concrete may be exposed to the air to hasten
hardening. The following suggestions as to time of removal are general
and must be followed with judgment.
Using dry concrete in warm weather the forms for retaining walls,
pedestals, isolated pillars, etc., can be removed in 12 hours; using wet
or sloppy concrete the time will be increased to 24 hours. In cold
weather the setting is further delayed and inspection is the only safe
guide to follow. Very cold weather delays setting indefinitely. Forms
for small arch work like sewers and culverts may be removed in 18 to 24
hours if dry concrete is used, and in 24 to 48 hours if wet concrete is
used. The time for removing large arch centers should not be less than
14 days for spans up to 50 ft. if the arch is back-filled at once; when
the center is not to be used again it is better to let it stand 28 days.
For very large arches the problem becomes a special one and is
considered in Chapter XVII. In building construction the following
schedule is a common one. Remove the column forms in 7 days and the
sides of the girder forms and the floor lagging in 14 days leaving the
bottom boards of the girder forms and their supports in place for 21
days.
As an example of individual practice the following requirements of a
large firm of concrete contractors are given:
Walls in mass work, 1 to 3 days, or until the concrete will bear
pressure of the thumb without indentation.
Thin walls, in summer, 2 days; in cold weather, 5 days.
Slabs up to 6-ft. span, in summer, 6 days; in cold weather, 2 weeks.
Beams and girders and long span slabs, in summer, 10 days or 2 weeks; in
cold weather, 3 weeks to 1 month. If shores are left without disturbing
them, the time of removal of the sheeting in summer may be reduced to 1
week.
Column forms, in summer, 2 days; in cold weather, 4 days, provided
girders are shored to prevent appreciable weight reaching columns.
Conduits, 2 or 3 days, provided there is not a heavy fill upon them.
Arches, of small size, 1 week; for large arches with heavy dead load, 1
month.
The method of removing forms will vary in detail with the character of
the structure. With proper design and lubrication of forms they will
ordinarily come away from the concrete with a moderate amount of sledge
and bar work. If the work will warrant it, have a special gang under a
competent foreman for removing forms. The organization of this gang and
the procedure it should follow will vary with the nature of the form
work, and they are considered in succeeding chapters for each kind of
work.
~ESTIMATING AND COST OF FORM WORK.~--It is common practice to record the
cost of forms in cents per cubic yard of concrete, giving separately the
cost of lumber and labor. This should be done, but the process of
analysis should be carried further. The records should be so kept as to
show the first cost per 1,000 ft. B. M. of lumber, the number of times
the lumber is used, the labor cost of framing, the labor cost of
erecting and the labor cost of taking down, all expressed in M. ft. B.
M. In this way only is it possible to compare the cost of forms on
different kinds of concrete work, and thus only can accurate predictions
be made of the cost of forms for concrete work having dimensions
differing from work previously done. It is well, also, to make a note of
the number of square feet of exposed concrete surface to which the forms
are applied.
Some of the items mentioned demand brief explanation. Framing and
erecting costs are kept separate for the reason that the framing is done
only once, whereas the erecting occurs two or more times. The lumber
cost, where the material is used more than once, can be computed in two
ways. An example will illustrate the two modes of procedure. In one of
the buildings described in Chapter XIX the lumber cost $30 per M. ft. B.
M. and was used three times. As 34,000 ft. B. M. were required to encase
the 200 cu. yds. of concrete in one floor, including columns, it would
have required 34,000 ÷ 200 = 170 ft. B. M. of lumber at $30 per M. per
cubic yard of concrete if it had been used only once. But since it was
used three times we may call it 170 ft. B. M. at $10 per M. per cubic
yard of concrete, or we may call it 170 ÷ 3 = 57 ft. B. M. at $30 per M.
per cubic yard of concrete. The authors prefer the first method, due to
the fact that it is 170 ft. B. M. that is handled and taken down each
time and it is more consistent to have the lumber cost on the same basis
thus:
170 ft. B. M. of lumber at $10 per M $1.70
170 ft. B. M. handled at $2 per M 0.34
170 ft. B. M. erected at $7 per M 1.19
-----
Total 170 ft. B. M. per cu. yd $3.23
Returning to our main thought, there are three ways of recording the
cost of form work: (1) In cents per cubic yard of concrete; (2) in cents
per square foot of concrete face to which forms are applied, and (3) in
dollars per 1,000 ft. B. M. of lumber used. In all cases the cost of
materials and of labor should be kept separate. It is well if it can be
done to attach a sketch of the forms to the record. So much for the
general method of recording costs in form work.
In estimating the probable cost of forms for any job the following
method will be found reliable: Having the total cubic yards of concrete
in the work and the time limit within which the work must be completed
determine the number of cubic yards that must be placed per day, making
liberal allowances for delays. Next estimate the number of thousands of
feet board measure of forms required to encase the concrete to be placed
in a day. This will give the minimum amount of lumber required, for it
is seldom permissible to remove the forms until the concrete has
hardened over night. Now we come to the very important and puzzling
question of the time element, particularly in work where it is possible
to use the same forms or the same form lumber two or more times.
It has already been pointed out that wet concrete sets more slowly than
dry concrete; that all concrete sets more slowly in cold than in warm
weather, and that the support of forms is necessary a longer time for
pieces subject to bending stress like arches and girders. General
suggestions as to specific times for removing forms have also been
given. Where the specifications state the time of removal the contractor
has a definite guide, but where they do not, as is most often the case,
he must depend very largely on judgment and previous experience. Another
matter which deserves consideration is the use of the forms as staging
for runways or tracks. Such use may result in forms having to stand on
work for sake of their service as trestles much longer than there is any
necessity so far as supporting the concrete is concerned. A derrick or
cableway may often prove cheaper than tieing up form lumber by trying to
make it serve the double purpose of a trestle.
The possibilities of repeated use of forms and of unit construction of
forms have already been noted. This is the next point to be considered
in estimating form lumber. At the expense of a little planning movable
forms can be used to materially reduce the amount of lumber required.
The reader is referred particularly to the chapters on retaining wall,
conduit and building work for specific data on movable form work.
Having estimated the amount of lumber required and the number of times
it can be used the labor cost of framing, erecting and taking down can
be figured. In ordinary retaining wall work forms will cost for framing
and erection from $6 to $7 per M. ft. B. M. To tear down such forms
carefully and to carry the lumber a short distance will cost some $1.50
to $2 per M. ft. B. M. We have then a cost of $7.50 to $9 per M. ft. B.
M. for each time the forms are erected and torn down. Where movable
panels are used and the forms not ripped apart and put together again
each time there is of course only the cost of moving, which may run as
low as 50 cts. per M. ft. B. M. Framing and erecting centers for piers
will run about the same as for retaining wall. At this point it may be
noted that in estimating the cost of forms for plain rectangular piers
the following method will give very accurate results. Ascertain the
surface area of the four sides of the pier. Multiply this area by 2, and
the product will be the number of feet board measure of 2-in. plank
required. Add 40 per cent. to this, and the total will be the number of
feet board measure of 2-in. plank and of upright studs (4×6), spaced 2½
ft. centers. Sometimes 3×6-in. studs are used, and spaced 2 ft. centers,
which requires practically the same percentage (40 per cent.) of timber
for the studs as where 4×6-in. studs are used and spaced 2½ ft. centers.
No allowance is made for timber to brace the studs, since, in pier work,
it is customary to hold the forms together either with bolts or with
ordinary No. 9 telegraph wire, which weighs 0.06 lb. per foot. The
foregoing data can be condensed into a rule that is easily remembered:
_Multiply the number of square feet surface area of the sides and ends
of a concrete pier by 2.8, and the product will be the number of feet
board measure required for sheet plank and studs for the forms._
If the form lumber can be used more than once, divide the number of feet
board measure by the number of times that it can be used, to ascertain
the amount to be charged to each pier. Forms can be erected and taken
down for $8 per M. carpenters being paid $2.50 and laborers $1.50 a day.
Since there are 2.8 ft. B. M. of forms per square foot of surface area
of concrete to be sheeted, it costs 2¼ cts. for the labor of carpenters
per square foot of surface area to be sheeted. If lumber is worth $24
per M., and is used three times, then the lumber itself also costs 2¼
cts. per sq. ft. of surface area of concrete. By dividing the total
number of cubic yards of concrete into the total number of square feet
of area of surface to be sheeted with forms, the area per cubic yard is
obtained. Multiply this area by 4½ cts., and the product is the cost per
cubic yard for material in the forms (assumed to be used three times)
and the labor of erecting it and taking it down.
The cost of framing and erection of forms for building work and of
centers for large arches is a special problem in each case and is
considered in the chapters devoted to those classes of work.
Reading Tips
Use arrow keys to navigate
Press 'N' for next chapter
Press 'P' for previous chapter