Concrete Construction: Methods and Costs by Gillette and Hill
75. Three shifts were worked, each composed as specified for the guard
3908 words | Chapter 59
lock, except that the number of tampers and spreaders was doubled,
bringing the gang up to 65 men. The average output per gang per shift
was 76 batches of concrete and 35 batches of facing mortar. The cost of
2,141 cu. yds. of concrete in this lock was as follows:
Item. Total. Per Cu. Yd.
3,010 bbls. Portland cement $9,057 $4.23
1,377 cu. yds. broken stone 1,922 0.90
393 cu. yds. pebbles 354 0.17
459 cu. yds. gravel 310 0.15
500 cu. yds. sand 889 0.42
150,000 ft. B. M. lumber (¼th cost) 600 0.28
Fuel, light, repairs, etc. 253 0.68
Carpenter work 1,472 0.11
Mixing and placing concrete 3,897 1.82
20% cost of plant 650 0.30
------- -----
Total $19,404 $9.06
The preceding data, made public by Mr. Woermann in 1894, are
supplemented by the following information prepared for the authors:
"If any criticism was to be made of the concrete masonry erected in 1893
and 1894, it would probably be to the effect that it was too expensive.
The cost of the masonry erected during those two seasons was $8 to $9
per cu. yd. Our records showed that about 45 per cent. of this cost was
for Portland cement alone, and moreover, that 40 per cent. of the total
cement used at a lock was placed in the 8-in. facing and 5-in. coping.
So in the seven locks erected in 1895 on the eastern section, the facing
was reduced to 3 ins. and the proportions changed from 1-2 to 1-2½.
"In 1898 this cost received another severe cut, and Major Marshall's
instructions stated that the facing should not exceed 1½ ins. in
thickness nor be less than ¾-in., while the layer of fine material on
top of the coping was to be only sufficient to cover the stone and
gravel. The amount of sand was again increased so that the proportions
were 1-3.
"The cost of the Portland cement concrete was likewise cheapened by
increasing the amount of aggregates. On the earlier work the proportions
were 1-2-2-3, while on the work in 1898 the proportions were 1-4-4. The
cost of the walls was further cheapened by using Utica cement in the
lower steps of the wall, with 2 ft. of Portland cement concrete on the
face. The proportions used in the Utica cement concrete were 1-2½-2½.
This lower step is one-third of the height, or about 7 ft.
[Illustration: Fig. 76.--Sketch Showing Method of Attaching Lagging to
Studs, Illinois & Mississippi Canal.]
"The forms were of the same character as those used on the first locks,
except that for lining the inner face, 3×10-in. hard pine planks were
substituted for the 4×8-in. white pine. The hard pine was damaged less
by the continuous handling, and the cost was practically the same. There
was also an important change made in the manner of fastening the plank
to the 8×10-in. posts. A strip 1¾ ins. square was thoroughly nailed to
each post, once for all, with 20d. spikes, and the planking was then
nailed from the outside, as shown in Fig. 76. This kept the face of the
plank in a perfectly smooth condition, and prevented the formation of
the little knobs on the face of the concrete which represented all the
old nail holes. This style of forming was also easier to take apart
after the setting of the concrete. Rough pine planks, 2×12-in., were
used for the back of the form, the same as before.
"In order to keep ahead of the concrete force it was necessary to use
two gangs of carpenters, erecting the forms for the next two locks. Each
gang consisted of about 20 carpenters (at $2.25) and 10 helpers (at
$1.50); but men were transferred from one to the other, according to the
stage of completion of the two locks. In addition to these two gangs,
two carpenters were on duty with each concrete shift to put in the steps
in the back of the forms. Sufficient lumber was required for the forms
for three complete locks, and 14 locks (Nos. 8 to 21) were built.
"The same type of mixer has been used as on the earlier work at Milan,
namely, a 4-ft. cubical steel box mounted on corners diagonally
opposite. On account of the greater number of locks to be built on the
eastern section, however, two mixers were found necessary, so that while
the concrete force was at work at one lock, the carpenters and helpers
were erecting the mixer at the next lock. The facing was mixed by hand.
After turning over the dry cement and sand at least twice with shovels,
the mixture was then cast through a No. 5 sieve, after which the water
was incorporated slowly by the use of a sprinkling can so as to avoid
washing. The secret of good concrete, after the selection of good
materials, is thorough mixing and hard tamping. Each batch of concrete,
consisting of about 1.2 cu. yds. in place, was turned in the mixer for
not less than 2 mins. at the rate of 9 revolutions per minute. The
amount of tamping is indicated by the fact that about 16 men out of 72
on each shift did nothing but tamp. The rammers used were 6 ins. square
and weighed 33 lbs. The bottom of the rammer consisted of three ridges,
each 1-in. in height, so as to make more bond between the successive
layers.
"On the eastern section the top of the lock walls was higher above the
ground, as a rule, than at the Milan locks, and the cars were run up an
incline with a small hoisting engine. A 15-HP. portable engine and
boiler operated the bucket hoist from one pulley, the mixer from the
other pulley, and also furnished steam for the hoist which pulled the
cars up the incline. The incline made an angle of about 30° with the
ground. The practice of carrying on two sections at once was continued
the same as on the western section. Each main wall was systematically
divided into 11 sections, making each section about 20 ft. long. The
corners of the coping were dressed to a quadrant of about 3 ins. radius
with a round trowel like those used on cement walks. In fact, the whole
method of finishing the coping was the same as is used on concrete
walks. The mortar was put on rather wet and then allowed to stand for
about 20 mins. before finishing. This allowed the water to come to the
surface and prevented the formation of the fine water cracks which are
sometimes seen on concrete work. After its final set the coping was
covered with several inches of fine gravel which was kept wet for at
least a week.
"The last concrete laid during the season was in November, on Lock No.
21, and Aqueducts Nos. 2 and 3. Portions of these structures were built
when the temperature was below freezing. The water was warmed to about
60° or 70° F., by discharging exhaust steam into the tank. Salt was used
only in the facing, simply sufficient to make the water taste saline.
The maximum amount used on the coldest night when the temperature was
about 20° F. was 1½ per cent.
The concrete force on each shift was as follows:
Men.
Filling and pushing stone car 10
Filling and pushing gravel car 8
Measuring cement 3
Measuring water and cleaning bucket 2
Dumping bucket on top platform 2
Operating mixer 2
Loading concrete cars 1
Pushing and dumping cars on forms 3
Switchmen on forms 2
Spreading concrete in forms 12
Tamping concrete in forms 16
Mixing facing 3
Water boys 2
--
Total laborers 66
Operating hoists 2
Finishing coping 2
Fireman 1
Sub-overseers 2
Overseer 1
--
Total force 74
The cost of material and labor at Lock No. 15 (10-ft. lift), which
contains 2,559 cu. yds. of concrete, was as follows:
Materials. Per cu. yd.
0.56 bbl. Portland cement (0.96 per cu. yd.) $1.42
0.64 bbl. Utica cement (1.58 per cu. yd.) .30
0.58 cu. yd. stone 1.15
0.60 cu. yd. gravel .52
14 ft. B. M. lumber[F] at $15 per M. .21
0.6 lb. spikes .01
Coal (10 tons in all, at $1.70) .01
0.35 gal. kerosene .03
-----
Total materials $3.65
Labor.
Erecting forms ($7 per M.) .45
Removing forms ($2 per M.) .13
Erecting and removing mixer ($161) .06
Loading and unloading materials at yards and lock sites .23
Track laying ($86) .03
Train service (narrow gage road) .09
Delivering materials to mixer .28
Mixing concrete .11
Depositing concrete .21
Tamping concrete .21
Mixing, depositing and tamping, 69 cu. yds. face mortar
($160) .23
General construction ($553) .22
-----
Total labor $2.25
[Footnote F: The lumber was used nearly five times, which accounts for
its low cost per cu. yd.]
There were 1,430 cu. yds. of Portland cement concrete. 69 cu. yds. of
Portland cement mortar facing, and 1,059 cu. yds. of Utica cement
concrete. The Portland concrete cost $6.43 per cu. yd.; the Utica
concrete, $4.77 per cu. yd. The following is the cost of labor on Lock
No. 20 (11-ft. lift.; 2,750 cu. yds.):
Per cu. yd.
Erecting forms ($7 per M.) $.434
Removing forms ($1.70 per M.) .113
Erecting and removing mixer ($151) .058
Loading and unloading at yards, lock sites, etc. .614
Tracks .024
Train service (narrow gage) .016
Pumping .114
Delivering material to mixer .288
Mixing concrete .134
Depositing concrete .205
Tamping concrete .192
Mixing, depositing and tamping, 85 cu. yds. face
mortar .071
General construction .246
------
Total $2.509
~COST OF HAND MIXING AND PLACING, CANAL LOCK FOUNDATION.~--Mr. Geo. P.
Hawley gives the following record of mixing and placing 4,000 cu. yds.
of 1-4½ gravel concrete for the foundation of a lock constructed for the
Illinois and Mississippi Canal in 1897. The concrete was mixed on
14×16-ft. board platforms, from which it was shoveled directly into
place. The materials were brought to the board in wheelbarrows. Two
boards were used, the usual gang for each being 4 men wheeling gravel, 4
men mixing, 1 man sprinkling, 2 men depositing and leveling and 2 men
tamping. The two gangs were worked against each other. Ten hours
constituted a day's work, and the average time and cost per cubic yard
for mixing and placing were:
Cts.
Foreman, 0.21 hr., at 30 cts 6.30
Laborers, 3.339 hrs., at 15 cts 50.09
Pump runner, 0.129 hr., at 20 cts 3.58
Water boy, 0.087 hr., at 7½ cts 0.65
-----
Total labor per cu. yd., cents. 60.62
~BREAKWATER AT MARQUETTE, MICH.~--The breakwater extends out from the
shore and consists of a prism of concrete resting on timber cribs filled
with stone. Originally the cribs carried a timber superstructure; this
was removed to give place to the concrete work. A typical cross-section
of the concrete prism is shown by Fig. 77; the prism is 23 ft. wide on
the base. Farther in shore the base width was reduced to 20 ft., and in
the shore section the prism was changed to a triangular trapezoid by
continuing the first slope to the bottom cutting off the berm and second
slope. The wooden structure was removed to a level 1 ft. below mean low
water and on it a concrete footing approximately 2 ft. thick was
constructed for the prism proper. This footing reached the full width of
the crib and was constructed in various ways during the 5 years through
which the work continued. At first the footing concrete was deposited
loose under water by means of bottom dumping buckets; later the stone
filling of the cribs was simply leveled up by depositing concrete in
bags, and last toe and heel blocks were molded and set flush with the
sides of the crib and filled between. Methods of construction and
records of cost are reported for portions only of the work and these are
given here.
[Illustration: Fig. 77.--Cross Section of Marquette Breakwater.]
_Footing Placed under Water with Buckets._--Besides the material track
which was constructed along the old wooden structure the plant
consisted of a mixing scow and a derrick scow, which were moored
alongside the work. The sand, stone and cement were brought out in cars
between working hours and stored on the mixing scow, enough for one
day's work at a time. The derrick handled a 40-cu. ft. bottom dump
bucket, which sat in a well on the mixing scow with its top flush with
the deck. The concrete was mixed by hand on the deck and shoveled into
the bucket; the bucket was then handled by the derrick to the crib and
lowered and dumped under water. The gang consisted of 24 men, 1 foreman,
1 master laborer, 14 men shoveling and mixing, 3 men wheeling materials,
1 derrick man and 3 men placing and depositing concrete. No record of
output of this gang is available. The cost of the concrete in place with
wages $1.25 to $1.40 per day for common labor is given as follows:
Materials. Per cu. yd.
1.21 bbls. (459 lbs.) cement at $2.20 $2.657
1 cu. yd. stone at $1.58 1.580
0.5 cu. yd. sand at $0.50 0.250
2.02 lbs. burlap at $0.037 0.075
Twine and needles 0.005
------
Total materials $4.567
Labor.
Loading scow with materials $0.4114
Mixing concrete 0.8459
Depositing concrete 0.5242
-------
Total labor $1.7815
Grand total $6.348
These figures are based on some 757 cu. yds. of concrete footing. In
explanation of the items of burlap, etc., it should be said that the
cribs were carpeted with burlap to prevent waste of concrete into the
stone fill.
[Illustration: Fig. 78.--Cross Section of Marquette Breakwater Showing
Manner of Constructing Footing with Bags of Concrete.]
_Leveling Off Cribs with Concrete in Bags._--The sketch, Fig. 78, shows
the method of leveling off the cribs with concrete in bags. The concrete
was mixed by hand on shore and filled into 8-oz. burlap bags, 6 ft. long
and 80 ins. around, holding 2,000 lbs. The bags were filled while lying
in position in a skip holding one bag. A skip was lifted by gallows
frame and tackle onto a car and run out to the work where the derrick
scow handled the skip to the crib, lowered it into the water and dumped
the bag. The cost of making and placing some 375 cu. yds. of concrete in
bags is given as follows:
Materials. Total. Per cu. yd.
453 bbls. cement at $2.627 $1,190.03 $3.173
375 cu. yds. stone at $1.619 607.13 1.619
180 cu. yds. sand at $0.392 70.56 0.188
3,220 yds. burlap at $0.03304 106.39 0.283
Twine and needles 6.36 0.017
--------- ------
Total materials $1,980.47 $5.280
Labor Mixing.
108 hrs. master laborer at $0.21-7/8 $ 23.42 $0.062
1,750 hrs. labor at $0.175 306.25 0.816
Superintendence 12.55 0.033
-------- ------
Total labor mixing $ 342.22 $0.911
Labor transporting.
306 hrs. labor at $0.175 $ 53.55 $0.142
Superintendence 5.25 0.014
-------- ------
Total labor transporting. $ 58.80 $0.156
Labor Depositing.
108 hrs. engineman at $0.25 $ 27.00 $0.072
108 hrs. master laborer at $0.21-7/8 23.42 0.062
510 hrs. labor at $0.175 89.25 0.238
Superintendence 13.25 0.035
-------- ------
Total labor depositing $ 152.92 $0.407
Grand total labor $ 553.94 $1.477
Grand total materials and labor $2,534.41 $6.757
_Molding Footing Blocks._--The blocks used at the toe of the prism were
of the form and dimensions shown by Fig. 79. They were molded in a
temporary shed heated to 50° to 65° F., and provided with a 2×8-in.
dressed plank floor on 12×12-in. sills. The floor formed the bottoms of
the block molds. Four molds were used, each consisting of four sides.
Three laborers molded one block, 2.22 cu. yds. per day, wheeling,
mixing, erecting and removing forms, placing concrete and doing all
other work. The cost of making 40 blocks was recorded as follows:
Materials. Total. Per cu. yd.
126 bbls. cement at $2.75 $346.50 $3.893
88.9 cu. yds. screenings at $1.10 97.79 1.098
40.1 cu. yds. sand at $0.45 18.04 0.203
5 gals. oil at $0.65 3.25 0.036
------- ------
Total materials $465.58 $5.230
Labor.
1,000 hrs. labor at $0.125 $125.00 $1.404
Watchman 29.15 0.327
Labor cutting wood for fuel 23.80 0.267
Superintendence 42.66 0.480
------- ------
Total labor $220.61 $2.478
Total labor and materials $686.19 $7.708
[Illustration: Fig. 79.--Details of Toe Blocks for Footing, Marquette
Breakwater.]
_Molding Concrete Prism in Place._--The concrete prism was molded in
alternate sections 10 ft. long; the form for the isolated sections
consisted of eight pieces so constructed that when assembled in place
and secured with bolts and turnbuckles the form was self-contained as to
strength and required no outside support or bracing. The form once in
place, all that remained to be done was to fill it, the block with the
gallery through it being molded in one operation. The forms for the
connecting blocks consisted of two slope panels, a panel for the harbor
face and the gallery form, the blocks previously molded making the other
sides of the form. The concrete was mixed by hand on shore, conveyed to
the work in 1 cu. yd. cars and shoveled into the forms, where it was
rammed with 35-lb. rammers. The following record covers 1,231 cu. yds.
of concrete prism. In this concrete some 214 cu. yds. of rubble stone
were embedded. The costs given are as follows:
Per
Materials-- Total. cu. yd.
1,780 bbls. natural cement at $1.068 $1,901.04 $1.545
963½ cu. yds. stone at $1.619 1,559.91 1.267
53½ cu. yds. screenings at $0.392 20.97 0.017
485.6 cu. yds. sand at $0.392 190.36 0.154
Miscellaneous materials 78.15 0.063
--------- ------
Totals $3,750.43 $3.046
Labor Mixing--
254 hrs. master laborer at $0.21-7/8 $ 55.56 $0.045
4,470 hrs. labor at $0.175 782.42 0.635
Superintendence 18.20 0.015
-------- ------
Total labor mixing $ 856.18 $0.695
Labor Transporting and Placing--
35 days overseer at $2.33-1/3 $ 81.67 $0.066
1,949 hrs. labor at $0.175 342.07 0.277
Superintendence 34.98 0.028
------- ------
Total labor transporting and placing $ 458.72 $0.371
Grand total, labor $1,314.90 1.066
Total labor and materials $5,065.33 4.112
No charge is made under materials for rubble stone as the only cost for
this was cost of handling and this is included in transporting and
placing.
~BREAKWATER, BUFFALO, N. Y.~--The following methods and costs of mixing
and placing some 2,561 cu. yds. of concrete are given by Mr. Emile Low,
for 10 parapet wall sections and 17 parapet deck sections for a
breakwater at Buffalo, N. Y.
The concrete used was a 1 cement, 1 gravel, 1 sand grit and 4 unscreened
broken stone. One bag of cement was assumed to measure 0.9 cu. ft. The
voids in the sand grit and gravel were 27 per cent. and in the
unscreened stone 39 per cent. The hardened concrete weighed 152 lbs. per
cu. ft.
[Illustration: Fig. 80.--Sketch Plan of Concrete Mixing Plant for
Buffalo Breakwater.]
Figure 80 shows the arrangement of the mixing plant. The mixer was a
5-ft. cube mixer holding 125 cu. ft., mounted on a trestle and operated
by a 9×12-in. horizontal engine taking steam from a 4×10-ft. locomotive
boiler, also supplying steam to two derrick engines. The material scow
contained two pockets for sand, one for gravel and one housed over for
cement. Two inside cement men passed out the bags in lots of six to one
outside cement man who cut and emptied them into the charging bucket.
Three sand shovelers each loaded a 3.6 cu. ft. barrow and wheeled them
tandem to the bucket, and two gravel men each loaded a 2.7 cu. ft.
barrow and wheeled them tandem to the bucket. The broken stone was
loaded by eight shovelers into another bucket, also containing 21.6 cu.
ft. The two buckets were alternately hoisted and emptied into the mixer
hopper, there being a dump man on the mixer who dumped the buckets and
attended to the water supply. A charger put the mixer in operation and
when the charge was mixed the car men dumped it into a skip resting on
a small car which was then run out on the track under the mixer to the
derrick which handled the skip to the work. Derrick A handled the
materials from the scows and derrick B handled the mixed concrete. The
force on the derricks consisted of two enginemen, four tagmen and the
fireman.
The ten parapet wall sections containing 841 cu. yds. were built in 46
hours, making 17 batches of 1.07 cu. yds., or 18.2 cu. yds. placed per
hour. The 17 parapet deck sections containing 1,720 cu. yds. were built
in 88 hours, making 18.8 batches of 1.08 cu. yds., or 19.5 cu. yds.
placed per hour. For the parapet deck work the force was increased by 2
men handling materials and 1 man on the mixer. The labor cost of mixing
and placing the concrete was as follows:
Per Per
Loading Gang-- day. cu. yd.
1 assistant foreman 2.00 $0.011
3 cement handlers 5.25 0.029
3 sand shovelers 5.25 0.029
2 gravel shovelers 3.50 0.020
8 stone shovelers 14.00 0.076
1 hooker on 1.75 0.010
------ ------
Totals $31.75 $0.175
Mixer Gang--
1 dumpman $ 1.75 $0.010
1 charging man 1.75 0.010
2 car men 3.50 0.020
2 enginemen at $3.25 6.50 0.035
4 tagmen at $2 8.00 0.044
1 fireman 2.00 0.011
------ ------
Totals $23.50 $0.130
Wall Gang--
1 Signalman $ 1.75 $0.010
1 dumper 1.75 0.010
6 shovelers at $2 12.00 0.065
4 rammers 7.00 0.038
1 foreman 4.00 0.022
------ -----
Totals $26.50 $0.145
Grand totals $81.75 $0.450
[Illustration: Fig. 81.--Concrete Blocks for Pier at Port Colborne
Harbor.]
[Illustration: Fig. 82.--Forms for Molding Blocks, Port Colborne Harbor
Pier.]
[Illustration: Fig. 83.--Device for Handling Blocks, Port Colborne
Harbor Pier.]
~PIER CONSTRUCTION, PORT COLBORNE, ONT.~--In constructing the new harbor
at Port Colborne, Ont., on Lake Erie, the piers consisted of parallel
rows of timber cribs set the width of the pier apart and filled in and
between with stone blasted and dredged from the lake bottom in deepening
the harbor. The tops of the cribs terminated below water level and were
surmounted by concrete walls set on the outer edges. These walls were
filled between with stone and the top of the filling was floored part
way or entirely across, as the case might be, with a thick concrete
slab. The footings of the walls to just above the water level were made
of concrete blocks 4½×4×7 ft., constructed as shown by Fig. 81. The wall
above the footing course and the floor slab were of concrete molded in
place. The concrete work consisted of molding and setting concrete
blocks and of molding concrete wall and slab in place.
The blocks were molded on shore, shipped to the work on scows and set in
place by a derrick. Figure 82 shows the construction of the forms for
molding the blocks; the bottom tie rods passed through the partitions
forming the ends of the molds. The sides were removed in 48 hours and
used over again. Figure 83 shows the hooks used for handling the molded
blocks. Considerable trouble was had in setting these blocks level and
close jointed, owing to the difficulty of leveling up the stone filling
under water.
[Illustration: Fig. 84.--Scow Plant for Mixing and Placing Concrete,
Port Colborne Harbor Pier.]
The mass concrete was mixed and placed by the scow plant, shown by Fig.
Reading Tips
Use arrow keys to navigate
Press 'N' for next chapter
Press 'P' for previous chapter