Concrete Construction: Methods and Costs by Gillette and Hill

84. The scow was loaded with sufficient sand and cement for a day's work

3319 words  |  Chapter 60

and towed to and moored alongside the pier. Forms were set for the wall on top of the block footing. These forms were placed in lengths of 60 to 75 ft. of wall and resembled the block forms with partitions omitted. The bottoms of the rear uprights were held by being wedged into the grooves in the blocks, and the bottoms of the front uprights were held by bolts resting on top of the blocks. The tops of the uprights were held together across the wall by tie bolts. The forms being placed, the mode of procedure was as follows: The crusher fed directly into a measuring box. After some 6 ins. of stone had run into the box the door of the crusher spout was closed. A wheelbarrow load of sand was spread over the stone in the box and over this were emptied and spread two or three bags of cement. Another layer of stone and then of sand and of cement were put in and these operations repeated until the box was full. The box was then hoisted and dumped into the hopper of a gravity mixer of the trough type which ran along a track on the scow and fed directly into the forms. The gang worked consisted of 1 foreman, 1 derrickman and 18 common laborers. This gang placed from 65 to 75 cu. yds. of concrete per day at a labor cost of 50 cts. per cu. yd. [Illustration: Fig. 85.--Cross-Section of Concrete Pier, Superior, Wis.] ~CONCRETE BLOCK PIER, SUPERIOR ENTRY, WIS.~--The methods and cost of constructing a concrete pier 3,023 ft. long and of the cross-section shown by Fig. 85 at Superior entry, Wisconsin, are given in the following paragraphs. _Molds and Molding._--About 80 per cent. of the concrete was deposited in molds under water, according to a plan devised by Major D. D. Galliard, corps of engineers. In brief the concrete was built in place in two tiers of blocks, the lower tier resting directly on piles and being entirely under water and the upper tier being almost entirely above water. As shown by Fig. 85, a pile trestle was built on each side of the proposed pier and a traveler for raising and lowering the molds spanned the space between trestles. The molds were bottomless boxes built in four pieces, two sides and two ends, held together by tie rods. Fig. 86 shows an end and a side of one of the shallow water molds and Fig. 87 shows in detail the method of fastening the end to the side. It will be seen that the 1¼-in. turnbuckle rods pass through the ends of beams that bear against the outside of the mold. These tie rods have eyes at each end in which rods with wedge-shaped ends are inserted. The molds were erected on the trestle by a locomotive crane and were then lifted by the mold traveler, carried and lowered into place. The largest one of these molds with its iron ballast, weighed 40 tons. To remove a mold, after the block had hardened, the nuts on the wedge-ended rods were turned, thus pulling the wedge end from the eye of the tie rod and releasing the sides of the mold from the ends. The locomotive crane then raised the ends and sides, one at a time, and assembled them ready to be lowered again for the next block. The time required to remove one of these 40-ton molds, reassemble and set it again rarely exceeded 60 minutes and was sometimes reduced to 45 minutes. [Illustration: Fig. 86.--Mold for Concrete Block for Pier at Superior, Wis.] The concrete was deposited in alternate blocks and the molds described were for the first blocks; for the intermediate blocks molds of two side pieces alone were used, the blocks already in place serving in lieu of end pieces. The two side pieces were bolted together with three tie rods at each end; the tie rods were encased in a box of 1-in. boards 4×4 ins. inside which served as a strut to prevent the sides from closing together and as a means of permitting the tie rods to be removed after the concrete had set. The mold was knocked down just as was the full mold described above and the boxes encasing the tie rods were left in the concrete. [Illustration: Fig. 87.--Device for Locking End and Side of Mold for Concrete Blocks for Pier at Superior, Wis.] An important feature was the device for handling the molds; this, as before stated, was a traveler, which straddled the pier site, it having a gage of 31 ft. It carried a four-drum engine, the drums of which were actuated, either separately or together, by a worm gear so as to operate positively in lowering as well as in raising. The load was hung from four hooks, depending by double blocks and 5/8-in. wire rope from four trolleys suspended from the trusses of the traveler; this arrangement allowed a lateral adjustment of the mold. The hoisting speed was 6 ft. per minute and the traveling speed 100 ft. per minute. The locomotive crane also deserves mention because it was mounted on a gantry high enough to permit material cars to pass under it on the same trestle, thus making it practicable to work two cranes. [Illustration: Fig. 88.--Bucket for Depositing Concrete Under Water for Pier at Superior, Wis.] The concrete was received from the mixer into drop bottom buckets of the form shown by Fig. 88. The buckets were taken to the work four at once on cars, and there lifted by the locomotive crane and lowered into the mold where they were dumped by tripping a latch connected by rope to the crane. To prevent the concrete from washing, the open tops of the buckets were covered with 3×4 ft. pieces of 12-oz. canvas in which were quilted 110 pieces of 1/16×1×3-in sheets of lead. Two covers were used on each bucket and were attached one to each side of the bucket top so as to fold over the top with a lap. This arrangement was entirely successful for its purpose. _Concrete Mixing._--The proportions of the subaqueous concrete were 1-2½-5 by volume, or 1-2.73-5.78 by weight, cement being assumed to weigh 100 lbs. per cu. ft.; the proportions of the superaqueous concrete were 1-3.12-6.25 by volume, or 1-3.41-7.22 by weight. The dry sand weighed 109.2 lbs. per cu. ft., the voids being 35.1 per cent.; the pebbles weighed 115.5 lbs. per cu. ft., the voids being 31 per cent. The pebbles for the concrete were delivered by contract and were unloaded from scows by clam-shell bucket into a hopper. This hopper fed onto an endless belt conveyor which delivered the pebbles to a rotary screen. Inside this screen water was discharged under a pressure of 60 lbs. per sq. in. from a 4-in. pipe to wash the pebbles. From the screen the pebbles passed through a chute into 4-cu. yd cars which were hauled up an incline to a height of 65 ft. by means of a hoisting engine. The cars were dumped automatically, forming a stock pile. Under the stock pile was a double gallery or tunnel provided with eight chutes through the roof and from these chutes the cars were loaded and hauled by a hoisting engine up an inclined trestle to the bins above the concrete mixer. The sand was handled from the stock pile in the same manner. The cement was loaded in bags on a car in the warehouse, hauled to the mixer and elevated by a sprocket chain elevator. Chutes from the bins delivered the materials into the concrete mixer, which was of the Chicago Improved Cube type, revolving on trunnions about an axial line through diagonal corners of the cube. The mixer possessed the advantage of charging and discharging without stopping. It was driven by a 7×10-in. vertical engine with boiler. The mixer demonstrated its ability to turn out a batch of perfectly mixed concrete every 1-1/3 minutes. It discharged into a hopper provided with a cut-off chute which discharged into the concrete buckets on the cars. _Labor Force and Costs._--In the operation of the plant 55 men were employed, 43 being engaged on actual concrete work and 12 building molds and appliances for future work. The work was done by day labor for the government and the cost of operation was as follows for one typical week, when in six days of eight hours each, the output was 1,383 cu. yds., or an average of 230 cu. yds. per day. The output on one day was considerably below the average on account of an accident to the plant, but this may be considered as typical. Pebbles from Stock Pile to Mixer-- Per cu. yd. 4 laborers at $2 $0.0348 1 engineman at $3 0.0131 Coal, oil and waste at $1.03 0.0043 Sand from Stock Pile to Mixer-- 5 laborers at $2 $0.0434 1 engineman at $2.50 0.0109 Coal, oil and waste at $0.82 0.0035 Cement from Warehouse to Mixer-- 5 laborers at $2 $0.0434 Mixing Concrete-- 1 engineman at $2.50 $0.0109 1 mechanic at $2.50 0.0108 Coal, oil and waste at $1.29 0.0056 Transporting Concrete-- 4 laborers at $2 $0.0348 1 engineman at $3 0.0130 Coal, oil and waste at $0.66 0.0028 Depositing Concrete in Molds-- 4 laborers at $2 $0.0348 1 engineman at $3 0.0130 1 rigger at $3 0.0130 Coal, oil and waste at $1.18 0.0051 Assembling, Transporting, Setting and Removing Molds-- 4 laborers at $2 $0.0347 1 engineman at $3.25 0.0141 1 carpenter at $3 0.0130 1 mechanic at $2.50 0.0109 Coal, oil and waste at $1.39 0.0060 Care of Tracks-- 1 laborer at $2 $0.0086 1 mechanic at $2.50 0.0109 Supplying Coal-- 3 laborers at $2 $0.0260 Blacksmith Work-- 1 laborer at $2 $0.0086 1 blacksmith at $3.25 0.0141 1 waterboy at $0.75 0.0032 ------- Total per cubic yard $0.4473 Add 75% of cost of administration 0.1388 ------- Total labor per cu. yd. $0.5861 The total cost of each cubic yard of concrete in place was estimated to be as follows: Per cu. yd. Ten-elevenths cu. yd. pebbles at $1.085 $0.9864 Ten-twenty seconds cu. yd. sand at $0.00 0.0000 1 26 bbls. cement at $1.77 2.2302 Labor as above given 0.5861 Cost of plant distributed over total yardage 0.8400 ------- Total $4.6427 It will be noted that the sand cost nothing as it was dredged from the trench in which the pier was built, and paid for as dredging. The cost of the plant is distributed over this south pier and over the proposed north pier work on the basis of only 20 per cent. salvage value after the completion of both piers. It is said, however, that 80 per cent. is too high an allowance for the probable depreciation. ~DAM, RICHMOND, INDIANA.~--The dam shown in cross-section in Fig. 89 was built at Richmond, Ind. It was 120 ft. long and was built between the abutments of a dismantled bridge. The concrete was made in the proportion of 1 bbl. Portland cement to 1 cu. yd. of gravel; old iron was used for reinforcement. The foundations were put down by means of a cofferdam which was kept dry by pumping. On completion it was found that there was a tendency to scour in front of the apron and accordingly piling was driven and the intervening space rip-rapped with large stone. Labor was paid as follows per day: Foreman, $3; carpenter, $2.50; cement finisher, $2; laborers, $1.50. The concrete was mixed by hand and wheeled to place in wheelbarrows. The cost of the work was as follows: Materials-- Per cu. yd. 204 bbls. cement at $1.60 $1.485 Sand and gravel 0.800 Lumber 0.610 Tools, hardware, etc. 0.445 ------ Total materials $3.34 Labor-- Clearing and excavating $0.96 Setting forms and mixing concrete 1.01 Pumping 0.27 ----- Total labor $2.24 Total materials and labor $5.58 [Illustration: Fig. 89.--Concrete Dam at Richmond, Ind.] ~DAM AT ROCK ISLAND ARSENAL, ILLINOIS.~--The dam was in the shape of an L with one side 192 ft. and the other side 208 ft. long; it consists of a wall 30½ ft. high, 3½ ft. wide at the top and 6½ ft. wide at the bottom with a counterfort every 16 ft., 26 in all. Each counterfort extended back 16 ft. and was 4 ft. thick for a height of 6 ft. and then 3 ft. thick. There were 3,500 cu. yds. of concrete in the work, which was done by day labor under the direction of the U. S. Engineer in charge. The forms consisted of front and back uprights of 8×10-in. stuff 24 ft. high, connected through the wall by ¾-in. rods which were left in the concrete. The lagging was 2×12-in. plank dressed down 1¾ ins. placed inside the uprights. These forms were built full height in 16-ft. sections with a counterfort coming at the center of each section. Each section contained 95 cu. yds. of concrete and was filled in a day's work. The concrete was a 1-4-7 mixture wet enough to quake when rammed. Run of crusher limestone was used of which 50 per cent. passed a 1-in. sieve, 17 per cent. a No. 3 sieve and 9 per cent. a No. 8 sieve. The concrete was mixed in Cockburn Barrow & Machine Co.'s screw-feed mixer which discharged into 2-in. plank skips 2 ft. wide 5-1/3 ft. long and 14 ins. deep, holding ¼ cu. yd. These skips were taken on cars to a derrick crane overhanging the forms and by it hoisted and dumped into the forms. The derrick was moved along a track at the foot of the wall as the work progressed. The concrete was spread and rammed in 6-in. layers. The men were paid $1.50 per 8-hour's work and the work cost including footing, as follows: Item-- Total. Per cu. yd. Cement $1,500.00 $0.429 Sand 400.00 0.114 Storing and hauling cement 460.00 0.131 Taking sand from barge to mixer 96.00 0.027 Crushing stone 1,450.00 0.414 Mixing concrete 4,825.00 1.378 Placing concrete 1,670.00 0.477 Lumber for forms, etc. 600.00 0.171 Erecting and taking down forms 2,450.00 0.700 ---------- ------ Totals $13,451.00 $3.841 ~DAM AT McCALL FERRY, PA.~--The dam was 2,700 ft. long and 48 ft. high of the cross-section shown by Fig. 90 and with its subsidiary works required some 350,000 cu. yds. of concrete. The plant for mixing and placing the concrete was notable chiefly for its size and cost. Parallel to the dam, which extended straight across the river, and just below its toe a service bridge consisting of a series of 40-ft. concrete arch spans was built across the river. This service bridge was 50 ft. wide and carried four standard gage railway tracks besides a traveling crane track of 44 ft. gage. This very heavy construction of a temporary structure was necessitated by the frequency of floods against which only a solid bridge could stand; it was considered cheaper in the long run to provide a bridge which would certainly last through the work than to chance a structure of less cost which would certainly go out with the floods. The concrete service bridge was designed to be destroyed by blasting when the dam had been completed. The method of construction was to build the dam in alternate 40 ft. sections, mixing the concrete on shore, taking it out along the service bridge in buckets on cars and handling the buckets from cars to forms by traveling cranes. [Illustration: Fig. 90.--Steel Forms for McCall Ferry Dam.] The concrete mixing plant is shown by Fig. 91. Cars loaded with cement, sand and stone were brought in over the tracks carried on the wall tops of the bins and were unloaded respectively into bins A, B and C, of which there were eight sets. Each set supplied material by means of measuring cars to a 1 cu. yd. Smith mixer. Two sets of cars were used for each mixer so that one could be loading while the other was charging. The mixers discharged into 1 cu. yd. buckets set two on a car and eight cars were hauled to the work in train by an 18-ton "dinky." At the work the buckets were picked up by the traveling cranes and the concrete dumped into the forms. Figure 90 shows the construction of the steel forms. Six sets of forms were used. Each set consisted of five frames spaced 10 ft. apart and braced together in the planes parallel to the dam, and each set molded 40 ft. of dam. The lagging consisted of wooden boxes 8½ ft. wide and 10 ft. long. For the vertical face of the dam these boxes were attached by bolts to the vertical post, for the curved face they were bolted to a channel bent to the curve and held by struts from the inclined post of the steel frame. [Illustration: Fig. 91.--Concrete Mixing Plant for McCall Ferry Dam.] In construction the footing and the body of the dam to an elevation of 5 ft. above the beginning of the curve were built continuously across the river; above this elevation the dam was built in alternate 40-ft. sections. The strut back to the service bridge shown in the lower right hand corner of Fig. 90, shows the manner of bracing the first 30-ft. section of the inclined post to hold the lagging for the continuous portion. The lagging was added a piece at a time as concreting progressed. The ends of each set of frames for a 40-ft. section were for the isolated sections closed by timber bulkheads carrying box forms to mold grooves into which the concrete of the intermediate sections would bond. [Illustration: Fig. 92.--Traveler for Concreting Dam, Chaudiere Falls, Quebec.] The concrete used was a 1-3-5 mixture, the stone ranging in size from 2 to 5 ins. Rubble stone from one man size to ½ ton were bedded in the concrete. The capacity of the concrete plant was 2,000 cu. yds. per day or about 250 cu. yds. per mixer per 10-hour day. ~DAM, CHAUDIERE FALLS, QUEBEC.~--The dam was 800 ft. long and from 16 to 20 ft. high, constructed of 1-2-4 concrete with rubble stone embedded. The rubble stones were separated at least 9 ins. horizontally and 12 ins. vertically and were kept 20 ins. from faces. At one point the rubble amounted to 40 per cent. of the volume, but the average for the dam was 25 to 30 per cent. The stone was broken at the work, some by hand, but most by machine, all to pass a 2-in. ring. Hand-broken stone ran very uniform in size and high in voids, often up to 50 per cent. Stone broken by crusher with jaws 2 ins. apart would run 20 to 30 per cent. over 2 ins. in size and give about 45 per cent. voids; with crusher jaws 1½ ins. apart from 98 to 100 per cent. was under 2 ins. in size and contained about 42 per cent. of voids. It was found that if the crushers were kept full all the time the product was much smaller, particularly with Gates gyratory crusher, though a little more than rated power was required when the crusher was thus kept full. This practice secured increased economy in both quantity and quality of product. The concrete was made and placed by means of a movable traveler shown by Fig. 92. Concrete materials were supplied to the charging platform of the traveler by means of a traveling derrick moving on a parallel track. In placing the concrete on the rock bottom it was found necessary in order to secure good bond to scrub the rock with water and brooms and cover it with a bed of 2 ins. of 1-2 mortar. The method of concreting in freezing weather is described in Chapter VII.

Chapters

1. Chapter 1 2. CHAPTER I.--METHODS AND COST OF SELECTING AND PREPARING 3. CHAPTER II.--THEORY AND PRACTICE OF PROPORTIONING CONCRETE. 25 4. CHAPTER III.--METHODS AND COSTS OF MAKING AND PLACING 5. CHAPTER IV.--METHODS AND COST OF MAKING AND PLACING 6. Introduction--Conveying and Hoisting Devices--Unloading with Grab 7. CHAPTER V.--METHODS AND COST OF DEPOSITING CONCRETE 8. Introduction--Depositing in Closed Buckets; O'Rourke Bucket; Cyclopean 9. CHAPTER VI.--METHODS AND COST OF MAKING AND USING RUBBLE 10. Introduction--Rubble Concrete: Chattahoochee River Dam; Barossa 11. CHAPTER VII.--METHODS AND COST OF LAYING CONCRETE IN 12. Introduction--Lowering the Freezing Point of the Mixing Water; Common 13. CHAPTER VIII.--METHODS AND COST OF FINISHING CONCRETE 14. Introduction--Effect of Design on Form Work--Kind of Lumber--Finish and 15. CHAPTER X.--METHODS AND COST OF CONCRETE PILE AND PIER 16. Introduction--Molding Piles in Place; Method of Constructing Raymond 17. CHAPTER XI.--METHODS AND COST OF HEAVY CONCRETE WORK 18. Introduction--Fortification Work: Gun Emplacement, Staten Island, N. Y., 19. CHAPTER XII.--METHODS AND COST OF CONSTRUCTING BRIDGE 20. Introduction--Rectangular Pier for a Railway Bridge--Backing for 21. CHAPTER XIII.--METHODS AND COST OF CONSTRUCTING RETAINING 22. Introduction--Comparative Economy of Plain and Reinforced Concrete 23. CHAPTER XIV.--METHODS AND COST OF CONSTRUCTING CONCRETE 24. Introduction--Mixtures Employed--Distribution of Stock Piles--Hints on 25. CHAPTER XV.--METHODS AND COST OF CONSTRUCTING SIDEWALKS, 26. Introduction--~Cement Sidewalks:~ General Method of Construction--Bonding 27. CHAPTER XVI.--METHODS AND COST OF LINING TUNNELS AND 28. Introduction--Capitol Hill Tunnel, Pennsylvania R. R., Washington, D. 29. CHAPTER XVII.--METHODS AND COST OF CONSTRUCTING ARCH 30. Introduction--Centers--Mixing and Transporting Concrete; Cableway 31. Introduction--Box Culvert Construction, C., B. & Q. R. R.--Arch Culvert 32. CHAPTER XIX.--METHODS AND COST OF REINFORCED CONCRETE 33. Introduction--Construction, Erection and Removal of Forms: Column Forms; 34. CHAPTER XX.--METHOD AND COST OF BUILDING CONSTRUCTION 35. Introduction--Column, Girder and Slab Construction: Warehouses, 36. CHAPTER XXI.--METHODS AND COST OF AQUEDUCT AND SEWER 37. Introduction--Forms and Centers--Concreting--Reinforced Conduit, Salt 38. CHAPTER XXII.--METHODS AND COST OF CONSTRUCTING RESERVOIRS 39. Introduction--Small Covered Reservoir--500,000 Gallon Covered Reservoir, 40. CHAPTER XXIII.--METHODS AND COST OF CONSTRUCTING ORNAMENTAL 41. Introduction--Separately Molded Ornaments: Wooden Molds; Iron Molds; 42. Introduction--Drilling and Blasting Concrete--Bench Monuments, Chicago, 43. CHAPTER XXV.--METHODS AND COST OF WATERPROOFING CONCRETE 44. CHAPTER I. 45. CHAPTER II. 46. CHAPTER III. 47. CHAPTER IV. 48. 15. The trestle work was made of 12×12-in. timbers and was approximately 49. CHAPTER V. 50. CHAPTER VI. 51. part 1/8 to ½-in. stone or screenings. The sand was one-half river sand 52. CHAPTER VII. 53. CHAPTER VIII. 54. CHAPTER IX. 55. Chapter XXI. Despite this considerable use of metal for special forms 56. Chapter XIX, showing the reduction in lumber cost coming from using the 57. CHAPTER X. 58. CHAPTER XI. 59. 75. Three shifts were worked, each composed as specified for the guard 60. 84. The scow was loaded with sufficient sand and cement for a day's work 61. CHAPTER XII. 62. CHAPTER XIII. 63. 102. In fastening the forms with ties the choice is usually between long 64. Chapter VIII. 65. CHAPTER XIV. 66. CHAPTER XV. 67. Chapter II we can estimate the quantity of cement required for any given 68. CHAPTER XVI. 69. CHAPTER XVII. 70. 155. The exact construction of the forms for one of the larger slabs is 71. CHAPTER XVIII. 72. CHAPTER XIX. 73. Chapter IV. 74. CHAPTER XX. 75. 3. One full depth side form and the side of girder No. 2 formed the mold 76. CHAPTER XXI. 77. CHAPTER XXII. 78. CHAPTER XXIII. 79. 289. Referring first to the end posts, it will be seen that they were 80. CHAPTER XXIV. 81. CHAPTER XXV.

Reading Tips

Use arrow keys to navigate

Press 'N' for next chapter

Press 'P' for previous chapter