Concrete Construction: Methods and Costs by Gillette and Hill

75. Three shifts were worked, each composed as specified for the guard

3908 words  |  Chapter 59

lock, except that the number of tampers and spreaders was doubled, bringing the gang up to 65 men. The average output per gang per shift was 76 batches of concrete and 35 batches of facing mortar. The cost of 2,141 cu. yds. of concrete in this lock was as follows: Item. Total. Per Cu. Yd. 3,010 bbls. Portland cement $9,057 $4.23 1,377 cu. yds. broken stone 1,922 0.90 393 cu. yds. pebbles 354 0.17 459 cu. yds. gravel 310 0.15 500 cu. yds. sand 889 0.42 150,000 ft. B. M. lumber (¼th cost) 600 0.28 Fuel, light, repairs, etc. 253 0.68 Carpenter work 1,472 0.11 Mixing and placing concrete 3,897 1.82 20% cost of plant 650 0.30 ------- ----- Total $19,404 $9.06 The preceding data, made public by Mr. Woermann in 1894, are supplemented by the following information prepared for the authors: "If any criticism was to be made of the concrete masonry erected in 1893 and 1894, it would probably be to the effect that it was too expensive. The cost of the masonry erected during those two seasons was $8 to $9 per cu. yd. Our records showed that about 45 per cent. of this cost was for Portland cement alone, and moreover, that 40 per cent. of the total cement used at a lock was placed in the 8-in. facing and 5-in. coping. So in the seven locks erected in 1895 on the eastern section, the facing was reduced to 3 ins. and the proportions changed from 1-2 to 1-2½. "In 1898 this cost received another severe cut, and Major Marshall's instructions stated that the facing should not exceed 1½ ins. in thickness nor be less than ¾-in., while the layer of fine material on top of the coping was to be only sufficient to cover the stone and gravel. The amount of sand was again increased so that the proportions were 1-3. "The cost of the Portland cement concrete was likewise cheapened by increasing the amount of aggregates. On the earlier work the proportions were 1-2-2-3, while on the work in 1898 the proportions were 1-4-4. The cost of the walls was further cheapened by using Utica cement in the lower steps of the wall, with 2 ft. of Portland cement concrete on the face. The proportions used in the Utica cement concrete were 1-2½-2½. This lower step is one-third of the height, or about 7 ft. [Illustration: Fig. 76.--Sketch Showing Method of Attaching Lagging to Studs, Illinois & Mississippi Canal.] "The forms were of the same character as those used on the first locks, except that for lining the inner face, 3×10-in. hard pine planks were substituted for the 4×8-in. white pine. The hard pine was damaged less by the continuous handling, and the cost was practically the same. There was also an important change made in the manner of fastening the plank to the 8×10-in. posts. A strip 1¾ ins. square was thoroughly nailed to each post, once for all, with 20d. spikes, and the planking was then nailed from the outside, as shown in Fig. 76. This kept the face of the plank in a perfectly smooth condition, and prevented the formation of the little knobs on the face of the concrete which represented all the old nail holes. This style of forming was also easier to take apart after the setting of the concrete. Rough pine planks, 2×12-in., were used for the back of the form, the same as before. "In order to keep ahead of the concrete force it was necessary to use two gangs of carpenters, erecting the forms for the next two locks. Each gang consisted of about 20 carpenters (at $2.25) and 10 helpers (at $1.50); but men were transferred from one to the other, according to the stage of completion of the two locks. In addition to these two gangs, two carpenters were on duty with each concrete shift to put in the steps in the back of the forms. Sufficient lumber was required for the forms for three complete locks, and 14 locks (Nos. 8 to 21) were built. "The same type of mixer has been used as on the earlier work at Milan, namely, a 4-ft. cubical steel box mounted on corners diagonally opposite. On account of the greater number of locks to be built on the eastern section, however, two mixers were found necessary, so that while the concrete force was at work at one lock, the carpenters and helpers were erecting the mixer at the next lock. The facing was mixed by hand. After turning over the dry cement and sand at least twice with shovels, the mixture was then cast through a No. 5 sieve, after which the water was incorporated slowly by the use of a sprinkling can so as to avoid washing. The secret of good concrete, after the selection of good materials, is thorough mixing and hard tamping. Each batch of concrete, consisting of about 1.2 cu. yds. in place, was turned in the mixer for not less than 2 mins. at the rate of 9 revolutions per minute. The amount of tamping is indicated by the fact that about 16 men out of 72 on each shift did nothing but tamp. The rammers used were 6 ins. square and weighed 33 lbs. The bottom of the rammer consisted of three ridges, each 1-in. in height, so as to make more bond between the successive layers. "On the eastern section the top of the lock walls was higher above the ground, as a rule, than at the Milan locks, and the cars were run up an incline with a small hoisting engine. A 15-HP. portable engine and boiler operated the bucket hoist from one pulley, the mixer from the other pulley, and also furnished steam for the hoist which pulled the cars up the incline. The incline made an angle of about 30° with the ground. The practice of carrying on two sections at once was continued the same as on the western section. Each main wall was systematically divided into 11 sections, making each section about 20 ft. long. The corners of the coping were dressed to a quadrant of about 3 ins. radius with a round trowel like those used on cement walks. In fact, the whole method of finishing the coping was the same as is used on concrete walks. The mortar was put on rather wet and then allowed to stand for about 20 mins. before finishing. This allowed the water to come to the surface and prevented the formation of the fine water cracks which are sometimes seen on concrete work. After its final set the coping was covered with several inches of fine gravel which was kept wet for at least a week. "The last concrete laid during the season was in November, on Lock No. 21, and Aqueducts Nos. 2 and 3. Portions of these structures were built when the temperature was below freezing. The water was warmed to about 60° or 70° F., by discharging exhaust steam into the tank. Salt was used only in the facing, simply sufficient to make the water taste saline. The maximum amount used on the coldest night when the temperature was about 20° F. was 1½ per cent. The concrete force on each shift was as follows: Men. Filling and pushing stone car 10 Filling and pushing gravel car 8 Measuring cement 3 Measuring water and cleaning bucket 2 Dumping bucket on top platform 2 Operating mixer 2 Loading concrete cars 1 Pushing and dumping cars on forms 3 Switchmen on forms 2 Spreading concrete in forms 12 Tamping concrete in forms 16 Mixing facing 3 Water boys 2 -- Total laborers 66 Operating hoists 2 Finishing coping 2 Fireman 1 Sub-overseers 2 Overseer 1 -- Total force 74 The cost of material and labor at Lock No. 15 (10-ft. lift), which contains 2,559 cu. yds. of concrete, was as follows: Materials. Per cu. yd. 0.56 bbl. Portland cement (0.96 per cu. yd.) $1.42 0.64 bbl. Utica cement (1.58 per cu. yd.) .30 0.58 cu. yd. stone 1.15 0.60 cu. yd. gravel .52 14 ft. B. M. lumber[F] at $15 per M. .21 0.6 lb. spikes .01 Coal (10 tons in all, at $1.70) .01 0.35 gal. kerosene .03 ----- Total materials $3.65 Labor. Erecting forms ($7 per M.) .45 Removing forms ($2 per M.) .13 Erecting and removing mixer ($161) .06 Loading and unloading materials at yards and lock sites .23 Track laying ($86) .03 Train service (narrow gage road) .09 Delivering materials to mixer .28 Mixing concrete .11 Depositing concrete .21 Tamping concrete .21 Mixing, depositing and tamping, 69 cu. yds. face mortar ($160) .23 General construction ($553) .22 ----- Total labor $2.25 [Footnote F: The lumber was used nearly five times, which accounts for its low cost per cu. yd.] There were 1,430 cu. yds. of Portland cement concrete. 69 cu. yds. of Portland cement mortar facing, and 1,059 cu. yds. of Utica cement concrete. The Portland concrete cost $6.43 per cu. yd.; the Utica concrete, $4.77 per cu. yd. The following is the cost of labor on Lock No. 20 (11-ft. lift.; 2,750 cu. yds.): Per cu. yd. Erecting forms ($7 per M.) $.434 Removing forms ($1.70 per M.) .113 Erecting and removing mixer ($151) .058 Loading and unloading at yards, lock sites, etc. .614 Tracks .024 Train service (narrow gage) .016 Pumping .114 Delivering material to mixer .288 Mixing concrete .134 Depositing concrete .205 Tamping concrete .192 Mixing, depositing and tamping, 85 cu. yds. face mortar .071 General construction .246 ------ Total $2.509 ~COST OF HAND MIXING AND PLACING, CANAL LOCK FOUNDATION.~--Mr. Geo. P. Hawley gives the following record of mixing and placing 4,000 cu. yds. of 1-4½ gravel concrete for the foundation of a lock constructed for the Illinois and Mississippi Canal in 1897. The concrete was mixed on 14×16-ft. board platforms, from which it was shoveled directly into place. The materials were brought to the board in wheelbarrows. Two boards were used, the usual gang for each being 4 men wheeling gravel, 4 men mixing, 1 man sprinkling, 2 men depositing and leveling and 2 men tamping. The two gangs were worked against each other. Ten hours constituted a day's work, and the average time and cost per cubic yard for mixing and placing were: Cts. Foreman, 0.21 hr., at 30 cts 6.30 Laborers, 3.339 hrs., at 15 cts 50.09 Pump runner, 0.129 hr., at 20 cts 3.58 Water boy, 0.087 hr., at 7½ cts 0.65 ----- Total labor per cu. yd., cents. 60.62 ~BREAKWATER AT MARQUETTE, MICH.~--The breakwater extends out from the shore and consists of a prism of concrete resting on timber cribs filled with stone. Originally the cribs carried a timber superstructure; this was removed to give place to the concrete work. A typical cross-section of the concrete prism is shown by Fig. 77; the prism is 23 ft. wide on the base. Farther in shore the base width was reduced to 20 ft., and in the shore section the prism was changed to a triangular trapezoid by continuing the first slope to the bottom cutting off the berm and second slope. The wooden structure was removed to a level 1 ft. below mean low water and on it a concrete footing approximately 2 ft. thick was constructed for the prism proper. This footing reached the full width of the crib and was constructed in various ways during the 5 years through which the work continued. At first the footing concrete was deposited loose under water by means of bottom dumping buckets; later the stone filling of the cribs was simply leveled up by depositing concrete in bags, and last toe and heel blocks were molded and set flush with the sides of the crib and filled between. Methods of construction and records of cost are reported for portions only of the work and these are given here. [Illustration: Fig. 77.--Cross Section of Marquette Breakwater.] _Footing Placed under Water with Buckets._--Besides the material track which was constructed along the old wooden structure the plant consisted of a mixing scow and a derrick scow, which were moored alongside the work. The sand, stone and cement were brought out in cars between working hours and stored on the mixing scow, enough for one day's work at a time. The derrick handled a 40-cu. ft. bottom dump bucket, which sat in a well on the mixing scow with its top flush with the deck. The concrete was mixed by hand on the deck and shoveled into the bucket; the bucket was then handled by the derrick to the crib and lowered and dumped under water. The gang consisted of 24 men, 1 foreman, 1 master laborer, 14 men shoveling and mixing, 3 men wheeling materials, 1 derrick man and 3 men placing and depositing concrete. No record of output of this gang is available. The cost of the concrete in place with wages $1.25 to $1.40 per day for common labor is given as follows: Materials. Per cu. yd. 1.21 bbls. (459 lbs.) cement at $2.20 $2.657 1 cu. yd. stone at $1.58 1.580 0.5 cu. yd. sand at $0.50 0.250 2.02 lbs. burlap at $0.037 0.075 Twine and needles 0.005 ------ Total materials $4.567 Labor. Loading scow with materials $0.4114 Mixing concrete 0.8459 Depositing concrete 0.5242 ------- Total labor $1.7815 Grand total $6.348 These figures are based on some 757 cu. yds. of concrete footing. In explanation of the items of burlap, etc., it should be said that the cribs were carpeted with burlap to prevent waste of concrete into the stone fill. [Illustration: Fig. 78.--Cross Section of Marquette Breakwater Showing Manner of Constructing Footing with Bags of Concrete.] _Leveling Off Cribs with Concrete in Bags._--The sketch, Fig. 78, shows the method of leveling off the cribs with concrete in bags. The concrete was mixed by hand on shore and filled into 8-oz. burlap bags, 6 ft. long and 80 ins. around, holding 2,000 lbs. The bags were filled while lying in position in a skip holding one bag. A skip was lifted by gallows frame and tackle onto a car and run out to the work where the derrick scow handled the skip to the crib, lowered it into the water and dumped the bag. The cost of making and placing some 375 cu. yds. of concrete in bags is given as follows: Materials. Total. Per cu. yd. 453 bbls. cement at $2.627 $1,190.03 $3.173 375 cu. yds. stone at $1.619 607.13 1.619 180 cu. yds. sand at $0.392 70.56 0.188 3,220 yds. burlap at $0.03304 106.39 0.283 Twine and needles 6.36 0.017 --------- ------ Total materials $1,980.47 $5.280 Labor Mixing. 108 hrs. master laborer at $0.21-7/8 $ 23.42 $0.062 1,750 hrs. labor at $0.175 306.25 0.816 Superintendence 12.55 0.033 -------- ------ Total labor mixing $ 342.22 $0.911 Labor transporting. 306 hrs. labor at $0.175 $ 53.55 $0.142 Superintendence 5.25 0.014 -------- ------ Total labor transporting. $ 58.80 $0.156 Labor Depositing. 108 hrs. engineman at $0.25 $ 27.00 $0.072 108 hrs. master laborer at $0.21-7/8 23.42 0.062 510 hrs. labor at $0.175 89.25 0.238 Superintendence 13.25 0.035 -------- ------ Total labor depositing $ 152.92 $0.407 Grand total labor $ 553.94 $1.477 Grand total materials and labor $2,534.41 $6.757 _Molding Footing Blocks._--The blocks used at the toe of the prism were of the form and dimensions shown by Fig. 79. They were molded in a temporary shed heated to 50° to 65° F., and provided with a 2×8-in. dressed plank floor on 12×12-in. sills. The floor formed the bottoms of the block molds. Four molds were used, each consisting of four sides. Three laborers molded one block, 2.22 cu. yds. per day, wheeling, mixing, erecting and removing forms, placing concrete and doing all other work. The cost of making 40 blocks was recorded as follows: Materials. Total. Per cu. yd. 126 bbls. cement at $2.75 $346.50 $3.893 88.9 cu. yds. screenings at $1.10 97.79 1.098 40.1 cu. yds. sand at $0.45 18.04 0.203 5 gals. oil at $0.65 3.25 0.036 ------- ------ Total materials $465.58 $5.230 Labor. 1,000 hrs. labor at $0.125 $125.00 $1.404 Watchman 29.15 0.327 Labor cutting wood for fuel 23.80 0.267 Superintendence 42.66 0.480 ------- ------ Total labor $220.61 $2.478 Total labor and materials $686.19 $7.708 [Illustration: Fig. 79.--Details of Toe Blocks for Footing, Marquette Breakwater.] _Molding Concrete Prism in Place._--The concrete prism was molded in alternate sections 10 ft. long; the form for the isolated sections consisted of eight pieces so constructed that when assembled in place and secured with bolts and turnbuckles the form was self-contained as to strength and required no outside support or bracing. The form once in place, all that remained to be done was to fill it, the block with the gallery through it being molded in one operation. The forms for the connecting blocks consisted of two slope panels, a panel for the harbor face and the gallery form, the blocks previously molded making the other sides of the form. The concrete was mixed by hand on shore, conveyed to the work in 1 cu. yd. cars and shoveled into the forms, where it was rammed with 35-lb. rammers. The following record covers 1,231 cu. yds. of concrete prism. In this concrete some 214 cu. yds. of rubble stone were embedded. The costs given are as follows: Per Materials-- Total. cu. yd. 1,780 bbls. natural cement at $1.068 $1,901.04 $1.545 963½ cu. yds. stone at $1.619 1,559.91 1.267 53½ cu. yds. screenings at $0.392 20.97 0.017 485.6 cu. yds. sand at $0.392 190.36 0.154 Miscellaneous materials 78.15 0.063 --------- ------ Totals $3,750.43 $3.046 Labor Mixing-- 254 hrs. master laborer at $0.21-7/8 $ 55.56 $0.045 4,470 hrs. labor at $0.175 782.42 0.635 Superintendence 18.20 0.015 -------- ------ Total labor mixing $ 856.18 $0.695 Labor Transporting and Placing-- 35 days overseer at $2.33-1/3 $ 81.67 $0.066 1,949 hrs. labor at $0.175 342.07 0.277 Superintendence 34.98 0.028 ------- ------ Total labor transporting and placing $ 458.72 $0.371 Grand total, labor $1,314.90 1.066 Total labor and materials $5,065.33 4.112 No charge is made under materials for rubble stone as the only cost for this was cost of handling and this is included in transporting and placing. ~BREAKWATER, BUFFALO, N. Y.~--The following methods and costs of mixing and placing some 2,561 cu. yds. of concrete are given by Mr. Emile Low, for 10 parapet wall sections and 17 parapet deck sections for a breakwater at Buffalo, N. Y. The concrete used was a 1 cement, 1 gravel, 1 sand grit and 4 unscreened broken stone. One bag of cement was assumed to measure 0.9 cu. ft. The voids in the sand grit and gravel were 27 per cent. and in the unscreened stone 39 per cent. The hardened concrete weighed 152 lbs. per cu. ft. [Illustration: Fig. 80.--Sketch Plan of Concrete Mixing Plant for Buffalo Breakwater.] Figure 80 shows the arrangement of the mixing plant. The mixer was a 5-ft. cube mixer holding 125 cu. ft., mounted on a trestle and operated by a 9×12-in. horizontal engine taking steam from a 4×10-ft. locomotive boiler, also supplying steam to two derrick engines. The material scow contained two pockets for sand, one for gravel and one housed over for cement. Two inside cement men passed out the bags in lots of six to one outside cement man who cut and emptied them into the charging bucket. Three sand shovelers each loaded a 3.6 cu. ft. barrow and wheeled them tandem to the bucket, and two gravel men each loaded a 2.7 cu. ft. barrow and wheeled them tandem to the bucket. The broken stone was loaded by eight shovelers into another bucket, also containing 21.6 cu. ft. The two buckets were alternately hoisted and emptied into the mixer hopper, there being a dump man on the mixer who dumped the buckets and attended to the water supply. A charger put the mixer in operation and when the charge was mixed the car men dumped it into a skip resting on a small car which was then run out on the track under the mixer to the derrick which handled the skip to the work. Derrick A handled the materials from the scows and derrick B handled the mixed concrete. The force on the derricks consisted of two enginemen, four tagmen and the fireman. The ten parapet wall sections containing 841 cu. yds. were built in 46 hours, making 17 batches of 1.07 cu. yds., or 18.2 cu. yds. placed per hour. The 17 parapet deck sections containing 1,720 cu. yds. were built in 88 hours, making 18.8 batches of 1.08 cu. yds., or 19.5 cu. yds. placed per hour. For the parapet deck work the force was increased by 2 men handling materials and 1 man on the mixer. The labor cost of mixing and placing the concrete was as follows: Per Per Loading Gang-- day. cu. yd. 1 assistant foreman 2.00 $0.011 3 cement handlers 5.25 0.029 3 sand shovelers 5.25 0.029 2 gravel shovelers 3.50 0.020 8 stone shovelers 14.00 0.076 1 hooker on 1.75 0.010 ------ ------ Totals $31.75 $0.175 Mixer Gang-- 1 dumpman $ 1.75 $0.010 1 charging man 1.75 0.010 2 car men 3.50 0.020 2 enginemen at $3.25 6.50 0.035 4 tagmen at $2 8.00 0.044 1 fireman 2.00 0.011 ------ ------ Totals $23.50 $0.130 Wall Gang-- 1 Signalman $ 1.75 $0.010 1 dumper 1.75 0.010 6 shovelers at $2 12.00 0.065 4 rammers 7.00 0.038 1 foreman 4.00 0.022 ------ ----- Totals $26.50 $0.145 Grand totals $81.75 $0.450 [Illustration: Fig. 81.--Concrete Blocks for Pier at Port Colborne Harbor.] [Illustration: Fig. 82.--Forms for Molding Blocks, Port Colborne Harbor Pier.] [Illustration: Fig. 83.--Device for Handling Blocks, Port Colborne Harbor Pier.] ~PIER CONSTRUCTION, PORT COLBORNE, ONT.~--In constructing the new harbor at Port Colborne, Ont., on Lake Erie, the piers consisted of parallel rows of timber cribs set the width of the pier apart and filled in and between with stone blasted and dredged from the lake bottom in deepening the harbor. The tops of the cribs terminated below water level and were surmounted by concrete walls set on the outer edges. These walls were filled between with stone and the top of the filling was floored part way or entirely across, as the case might be, with a thick concrete slab. The footings of the walls to just above the water level were made of concrete blocks 4½×4×7 ft., constructed as shown by Fig. 81. The wall above the footing course and the floor slab were of concrete molded in place. The concrete work consisted of molding and setting concrete blocks and of molding concrete wall and slab in place. The blocks were molded on shore, shipped to the work on scows and set in place by a derrick. Figure 82 shows the construction of the forms for molding the blocks; the bottom tie rods passed through the partitions forming the ends of the molds. The sides were removed in 48 hours and used over again. Figure 83 shows the hooks used for handling the molded blocks. Considerable trouble was had in setting these blocks level and close jointed, owing to the difficulty of leveling up the stone filling under water. [Illustration: Fig. 84.--Scow Plant for Mixing and Placing Concrete, Port Colborne Harbor Pier.] The mass concrete was mixed and placed by the scow plant, shown by Fig.

Chapters

1. Chapter 1 2. CHAPTER I.--METHODS AND COST OF SELECTING AND PREPARING 3. CHAPTER II.--THEORY AND PRACTICE OF PROPORTIONING CONCRETE. 25 4. CHAPTER III.--METHODS AND COSTS OF MAKING AND PLACING 5. CHAPTER IV.--METHODS AND COST OF MAKING AND PLACING 6. Introduction--Conveying and Hoisting Devices--Unloading with Grab 7. CHAPTER V.--METHODS AND COST OF DEPOSITING CONCRETE 8. Introduction--Depositing in Closed Buckets; O'Rourke Bucket; Cyclopean 9. CHAPTER VI.--METHODS AND COST OF MAKING AND USING RUBBLE 10. Introduction--Rubble Concrete: Chattahoochee River Dam; Barossa 11. CHAPTER VII.--METHODS AND COST OF LAYING CONCRETE IN 12. Introduction--Lowering the Freezing Point of the Mixing Water; Common 13. CHAPTER VIII.--METHODS AND COST OF FINISHING CONCRETE 14. Introduction--Effect of Design on Form Work--Kind of Lumber--Finish and 15. CHAPTER X.--METHODS AND COST OF CONCRETE PILE AND PIER 16. Introduction--Molding Piles in Place; Method of Constructing Raymond 17. CHAPTER XI.--METHODS AND COST OF HEAVY CONCRETE WORK 18. Introduction--Fortification Work: Gun Emplacement, Staten Island, N. Y., 19. CHAPTER XII.--METHODS AND COST OF CONSTRUCTING BRIDGE 20. Introduction--Rectangular Pier for a Railway Bridge--Backing for 21. CHAPTER XIII.--METHODS AND COST OF CONSTRUCTING RETAINING 22. Introduction--Comparative Economy of Plain and Reinforced Concrete 23. CHAPTER XIV.--METHODS AND COST OF CONSTRUCTING CONCRETE 24. Introduction--Mixtures Employed--Distribution of Stock Piles--Hints on 25. CHAPTER XV.--METHODS AND COST OF CONSTRUCTING SIDEWALKS, 26. Introduction--~Cement Sidewalks:~ General Method of Construction--Bonding 27. CHAPTER XVI.--METHODS AND COST OF LINING TUNNELS AND 28. Introduction--Capitol Hill Tunnel, Pennsylvania R. R., Washington, D. 29. CHAPTER XVII.--METHODS AND COST OF CONSTRUCTING ARCH 30. Introduction--Centers--Mixing and Transporting Concrete; Cableway 31. Introduction--Box Culvert Construction, C., B. & Q. R. R.--Arch Culvert 32. CHAPTER XIX.--METHODS AND COST OF REINFORCED CONCRETE 33. Introduction--Construction, Erection and Removal of Forms: Column Forms; 34. CHAPTER XX.--METHOD AND COST OF BUILDING CONSTRUCTION 35. Introduction--Column, Girder and Slab Construction: Warehouses, 36. CHAPTER XXI.--METHODS AND COST OF AQUEDUCT AND SEWER 37. Introduction--Forms and Centers--Concreting--Reinforced Conduit, Salt 38. CHAPTER XXII.--METHODS AND COST OF CONSTRUCTING RESERVOIRS 39. Introduction--Small Covered Reservoir--500,000 Gallon Covered Reservoir, 40. CHAPTER XXIII.--METHODS AND COST OF CONSTRUCTING ORNAMENTAL 41. Introduction--Separately Molded Ornaments: Wooden Molds; Iron Molds; 42. Introduction--Drilling and Blasting Concrete--Bench Monuments, Chicago, 43. CHAPTER XXV.--METHODS AND COST OF WATERPROOFING CONCRETE 44. CHAPTER I. 45. CHAPTER II. 46. CHAPTER III. 47. CHAPTER IV. 48. 15. The trestle work was made of 12×12-in. timbers and was approximately 49. CHAPTER V. 50. CHAPTER VI. 51. part 1/8 to ½-in. stone or screenings. The sand was one-half river sand 52. CHAPTER VII. 53. CHAPTER VIII. 54. CHAPTER IX. 55. Chapter XXI. Despite this considerable use of metal for special forms 56. Chapter XIX, showing the reduction in lumber cost coming from using the 57. CHAPTER X. 58. CHAPTER XI. 59. 75. Three shifts were worked, each composed as specified for the guard 60. 84. The scow was loaded with sufficient sand and cement for a day's work 61. CHAPTER XII. 62. CHAPTER XIII. 63. 102. In fastening the forms with ties the choice is usually between long 64. Chapter VIII. 65. CHAPTER XIV. 66. CHAPTER XV. 67. Chapter II we can estimate the quantity of cement required for any given 68. CHAPTER XVI. 69. CHAPTER XVII. 70. 155. The exact construction of the forms for one of the larger slabs is 71. CHAPTER XVIII. 72. CHAPTER XIX. 73. Chapter IV. 74. CHAPTER XX. 75. 3. One full depth side form and the side of girder No. 2 formed the mold 76. CHAPTER XXI. 77. CHAPTER XXII. 78. CHAPTER XXIII. 79. 289. Referring first to the end posts, it will be seen that they were 80. CHAPTER XXIV. 81. CHAPTER XXV.

Reading Tips

Use arrow keys to navigate

Press 'N' for next chapter

Press 'P' for previous chapter