Concrete Construction: Methods and Costs by Gillette and Hill
CHAPTER XIII.
1601 words | Chapter 62
METHODS AND COST OF CONSTRUCTING RETAINING WALLS.
Concrete retaining walls may for construction purposes be divided into
two classes: Plain concrete walls of gravity section and reinforced
concrete walls consisting of a thin slab taking the thrust of the earth
as a cantilever anchored to a base slab or as a flat beam between
counterforts. The reinforced wall requires much less concrete for a
given height than does the plain, gravity wall, but the concrete is more
expensive owing to the reinforcement and to the more complex form of
construction, and, in some measure, to the greater cost of placing the
mixture in narrow forms and around reinforcement. It is common, too, to
require a richer concrete for the reinforced than for the plain wall.
[Illustration: Fig. 98.--Comparison of Plain and Reinforced Sections for
Retaining Walls (C. E. Graff).]
~COMPARATIVE ECONOMY OF PLAIN AND REINFORCED CONCRETE WALLS.~--Prior to
the construction of some 2,000 ft. of retaining wall ranging in height
from 2 ft. to 38 ft., at Seattle, Wash., calculation was made by the
engineers of the Great Northern Ry. to determine the comparative economy
of plain concrete and reinforced concrete sections. The sections assumed
were those shown by Fig. 98, and comparisons were made at heights of 10,
20, 30 and 40 ft., with the following results:
Height in Plain. Reinforced. Per cent.
feet. Cu. yds. per ft. Cu. yds. per ft. Saving.
10 1.63 1.29 20.4
20 4.08 2.59 36.4
30 8.40 4.73 43.3
40 14.70 8.07 45.0
The saving in concrete increased as the height of the wall increased;
for a 40-ft. wall reinforced concrete at nearly double the cost per
cubic yard in place would be as cheap as plain concrete.
[Illustration: Fig. 99.--Comparison of Plain and Reinforced Sections for
Retaining Wall (F. F. Sinks).]
Taking substantially the section of reinforced wall being used on the
Chicago track elevation work of the Chicago, Burlington & Quincy R. R.,
and comparing it with a plain wall as shown by Fig. 99, Mr. F. F. Sinks
obtained the following results:
Plain Wall, Cost per Lineal Foot--
4.8 cu. yds. concrete at $4 $19.20
115 ft. B. M. of forms at $31 3.56
------
Total 4.8 cu. yds. at $4.74 $22.76
Reinforced Wall, Cost per Lineal Foot--
3.46 cu. yds. concrete at $4.10 $14.18
115 ft. B. M. of forms at $31 3.56
109 lbs. reinforcing steel at 3¼ cts. 3.54
1.34 cu. yds. extra fill at 20 cts. 0.27
0.32 cu. yd. extra excavation at 20 cts. 0.06
-----
Total, 3.46 cu. yds. concrete at $6.25 $21.61
The saving in this case was $1.15 per lineal foot of wall with the unit
cost of reinforced concrete in place 24 per cent. greater than the unit
cost of plain concrete. It will be noted that there is some 28 per cent.
less concrete per lineal foot of wall in the reinforced section and also
that this section is so designed that the form work is about as simple
for one section as for the other. Another point to be noticed is that
there is no saving in excavation by using a reinforced section instead
of a gravity section, in fact the excavation runs slightly more for the
reinforced section.
[Illustration: Fig. 100.--Forms for Retaining Wall Work, N. Y. C. & H.
R. R. R.]
~FORM CONSTRUCTION.~--Retaining wall work often affords an opportunity for
constructing the forms in panels and this opportunity should be taken
advantage of when possible. Several of the walls described later give
examples of form work that may be studied with profit in this respect.
Figure 100 shows a panel form construction employed on the New York
Central & Hudson River R. R. The 3×8-in. studs are erected, care being
taken to get them in proper line and to true batter and also to brace
them rigidly by diagonal props. Generally the studding is erected for a
section of wall 50 ft. long at one time. The lagging, made in panels 2½
ft. wide and 10 ft. long, by nailing 2-in. plank to 2×4-in. cleats, is
attached to the studding a panel at a time and beginning at the bottom,
by means of the straps, wedges and blocks shown. Five bottom panels
making a form 2½ ft. high and 50 ft. long are placed first. When the
concrete has been brought up nearly to the top of these panels, a second
row of panels is placed on top of the first. When it is judged that the
concrete is hard enough the lowermost panels are loosened and made free
by removing the wedges, blocks and straps and the panels are drawn out
endwise from behind the studding and used over again for one of the
upper courses. The small size of the panels makes it practicable to lay
bare the concrete while it is yet soft enough to work with a float or to
finish by scrubbing as described in Chapter VIII. In cases where this
object is not sought, panels of much larger size may be used. Working
with panels 2¼×12½ ft. of 2-in. plank it was found that each panel could
be used 16 times before becoming unfit for further use, but as, owing to
the nicety of molded surface demanded, panels were discarded when
showing comparatively small blemishes, this record cannot be taken as a
true indication of the life of such forms. These panel forms are used by
the railway named for long abutments and piers as well as for retaining
walls.
A different type of sectional form construction is illustrated by Figs.
101 and 102. It has been extensively used for retaining wall work by the
Chicago, Burlington & Quincy R. R. The studding and waling are framed in
units as shown. The lagging is framed in panels for the rear of the
wall, for the face of the coping, and for the inclined toe of the wall,
and is ordinary sheathing boards for the main face of the wall. The
make-up of the several panels is shown by the drawings. The reason for
using ordinary sheathing instead of panels for the face of the wall is
stated by Mr. L. J. Hotchkiss, Assistant Bridge Engineer, to be that
"the sections become battered and warped with use, do not fit closely
together, and leave the wall rough when they are removed." The manner of
bracing the form and of anchoring it down against the up-thrust of the
wet concrete is shown by Fig. 102.
Two other examples of sectional form construction are given in the
succeeding descriptions of work for the Grand Central Station terminal
in New York City and for the Chicago Drainage Canal. In the former work
it is notable that panels 51×20 ft. were used, being handled by
locomotive crane. The panels used on the drainage canal work and in the
forms previously described are of sizes that can be taken down and
erected by hand, and the means of handling them should always be given
consideration in deciding on the sizes to be adopted for form panels not
only in wall construction but in any other class of work where sectional
forms may be used. Wet spruce or yellow pine will weigh 4½ lbs. per ft.
B. M., so that a panel 10×2½ ft. made of 2-in. plank and three 2×4-in.
battens will weigh some 225 lbs. In form work where the panels are
removed and re-erected in succession facility in handling is an
important matter. When one figures that he may handle both the concrete
and the form panels with it a cableway or a locomotive crane becomes a
tool well worth considering in heavy wall work.
[Illustration: Fig. 101.--Forms for Retaining Wall Work, C., B. & Q. R.
R.]
Three details in retaining wall form work that are often sources of
annoyance out of proportion to their magnitude are alignment, coping
construction and wall ties. Small variations from line in the face of
the wall are seldom noticeable, but a wavy coping shows at a glance.
For this reason it is often wise to build the coping after the main body
of the wall has been stripped, or if both are built together to provide
in the forms some independent means of lining up the coping molds. In
the form shown by Fig. 101 the latter is done by bracing the coping
panel so as to permit it to be set and lined up independently of the
main form. A separate form for molding the coping after the main body of
the wall is completed may be constructed as shown by Fig. 103. Bolts at
B and C permit the yokes to be collapsed and the form to be shifted
ahead as the work advances. This mold provides for beveling the top
edges of the coping and also the edge of the overhang, and the beveling
or rounding of these edges should never be omitted where a neat
appearance is desired. It is not essential, however, that this finishing
be done in the molds. By stripping the concrete while it is still
pliable the edges can be worked down by the ordinary cement sidewalk
edger.
[Illustration: Fig. 102.--Sketch Showing Method of Bracing Form Shown by
Fig. 101.]
[Illustration: Fig. 103.--Sectional Form for Constructing Coping.]
Wall ties are commonly used to hold the face and back forms to proper
spacing, but occasionally they are not permitted. In the latter case the
bracing must be arranged to hold the forms from tipping inward as well
as from being thrust outward. A good arrangement is that shown by Fig.
Reading Tips
Use arrow keys to navigate
Press 'N' for next chapter
Press 'P' for previous chapter