Concrete Construction: Methods and Costs by Gillette and Hill
CHAPTER XIV.
5979 words | Chapter 65
METHODS AND COST OF CONSTRUCTING CONCRETE FOUNDATIONS FOR PAVEMENTS.
Contractor's skill or want of skill in systematizing and managing labor
counts as high in street work as in any class of concrete construction.
As previously demonstrated, the cost of mixing is a very small portion
of the labor cost of concrete in place; the costs of getting the
materials to the mixer and the mixed concrete to the work are the big
items, and in street work the opportunity for increasing the cost of
these items through mismanagement is magnified by the large area of
operations involved per cubic yard of concrete placed. One cubic yard of
concrete makes 6 sq. yds. of 6-in. pavement foundations and 100 cu. yds.
of concrete make a 6-in. foundation for 300 ft. of 30-ft. street, while
4 to 5 cu. yds. will build 100 ft. of ordinary curb and gutter. Thus the
haulage per cubic yard is considerable at best, and lack of plan in
distributing stock piles and handling the concrete can easily result in
such increased haulage expenses as to change a possible profit into a
certain loss. A little thought and skill in planning street work pays a
good profit.
~MIXTURES EMPLOYED.~--A comparatively lean concrete will serve for
pavement foundations; mixtures of 1-4-8 Portland cement or 1-2-5 natural
cement are amply good and it is folly, ordinarily, to employ richer
mixtures. Until recently, natural cement has been used almost
exclusively; a 1-2-5 natural cement mixture requires about 1.15 bbls. of
cement per cubic yard of concrete. A 1-4-8 Portland cement mixture
requires about 0.7 bbl. of cement per cubic yard. In the opinion of the
authors a considerably leaner mixture of Portland concrete is
sufficiently good when it is well mixed in machine mixers--for a 6-in.,
foundation 0.5 bbl. per cu. yd. The mixtures actually employed are
proportioned about as stated and their cost, or that of any other common
mixture, may easily be computed from Tables XII and XIII, giving for
different mixtures the quantities of cement, sand and stone per cubic
yard of concrete; the product of these quantities and the local prices
of materials in the stock piles gives the cost. When the concrete is
mixed by hand the ordinary labor cost of foundations is 0.4 to 0.5 of a
10-hour day's wages per cubic yard of concrete; occasionally it may be
as low as 0.3 of a day's wages where two mixing gangs are worked side by
side under different foremen and with an exacting contractor. Data for
machine mixing are too few to permit a similar general statement for
machine work, but in one case coming under the authors' observation, the
cost figured out to a little less than 0.2 of a day's wages per cubic
yard.
~DISTRIBUTION OF STOCK PILES.~--Assuming a 30-ft. street and a 1-3-5
concrete laid 6 ins. thick, the quantities of concrete materials
required per lineal foot of street are: Cement 0.60 bbl., sand 0.27 cu.
yd., stone 0.44 cu. yd. The stock piles should be so distributed that
each supplies enough materials for a section of foundation reaching half
way to the next adjacent stock pile on each side, and they should not
contain more or less material, otherwise a surplus remains to be cleaned
up or a deficiency to be supplied by borrowing from another pile. A
little care will ensure the proper distribution and it is well paid for
in money saved by not rehandling surplus or borrowed materials. For a
given mixture and a given width and thickness of foundation, the sizes
of the stock piles are determined by their distance apart and this will
depend upon whether hand or machine mixing is employed and upon the
means adopted for hauling the raw materials and the mixed concrete. It
is worth while always in stock piles of any size, to lay a flooring of
plank particularly under the stone pile; if dumped directly on the
ground it costs half as much again to handle stone. Current practice
warrants everything from a continuous bank, to piles from 1,000 to 1,500
ft. apart, in the spacing of stock piles.
~HINTS ON HAND MIXING.~--All but a small percentage of the concrete
annually laid in street work is hand mixed. The authors are confident
that this condition will disappear as contractors learn more of the
advantages of machine mixing, but it prevails at present. The general
economics of hand mixing are discussed in Chapter II; in street work as
before stated, the big items of labor cost are the costs of handling
materials and the data in Chapter II on these processes deserve special
attention. It is particularly worth noting that it is seldom economical
to handle materials in shovels where carrying is necessary; it is a
common thing in street work to see an attempt to get the stock piles so
close to the mixing board that the material can be handled with shovels,
and this is nearly always an economic error. Street work is readily
measured; in fact, its progress can be seen at a glance, and advantage
can often be taken of this fact to profit by the rivalry of separate
gangs. The authors have known of the labor costs being reduced as much
as 25 per cent., due to pitting one gang against another where each
could see the progress made by the other.
~METHODS OF MACHINE MIXING.~--Concrete mixers have been slow to replace
handwork in laying pavement foundations. In explanation of this fact it
is asserted: (1) That frequent shifting of the mixer causes too much
lost time, and (2) that the principal item of labor cost in street work
is the conveying of materials to and from the mixer, and this item is
the same whether hand or machine mixing be employed. The records of
machine mixer work given elsewhere in this chapter go far, in the
opinion of the authors, toward disproving the accuracy of both
assertions. If the machine used and the methods of work employed are
adapted to the conditions of street work, machine mixing can be employed
to decided advantage.
A continuous and large output is demanded in a mixer for street work;
the perfection of the mixing is within limits a minor consideration.
This at once admits for consideration types of mixers whose product is
classed as unsuitable for reinforced concrete work, and also admits of
speeding up the output of the better types to a point beyond that at
which they turn out their most perfect product. Keeping these facts in
mind either of the following two systems of work may be employed: (1)
Traction plants which travel with the work and deposit concrete in
place, or so nearly in place that little shoveling is necessary; (2)
portable plants which are set up at wide intervals along the work and
which discharge the concrete into carts or dump wagons which distribute
it to the work.
The secret of economic work with plants of the class cited first is the
distribution of the stock piles so as practically to eliminate haulage
from stock pile to mixer. The mixer backs away from the work, its
discharge end being toward the work and its charging end away from it.
Then deposit the materials so as to form a continuous stock pile along
the center of the street; the mixer moving backward from the completed
foundation keeps close to the materials and if the latter are uniformly
distributed in the pile the great bulk of the charging is done by
shoveling direct into the charging bucket. The point to be watched here
is that the shovelers do not have to carry the materials; separate stock
piles within moderate hauling distance by wheelbarrows are a far more
economic arrangement than a continuous pile so irregularly distributed
that much of the material has to be carried even a few paces in shovels.
Economic work with plants of the second class depends upon efficient and
adequate means of hauling the mixed concrete to the work. The plant
should not be shifted oftener than once in 1,000 to 2,000 ft., or, say,
four city blocks. This does away with the possibility of wheelbarrow
haulage; large capacity hand or horse carts must be employed. With 6 cu.
ft. hand carts, such as the Ransome cart, a haul of 500 ft. each way
from the mixer is possible and with horse carts, such as the Briggs,
this economic distance is increased to 1,000 ft. each way from the
mixer. The mixer must be close to the stock pile and it will pay to make
use of improved charging devices. A 6-in. foundation for 2,000 ft. of
30-ft. street calls for 667 cu. yds. of concrete, and if both sides are
curbed at the same time, 100 cu. yds. more are added, or 767 cu. yds. in
all; where intersecting streets are to be paved in both directions from
the mixer plant these amounts are doubled. A very small saving per cubic
yard due to mechanical handling of the materials to the mixer amounts to
the interest on a considerable investment in such plant. A point that
should not be forgotten is that carts such as those named above spread
the concrete in dumping so that little or no shoveling is required.
~FOUNDATION FOR STONE BLOCK PAVEMENT, NEW YORK, N. Y.~--Mr. G. W. Tillson,
in "Street Pavements and Paving Materials," p. 204, gives the following
data on the cost of granite block pavement in New York City in 1899. The
day was 10 hours long:
Per Per Per
Concrete gang-- day. sq. yd. cu. yd.
1 foreman $ 3.00 $0.0125 $0.075
8 mixers on two boards, at $1.25 10.00 0.0416 0.250
4 wheeling stone and sand, at $1.25. 5.00 0.0208 0.125
1 carrying cement and supplying
water, at $1.25 1.25 0.0051 0.031
1 ramming, at $1.25 1.25 0.0051 0.031
------ ------- ------
Total, 240 sq. yds. (40 cu. yds.). $20.50 $0.0851 $0.512
The concrete was shoveled direct from the mixing boards to place.
Cost 1-2-4 concrete-- Per cu. yd.
1-1/3 bbls. natural cement, at $0.90 $1.20
0.95 cu. yd. stone, at $1.25 1.19
0.37 cu. yd. sand, at $1.00 0.37
Labor 0.51
-----
$3.27
In laying 5,167 sq. yds. of granite block pavement on one job in New
York City in 1905, the authors' records show that one laborer mixed and
laid 1.3 cu. yds. of concrete per day in a 6-in. foundation; this is a
very small output. The work was done by contract and the labor cost was
as follows:
Per Per
Item. Total. sq. yd. cu. yd.
28½ days foreman at $3.50 $ 99.75 $0.0193 $0.118
399 days laborers at $1.75 698.25 0.1351 0.826
------- ------- ------
$798.00 $0.1544 $0.944
The average day's wages was $1.86, so that the labor cost was about 0.5
of a day's wages per cubic yard of concrete.
~FOUNDATION FOR PAVEMENT, NEW ORLEANS. LA.~--Mr. Alfred E. Harley states
that in laying concrete foundations for street pavement in New Orleans,
a day's work, in running three mixing boards, covering the full width
of the street, averaged 900 sq. yds., 6 ins. thick, or 150 cu. yds.,
with a gang of 40 men. With wages assumed to be 15 cts. per hour the
labor cost was:
Cts. per cu. yd.
6 men wheeling broken stone 6
3 men wheeling sand 3
1 man wheeling cement 1
2 men opening cement 2
7 men dry mixing 7
8 men taking concrete off 8
3 men tamping 3
3 men grading concrete 3
1 man attending run planks 1
3 water boys 1
2 extra men and 1 foreman 4
--
Total labor cost 39 cts.
~FOUNDATIONS FOR STREET PAVEMENT, TORONTO, CANADA.~--The following cost of
a concrete base for pavements at Toronto has been abstracted from a
report (1892) of the City Engineer, Mr. Granville C. Cunningham. The
concrete was 1-2½-7½ Portland; 2,430 cu. yds. were laid, the thickness
being 6 ins., at the following cost per cubic yard:
0.77 bbl. cement, at $2.78 $2.14
0.76 cu. yd. stone, at $1.91 1.45
0.27 cu. yd. sand and gravel, at $0.80 0.22
Labor (15 cts. per hr) 1.03
-----
Total $4.84
Judging by the low percentage of stone in so lean a mixture as the
above, the concrete was not fully 6 ins. thick as assumed by Mr.
Cunningham. Note that the labor cost was 1½ to 2 times what it would
have been under a good contractor.
~MISCELLANEOUS EXAMPLES OF PAVEMENT FOUNDATION WORK.~--The following
records of pavement foundation work are taken from the note and time
books of one of the authors:
_Case 1._--Laying 6-in. pavement foundation; stone delivered and dumped
upon 2-in. plank laid to receive it. Sand and stone were dumped along
the street, so that the haul in wheelbarrows to mixing board Was about
40 ft. Two gangs of men worked under separate foremen, and each gang
averaged 4.5 cu. yds. concrete per hour. The labor cost was as follows
for 45 cu. yds. per gang:
Per day. Per cu. yd.
4 men filling barrows with stone and sand
ready for the mixers, wages 15 cts.
per hour $6.00 $0.13
10 men, wheeling, mixing and shoveling to
place (3 or 4 steps), wages 15 cts. per
hour 15.00 0.33
2 men ramming, wages 15 cts. per hour 3.00 0.07
1 foreman at 30 cts. per hour and 1 water
boy, 5 cts 3.50 0.08
----- -----
Total $27.50 $0.61
_Case II._--Sometimes it is desirable to know every minute detail cost,
for which purpose the following is given:
----Per cu. yd.----
Day's labor. Cost.
3 men loading stones into barrows $0.06 $0.09
1 man loading sand into barrows 0.02 0.03
2 men ramming 0.04 0.06
1 foreman and 1 water boy equivalent to 0.035 0.05
Wheeling sand and cement to mixing board 0.02 0.03
Wheeling stone to mixing board 0.026 0.04
9 men mixing mortar 0.013 0.02
Mixing stone and mortar 0.049 0.07
Placing concrete (walking 15 ft.) 0.072 0.11
------ -----
Total $0.335 $0.50
In one respect this is not a perfectly fair example (although it
represents ordinary practice), for the mortar was only turned over once
in mixing instead of three times, and the stone was turned only twice
instead of three or four times. Water was used in great abundance, and
by its puddling action probably secured a very fair mixture of cement
and sand, and in that way secured a better mixture than would be
expected from the small amount of labor expended in actual mixing.
About 9 cts. more per cu. yd. spent in mixing would have secured a
perfect concrete without trusting to the water.
_Case III._--Two gangs (34 men) working under separate foremen averaged
600 sq. yds., or 100 cu. yds. of concrete per 10-hour day for a season.
This is equivalent to 3 cu. yds. per man per day. The stone and sand
were wheeled to the mixing board in barrows, mixed and shoveled to
place. Each gang was organized as follows:
Per day. Per cu. yd.
4 men loading barrows $ 6.00 $0.12
9 men mixing and placing 13.50 0.27
2 men tamping 3.00 0.06
1 foreman 2.50 0.05
------ -----
Total $25.00 $0.50
These men worked with great rapidity. The above cost of 50 cts. per cu.
yd. is about as low as any contractor can reasonably expect to mix and
place concrete by hand in pavement work.
_Case IV._--Two gangs of men, 34 in all, working side by side on
separate mixing boards, averaged 720 sq. yds., or 120 cu. yds., per
10-hour day. Each gang was organized as follows:
Per day. Per cu. yd.
6 men loading and wheeling $ 9.00 $0.15
8 men mixing and placing 12.00 0.20
2 men tamping 3.00 0.05
1 foreman 3.00 0.05
------ -----
Total $27.00 $0.45
Instead of shoveling the concrete from the mixing board into place, the
mixers loaded it into barrows and wheeled it to place. The men worked
with great rapidity.
Mr. Irving E. Howe gives the cost of a 6-in. foundation of 1-3-5 natural
cement at Minneapolis, Minn., in 1897, as $2.80 per cu. yd., or $0.467
per sq. yd. Cement cost 76 cts. per barrel and stone and sand cost
delivered $1.15 and 30 cts. respectively. Mixers received $1.75 per
day.
Mr. Niles Meriwether gives the cost of materials and labor for an 8-in.
foundation constructed by day labor (probably colored) at Memphis,
Tenn., in 1893, as follows:
Per sq. yd.
Natural cement at $0.74 per bbl $0.195
Sand at $1.25 per cu. yd 0.075
Stone at $1.87 per cu. yd 0.355
Labor mixing and placing 0.155
-----
Total $0.780
Labor was paid $1.25 to $1.50 per 8-hour day and 1.16 bbls. of cement
were used per cubic yard of concrete. The cost of materials, as will be
noted, was high and the labor seems to have been inefficient.
~FOUNDATIONS FOR BRICK PAVEMENT, CHAMPAIGN, ILL.~--The concrete foundation
for a brick pavement constructed in 1903 was 6 ins. thick; the concrete
used was composed of 1 part natural cement, 3 parts of sand and gravel,
and 3 parts of broken stone. All the materials were mixed with shovels,
and were thrown into place from the board upon which the mixing was
done. The material was brought to the steel mixing board in wheelbarrows
from piles where it had been placed in the middle of the street, the
length of haul being usually from 30 to 60 ft. The foundation was 6 ins.
thick and it cost as follows for materials and labor:
Cost per
cu. yd.
1.2 bbls. cement, at $0.50 $0.600
0.6 cu. yd. sand and gravel, at $1 0.600
0.6 cu. yd. broken stone, at $1.40 0.840
6 men turning with shovels, at $2 0.080
4 men throwing into place, at $2 0.053
2 men handling cement, at $1.75 0.023
1 man wetting with hose, at $1.75 0.012
2 men tamping, at $1.75 0.023
1 man leveling, at $1.75 0.012
6 men wheeling stone, at $1.75 0.070
4 men wheeling gravel, at $1.75 0.047
1 foreman, at $4 0.027
------
$2.387
This is practically 40 cts. per sq. yd., or $2.40 per cu. yd. of
concrete for materials and labor. It is evident from the above
quantities that a cement barrel was assumed to hold about 4.5 cu. ft.,
hence the cement was measured loose in making the 1-3-3 concrete. The
accuracy of the quantities given is open to serious doubt. It will also
be noted that the labor cost of making and placing the concrete was only
35 cts. per cu. yd., wages being nearly $1.85 per day. This is so
remarkably low that some mistake would seem to have been made in the
measurement of the work. The authors do not hesitate to say that no gang
of men ever made any considerable amount of concrete by hand at the rate
of 5.75 cu. yds. per man per day.
[Illustration: Fig. 112.--Foote Continuous Mixer Arranged for Pavement
Foundation Work.]
~FOUNDATION CONSTRUCTION USING CONTINUOUS MIXERS.~--The following are
records of two jobs of pavement foundation work using continuous mixers
with one-horse concrete carts in one instance and wheelbarrows in the
other instance. The mixer used was the Foote mixer, as arranged for the
work being described it is shown by Fig. 112. One particular advantage
of this and similar mixers for street work is that no proportioning or
measuring of the materials is required of the men. The mixers are
provided with an automatic measuring device, by means of which any
desired proportion of cement, sand and stone is delivered to the mixing
trough. The mixer is mounted on trucks, and the hoppers that receive
the sand and stone are comparatively low down. The sand can be wheeled
in barrows up a run plank and dumped into a hopper on one side of the
mixer, and in like manner the gravel or broken stone can be delivered
into a hopper on the other side. The cement is delivered in bags or
buckets to a man who dumps it into a cement hopper directly over the
mixer. All that the operator needs to attend to is to see that the men
keep the hoppers comparatively full. The records of work on the two jobs
mentioned are as follows:
[Illustration: Fig: 113.--Briggs Cart Distributing Concrete for Pavement
Foundation.]
_Job I._--The sand was delivered from the stock pile by a team hitched
to a drag scraper, and was dumped alongside the mixer where two men
shoveled it into the hopper. On the same job the concrete was hauled
away from the mixer in Briggs' concrete carts. With a gang of 30 men and
2 to 4 horses hauling concrete in Briggs' carts, the contractor averaged
1,200 sq. yds., or 200 cu. yds., per day of 10 hours. With wages of
laborers at 15 cts. per hour, and a single horse at the same rate, the
cost of labor was 26 cts. per cu. yd., or less than 4½ cts. per sq. yd.
of concrete base 6 ins. thick. The coal was a nominal item, and did not
add 1 ct. per cu. yd. to the cost. In this case the mixer was set up on
a side street and the concrete was hauled in the carts for a distance of
a block each way from the mixer. At first four carts were used, but as
the concreting approached the mixer, less hauling was required, and
finally only two carts were used. An illustration of a Briggs cart is
given by Fig. 113; it is hauled by one horse, which the driver leads,
and is dumped by an ingenious device operated from the horse's head. The
cart dumps from the bottom and spreads the load in a layer about 8 or 9
ins. thick, so that no greater amount of shoveling is necessary than
when barrows are used. It took about 20 seconds for the cart to back up
and get its load and about 5 seconds to dump and spread the load.
_Job II._--In this job the mixer was charged with wheelbarrows and
wheelbarrows were also employed to take the mixed concrete to the work,
the mixer being moved forward at frequent intervals. The stock piles
were continuous, sand on one side of the street and stone on the other
side. A 1-3-6 Portland cement concrete was used, a very rich mixture for
a 6-in. foundation. The organization of the working gang was as follows:
Men loading and wheeling gravel 8
Men assisting in loading gravel 2
Man dumping barrows into hopper 1
Men loading and wheeling sand 3
Man dumping barrows into hopper 1
Men wheeling concrete in barrows 7
Men spreading concrete 3
Men tamping concrete 2
Man pouring cement into hopper 1
Man operating mixer 1
Man shoveling spilled concrete 1
Man opening cement bags 1
Engineer 1
--
Total men in gang 32
The average day's output of this gang was 150 cu. yds., or 900 sq. yds.
in 8 hours; but on the best day's work the output was 200 cu. yds., or
1,200 sq. yds. in 8 hours, which is a remarkable record for 32 men and a
mixer working only 8 hours.
The following is the labor cost of 8,896 sq. yds. of 4½-in. concrete
foundation for an asphalt pavement constructed in New York City in 1904:
Item. Per sq yd.
Foreman at $3.75 $0.030
Laborers at $1.50 0.242
Teams at $5 0.040
Steam engine at $3.50 0.028
------
Total $0.340
The concrete was a 1-3-6 mixture and was mixed in a Foote mixer. These
costs are compiled from data collected by the authors.
~FOUNDATION CONSTRUCTION FOR STREET RAILWAY TRACK USING CONTINUOUS
MIXERS.~--The following account of the methods and cost of constructing a
concrete foundation for street railway track at St. Louis, Mo., is
compiled from information published by Mr. Richard McCulloch. The work
was done by day labor by the United Railways Co., in 1906. Figure 114
shows the concrete construction. A 1-2½-6½ Portland cement, broken stone
concrete mixed by machine was used.
[Illustration: Fig. 114.--Concrete Foundation for Street Railway Track.]
The material for the concrete was distributed on the street beside the
tracks in advance of the machine, the sand being first deposited, then
the crushed rock piled on that, and finally the cement sacks emptied on
top of this pile. The materials were shoveled from this pile into the
concrete mixing machine without any attempt at hand mixing on the
street. Great care was taken in the delivery of materials on the street
to have exactly the proper quantity of sand, rock and cement, so that
there would be enough for the ballasting of the track to the proper
height and that none would be left over. Each car was marked with its
capacity in cubic feet, and each receiver was furnished with a table by
which he could easily estimate the number of lineal feet of track over
which the load should be distributed.
The concrete mixing machines were designed and built in the shops of the
United Railways Co. Three machines were used in this work, one for each
gang. The machine is composed of a Drake continuous worm mixer, fed by a
chain dragging in a cast-iron trough. The trough is 36 ft. long, so that
there is room for 14 men to shovel into it. Water is sprayed into the
worm after the materials are mixed dry. This water was obtained from the
fire plugs along the route. In the first machine built, the Drake mixer
was 8 ft. long. In the two newer machines the mixer was 10 ft. long.
Both the conveyor and the mixer were motor driven, current being
obtained for this purpose from the trolley wire overhead. Two types of
machines were used, one in which the conveyor trough was straight and 45
in. above the rail, and the other in which the conveyor trough was
lowered back of the mixer, being 25 in. above the rail. The latter type
had the advantage of not requiring such a lift in shoveling, but the
trough is so low that a motor truck cannot be placed underneath it. In
the high machine the mixer is moved forward by a standard motor truck
under the conveyor. In the low machine the mixer is moved by a ratchet
and gear on the truck underneath the mixer. A crew of 27 men is required
to work each machine, and under average conditions concrete for 80 lin.
ft. of single track, amounting to 22 cu. yds., can be discharged per
hour.
The costs of the concrete materials delivered per cubic yard of concrete
were: Cement, per barrel, $1.70; sand, per cu. yd., $0.675, and stone,
per cu. yd., $0.425. The cost of the concrete work per cubic yard and
per lineal foot of track was as follows:
Item. Per lin. ft. Per cu. yd.
Concrete materials $0.791 $2.92
Labor mixing and placing 0.071 0.26
------ -----
Total labor and materials $0.862 $3.18
~FOUNDATION CONSTRUCTION USING BATCH MIXERS AND WAGON HAULAGE, ST. LOUIS,
MO.~--The following record of the method and cost of laying a concrete
foundation for street pavement using machine mixing and wagon haulage is
given by Mr. D. A. Fisher. The foundation was 6 ins. thick. The gravel
was dumped from wagons into a large hopper, raised by a bucket elevator
into bins, and drawn off through gates into receiving hoppers on the
charging platform where the cement was added. The receiving hoppers
discharged into the mixers, which discharged the mixed concrete into a
loading car that dumped into wagons, which delivered it on the street
where wanted. The longest haul in wagons was 30 mins., but careful tests
showed that the concrete had hardened well. The wagons were patent dump
wagons of the drop-bottom type. Mr. Fisher says:
"You may consider the following figures a fair average of the plant
referred to, working to its capacity. To these amounts, however, must be
added the interest on the investment, the cost of wrecking the plant and
the depreciation of the same, superintendence, and the pay roll that
must be maintained in wet weather. I am assuming the street as already
brought to grade and rolled.
"With labor at $1.75 per day of 10 hours, teams at $4, engineer and
foremen at $3, and engine at $5 per day, concrete mixed and put in place
by the above method costs:
Per cu. yd.
To mix $0.12 to $0.15
To deliver to street 0.10 to 0.14
To spread and tamp in place 0.08 to 0.11
--------------
Total $0.30 to $0.40
"The mixers are No. 2½ Smith, sold by the Contractors' Supply Co.,
Chicago, Ill., and a ½ yd. cube, sold by Municipal Engineering &
Contracting Co., Chicago.
"The above figures are on the basis of a batch every 2 minutes, which is
easily maintained by using the loading car, as by this means there will
be no delay in the operation of the plant owing to the irregularity of
the arrival of the teams.
"My experience leads me to believe that a better efficiency can be
obtained by using mixers of 1 cu. yd. capacity, and that the batch
mixer is the only type of machine where any certainty of the proportion
of the mixture is realized."
[Illustration: Fig. 115.--Chicago Improved Cube Traction Mixer for
Pavement Foundation.]
~FOUNDATION CONSTRUCTION USING A TRACTION MIXER.~--In laying a 6-in.
foundation for an asphalt pavement in Buffalo, N. Y., an average of 100
sq. yds., or 16.6 cu. yds., of concrete in place was made per hour using
the traction mixer shown by Fig. 115. This mixer was made by the
Municipal Engineering & Contracting Co., of Chicago, Ill., and consisted
of one of that company's improved cube mixers operated by a gasoline
engine and equipped with the regulation mechanical charging device and
also with a swinging conveyor to deliver the mixed concrete to the work.
The feature of the apparatus in its application to paving work is the
conveyor. This was 25 ft. long and pivoted at the mixer end so as to
swing through an arc of 170°. The mixer discharged into a skip or bucket
traveling on the conveyor frame and discharging over the end spreading
its load anywhere within a radius of 25 ft. In operation the mixer
traveled along the center of the street, backing away from the finished
foundation and toward the stock pile, which was continuous and was
deposited along the center of the street. The bulk of the sand and stone
was thus shoveled direct into the charging bucket and the remainder was
wheeled to the bucket in barrows. As the charging bucket is only 14 ins.
high the barrows could be dumped directly into it from the ground. The
gang worked was 17 including a foreman and one boy, and with this gang
100 sq. yds. of 6-in. foundation was laid per hour. Assuming an average
wage of 20 cts. an hour the cost of mixing and placing the foundation
concrete was 3.4 cts. per sq. yd. or 20.4 cts. per cu. yd. for labor
alone.
~FOUNDATION CONSTRUCTION USING CONTINUOUS MIXER.~--The foundation was 6
ins. thick for an asphalt pavement and was laid in Chicago, Ill. The
concrete used was exceptionally rich for pavement foundation work, it
being a 1-3-6 Lehigh Portland cement, broken stone mixture. The mixing
was done by machine, a mixer made by the Buffalo Concrete Mixer Co.,
Buffalo, N. Y., being used. This mixer was equipped with an elevating
charging hopper and was operated as a continuous mixer. The mixer was
mounted on wheels and was pulled along the center of the street ahead of
the work with its discharge end toward the work. Moves of about 25 to 30
ft. were made, the mixer being pulled ahead for this distance each time
that the concrete came up to its discharge end. The stock piles were
continuous, sand on one side and stone on the other side of the street.
Cement was stored in a pile at each end of the block. All materials were
wheeled from stock piles to mixer in wheelbarrows. The men wheeling sand
and stone loaded their own barrows, wheeled them to the mixer and
discharged them directly into the elevating hopper. No runways were
used, the barrows being wheeled directly on the ground. The cement was
brought in barrows, two or three bags being a load, and dumped alongside
a cement box which was located close to and at one side of the elevating
hopper. A man untied the bags and emptied them into the cement box and
another man scooped the cement out of the box in bucketfuls and emptied
it over the sand and stone in the elevating hopper. The mixer discharged
onto a sheet iron shoveling board, and the concrete was carried in
shovels from shoveling board to place, the length of carry being a
maximum of 25 to 30 ft. Two men were required to pull down the cone of
concrete at the discharge end of the mixer and to keep the stone from
separating and rolling down the sides. The gang was organized as
follows:
No. Men.
Loading and wheeling stone 10
Loading and wheeling sand 3 to 4
Loading and wheeling cement 2
Untieing and emptying cement bags 1
Charging cement to hopper 1
Operating mixer and hopper 1
Pulling down and tending discharge 2
Carrying concrete in shovels 8
Spreading concrete 2
Tamping concrete 2
Sweeping concrete 1
General laborers 3
Foreman 1
Watchman 1
Timekeeper 1
--
Total gang 40
This gang averaged 1,000 sq. yds. of 6-in. foundation per 10-hour day; a
maximum of 1,400 sq. yds. was laid in a day. We have thus an average of
167 cu. yds. and a maximum of 234 cu. yds. of concrete foundation mixed
and placed per 10-hour day. At an average wage of $2 per day the average
labor cost of mixing and placing concrete was 48 cts. per cu. yd. or 8
cts. per sq. yd. of 6-in. foundation. It was stated that the gang was
larger by three men than was ordinarily used owing to certain extra work
being done at the time that the above figures were collected. Taking out
three extra men and the timekeeper and watchman we get 34 men actually
working in mixing and placing concrete. This reduced gang gives us a
labor cost for mixing and placing of about 41 cts. per cu. yd. or 6.8
cts. per sq. yd. of 6-in. foundation.
~FOUNDATION CONSTRUCTION USING A BATCH MIXER.~--The following figures are
an average of several jobs using a Ransome ½-cu. yd. mixer for
constructing 6-in. foundations. The mixer was moved 1,000 ft. at a time
and the work conducted 500 ft. in each direction from each station. The
concrete materials were delivered from stock pile to mixer in
wheelbarrows and the mixed concrete was hauled to the work in
two-wheeled Ransome carts. Run planks were laid for the carts and one
man readily pushed a cart holding 6 cu. ft. The men had to work fast on
the long haul but had an easy time when the haul was short. The
organization of the gang was as follows, wages being $1.50 per day:
10 men loading and wheeling stone $15.00
4 men loading and wheeling sand 6.00
2 men handling cement 3.00
1 fireman 2.00
1 man dumping mixer 1.50
5 men wheeling carts 7.50
3 men spreading and ramming 4.50
1 foreman 3.50
------
Total wages per day $43.00
This gang averaged 1,080 sq. yds. of 6-in. foundation or 180 cu. yds. of
concrete in place per day which gives a labor cost of 24 cts per cu. yd.
or 4 cts. per sq. yd. for mixing and placing.
Reading Tips
Use arrow keys to navigate
Press 'N' for next chapter
Press 'P' for previous chapter