Concrete Construction: Methods and Costs by Gillette and Hill
84. The scow was loaded with sufficient sand and cement for a day's work
3319 words | Chapter 60
and towed to and moored alongside the pier. Forms were set for the wall
on top of the block footing. These forms were placed in lengths of 60 to
75 ft. of wall and resembled the block forms with partitions omitted.
The bottoms of the rear uprights were held by being wedged into the
grooves in the blocks, and the bottoms of the front uprights were held
by bolts resting on top of the blocks. The tops of the uprights were
held together across the wall by tie bolts. The forms being placed, the
mode of procedure was as follows:
The crusher fed directly into a measuring box. After some 6 ins. of
stone had run into the box the door of the crusher spout was closed. A
wheelbarrow load of sand was spread over the stone in the box and over
this were emptied and spread two or three bags of cement. Another layer
of stone and then of sand and of cement were put in and these operations
repeated until the box was full. The box was then hoisted and dumped
into the hopper of a gravity mixer of the trough type which ran along a
track on the scow and fed directly into the forms. The gang worked
consisted of 1 foreman, 1 derrickman and 18 common laborers. This gang
placed from 65 to 75 cu. yds. of concrete per day at a labor cost of 50
cts. per cu. yd.
[Illustration: Fig. 85.--Cross-Section of Concrete Pier, Superior, Wis.]
~CONCRETE BLOCK PIER, SUPERIOR ENTRY, WIS.~--The methods and cost of
constructing a concrete pier 3,023 ft. long and of the cross-section
shown by Fig. 85 at Superior entry, Wisconsin, are given in the
following paragraphs.
_Molds and Molding._--About 80 per cent. of the concrete was deposited
in molds under water, according to a plan devised by Major D. D.
Galliard, corps of engineers. In brief the concrete was built in place
in two tiers of blocks, the lower tier resting directly on piles and
being entirely under water and the upper tier being almost entirely
above water. As shown by Fig. 85, a pile trestle was built on each side
of the proposed pier and a traveler for raising and lowering the molds
spanned the space between trestles.
The molds were bottomless boxes built in four pieces, two sides and two
ends, held together by tie rods. Fig. 86 shows an end and a side of one
of the shallow water molds and Fig. 87 shows in detail the method of
fastening the end to the side. It will be seen that the 1¼-in.
turnbuckle rods pass through the ends of beams that bear against the
outside of the mold. These tie rods have eyes at each end in which rods
with wedge-shaped ends are inserted. The molds were erected on the
trestle by a locomotive crane and were then lifted by the mold traveler,
carried and lowered into place. The largest one of these molds with its
iron ballast, weighed 40 tons. To remove a mold, after the block had
hardened, the nuts on the wedge-ended rods were turned, thus pulling the
wedge end from the eye of the tie rod and releasing the sides of the
mold from the ends. The locomotive crane then raised the ends and sides,
one at a time, and assembled them ready to be lowered again for the next
block. The time required to remove one of these 40-ton molds, reassemble
and set it again rarely exceeded 60 minutes and was sometimes reduced to
45 minutes.
[Illustration: Fig. 86.--Mold for Concrete Block for Pier at Superior,
Wis.]
The concrete was deposited in alternate blocks and the molds described
were for the first blocks; for the intermediate blocks molds of two side
pieces alone were used, the blocks already in place serving in lieu of
end pieces. The two side pieces were bolted together with three tie rods
at each end; the tie rods were encased in a box of 1-in. boards 4×4 ins.
inside which served as a strut to prevent the sides from closing
together and as a means of permitting the tie rods to be removed after
the concrete had set. The mold was knocked down just as was the full
mold described above and the boxes encasing the tie rods were left in
the concrete.
[Illustration: Fig. 87.--Device for Locking End and Side of Mold for
Concrete Blocks for Pier at Superior, Wis.]
An important feature was the device for handling the molds; this, as
before stated, was a traveler, which straddled the pier site, it having
a gage of 31 ft. It carried a four-drum engine, the drums of which were
actuated, either separately or together, by a worm gear so as to operate
positively in lowering as well as in raising. The load was hung from
four hooks, depending by double blocks and 5/8-in. wire rope from four
trolleys suspended from the trusses of the traveler; this arrangement
allowed a lateral adjustment of the mold. The hoisting speed was 6 ft.
per minute and the traveling speed 100 ft. per minute. The locomotive
crane also deserves mention because it was mounted on a gantry high
enough to permit material cars to pass under it on the same trestle,
thus making it practicable to work two cranes.
[Illustration: Fig. 88.--Bucket for Depositing Concrete Under Water for
Pier at Superior, Wis.]
The concrete was received from the mixer into drop bottom buckets of the
form shown by Fig. 88. The buckets were taken to the work four at once
on cars, and there lifted by the locomotive crane and lowered into the
mold where they were dumped by tripping a latch connected by rope to the
crane. To prevent the concrete from washing, the open tops of the
buckets were covered with 3×4 ft. pieces of 12-oz. canvas in which were
quilted 110 pieces of 1/16×1×3-in sheets of lead. Two covers were used
on each bucket and were attached one to each side of the bucket top so
as to fold over the top with a lap. This arrangement was entirely
successful for its purpose.
_Concrete Mixing._--The proportions of the subaqueous concrete were
1-2½-5 by volume, or 1-2.73-5.78 by weight, cement being assumed to
weigh 100 lbs. per cu. ft.; the proportions of the superaqueous concrete
were 1-3.12-6.25 by volume, or 1-3.41-7.22 by weight. The dry sand
weighed 109.2 lbs. per cu. ft., the voids being 35.1 per cent.; the
pebbles weighed 115.5 lbs. per cu. ft., the voids being 31 per cent.
The pebbles for the concrete were delivered by contract and were
unloaded from scows by clam-shell bucket into a hopper. This hopper fed
onto an endless belt conveyor which delivered the pebbles to a rotary
screen. Inside this screen water was discharged under a pressure of 60
lbs. per sq. in. from a 4-in. pipe to wash the pebbles. From the screen
the pebbles passed through a chute into 4-cu. yd cars which were hauled
up an incline to a height of 65 ft. by means of a hoisting engine. The
cars were dumped automatically, forming a stock pile. Under the stock
pile was a double gallery or tunnel provided with eight chutes through
the roof and from these chutes the cars were loaded and hauled by a
hoisting engine up an inclined trestle to the bins above the concrete
mixer. The sand was handled from the stock pile in the same manner. The
cement was loaded in bags on a car in the warehouse, hauled to the mixer
and elevated by a sprocket chain elevator.
Chutes from the bins delivered the materials into the concrete mixer,
which was of the Chicago Improved Cube type, revolving on trunnions
about an axial line through diagonal corners of the cube. The mixer
possessed the advantage of charging and discharging without stopping. It
was driven by a 7×10-in. vertical engine with boiler. The mixer
demonstrated its ability to turn out a batch of perfectly mixed concrete
every 1-1/3 minutes. It discharged into a hopper provided with a cut-off
chute which discharged into the concrete buckets on the cars.
_Labor Force and Costs._--In the operation of the plant 55 men were
employed, 43 being engaged on actual concrete work and 12 building molds
and appliances for future work. The work was done by day labor for the
government and the cost of operation was as follows for one typical
week, when in six days of eight hours each, the output was 1,383 cu.
yds., or an average of 230 cu. yds. per day. The output on one day was
considerably below the average on account of an accident to the plant,
but this may be considered as typical.
Pebbles from Stock Pile to Mixer-- Per cu. yd.
4 laborers at $2 $0.0348
1 engineman at $3 0.0131
Coal, oil and waste at $1.03 0.0043
Sand from Stock Pile to Mixer--
5 laborers at $2 $0.0434
1 engineman at $2.50 0.0109
Coal, oil and waste at $0.82 0.0035
Cement from Warehouse to Mixer--
5 laborers at $2 $0.0434
Mixing Concrete--
1 engineman at $2.50 $0.0109
1 mechanic at $2.50 0.0108
Coal, oil and waste at $1.29 0.0056
Transporting Concrete--
4 laborers at $2 $0.0348
1 engineman at $3 0.0130
Coal, oil and waste at $0.66 0.0028
Depositing Concrete in Molds--
4 laborers at $2 $0.0348
1 engineman at $3 0.0130
1 rigger at $3 0.0130
Coal, oil and waste at $1.18 0.0051
Assembling, Transporting, Setting and Removing Molds--
4 laborers at $2 $0.0347
1 engineman at $3.25 0.0141
1 carpenter at $3 0.0130
1 mechanic at $2.50 0.0109
Coal, oil and waste at $1.39 0.0060
Care of Tracks--
1 laborer at $2 $0.0086
1 mechanic at $2.50 0.0109
Supplying Coal--
3 laborers at $2 $0.0260
Blacksmith Work--
1 laborer at $2 $0.0086
1 blacksmith at $3.25 0.0141
1 waterboy at $0.75 0.0032
-------
Total per cubic yard $0.4473
Add 75% of cost of administration 0.1388
-------
Total labor per cu. yd. $0.5861
The total cost of each cubic yard of concrete in place was estimated to
be as follows:
Per cu. yd.
Ten-elevenths cu. yd. pebbles at $1.085 $0.9864
Ten-twenty seconds cu. yd. sand at $0.00 0.0000
1 26 bbls. cement at $1.77 2.2302
Labor as above given 0.5861
Cost of plant distributed over total yardage 0.8400
-------
Total $4.6427
It will be noted that the sand cost nothing as it was dredged from the
trench in which the pier was built, and paid for as dredging. The cost
of the plant is distributed over this south pier and over the proposed
north pier work on the basis of only 20 per cent. salvage value after
the completion of both piers. It is said, however, that 80 per cent. is
too high an allowance for the probable depreciation.
~DAM, RICHMOND, INDIANA.~--The dam shown in cross-section in Fig. 89 was
built at Richmond, Ind. It was 120 ft. long and was built between the
abutments of a dismantled bridge. The concrete was made in the
proportion of 1 bbl. Portland cement to 1 cu. yd. of gravel; old iron
was used for reinforcement. The foundations were put down by means of a
cofferdam which was kept dry by pumping. On completion it was found that
there was a tendency to scour in front of the apron and accordingly
piling was driven and the intervening space rip-rapped with large
stone. Labor was paid as follows per day: Foreman, $3; carpenter, $2.50;
cement finisher, $2; laborers, $1.50. The concrete was mixed by hand and
wheeled to place in wheelbarrows. The cost of the work was as follows:
Materials-- Per cu. yd.
204 bbls. cement at $1.60 $1.485
Sand and gravel 0.800
Lumber 0.610
Tools, hardware, etc. 0.445
------
Total materials $3.34
Labor--
Clearing and excavating $0.96
Setting forms and mixing concrete 1.01
Pumping 0.27
-----
Total labor $2.24
Total materials and labor $5.58
[Illustration: Fig. 89.--Concrete Dam at Richmond, Ind.]
~DAM AT ROCK ISLAND ARSENAL, ILLINOIS.~--The dam was in the shape of an L
with one side 192 ft. and the other side 208 ft. long; it consists of a
wall 30½ ft. high, 3½ ft. wide at the top and 6½ ft. wide at the bottom
with a counterfort every 16 ft., 26 in all. Each counterfort extended
back 16 ft. and was 4 ft. thick for a height of 6 ft. and then 3 ft.
thick. There were 3,500 cu. yds. of concrete in the work, which was done
by day labor under the direction of the U. S. Engineer in charge.
The forms consisted of front and back uprights of 8×10-in. stuff 24 ft.
high, connected through the wall by ¾-in. rods which were left in the
concrete. The lagging was 2×12-in. plank dressed down 1¾ ins. placed
inside the uprights. These forms were built full height in 16-ft.
sections with a counterfort coming at the center of each section. Each
section contained 95 cu. yds. of concrete and was filled in a day's
work. The concrete was a 1-4-7 mixture wet enough to quake when rammed.
Run of crusher limestone was used of which 50 per cent. passed a 1-in.
sieve, 17 per cent. a No. 3 sieve and 9 per cent. a No. 8 sieve. The
concrete was mixed in Cockburn Barrow & Machine Co.'s screw-feed mixer
which discharged into 2-in. plank skips 2 ft. wide 5-1/3 ft. long and 14
ins. deep, holding ¼ cu. yd. These skips were taken on cars to a derrick
crane overhanging the forms and by it hoisted and dumped into the forms.
The derrick was moved along a track at the foot of the wall as the work
progressed. The concrete was spread and rammed in 6-in. layers. The men
were paid $1.50 per 8-hour's work and the work cost including footing,
as follows:
Item-- Total. Per cu. yd.
Cement $1,500.00 $0.429
Sand 400.00 0.114
Storing and hauling cement 460.00 0.131
Taking sand from barge to mixer 96.00 0.027
Crushing stone 1,450.00 0.414
Mixing concrete 4,825.00 1.378
Placing concrete 1,670.00 0.477
Lumber for forms, etc. 600.00 0.171
Erecting and taking down forms 2,450.00 0.700
---------- ------
Totals $13,451.00 $3.841
~DAM AT McCALL FERRY, PA.~--The dam was 2,700 ft. long and 48 ft. high of
the cross-section shown by Fig. 90 and with its subsidiary works
required some 350,000 cu. yds. of concrete. The plant for mixing and
placing the concrete was notable chiefly for its size and cost. Parallel
to the dam, which extended straight across the river, and just below its
toe a service bridge consisting of a series of 40-ft. concrete arch
spans was built across the river. This service bridge was 50 ft. wide
and carried four standard gage railway tracks besides a traveling crane
track of 44 ft. gage. This very heavy construction of a temporary
structure was necessitated by the frequency of floods against which only
a solid bridge could stand; it was considered cheaper in the long run to
provide a bridge which would certainly last through the work than to
chance a structure of less cost which would certainly go out with the
floods. The concrete service bridge was designed to be destroyed by
blasting when the dam had been completed. The method of construction was
to build the dam in alternate 40 ft. sections, mixing the concrete on
shore, taking it out along the service bridge in buckets on cars and
handling the buckets from cars to forms by traveling cranes.
[Illustration: Fig. 90.--Steel Forms for McCall Ferry Dam.]
The concrete mixing plant is shown by Fig. 91. Cars loaded with cement,
sand and stone were brought in over the tracks carried on the wall tops
of the bins and were unloaded respectively into bins A, B and C,
of which there were eight sets. Each set supplied material by means of
measuring cars to a 1 cu. yd. Smith mixer. Two sets of cars were used
for each mixer so that one could be loading while the other was
charging. The mixers discharged into 1 cu. yd. buckets set two on a car
and eight cars were hauled to the work in train by an 18-ton "dinky." At
the work the buckets were picked up by the traveling cranes and the
concrete dumped into the forms. Figure 90 shows the construction of the
steel forms. Six sets of forms were used. Each set consisted of five
frames spaced 10 ft. apart and braced together in the planes parallel to
the dam, and each set molded 40 ft. of dam. The lagging consisted of
wooden boxes 8½ ft. wide and 10 ft. long. For the vertical face of the
dam these boxes were attached by bolts to the vertical post, for the
curved face they were bolted to a channel bent to the curve and held by
struts from the inclined post of the steel frame.
[Illustration: Fig. 91.--Concrete Mixing Plant for McCall Ferry Dam.]
In construction the footing and the body of the dam to an elevation of 5
ft. above the beginning of the curve were built continuously across the
river; above this elevation the dam was built in alternate 40-ft.
sections. The strut back to the service bridge shown in the lower right
hand corner of Fig. 90, shows the manner of bracing the first 30-ft.
section of the inclined post to hold the lagging for the continuous
portion. The lagging was added a piece at a time as concreting
progressed. The ends of each set of frames for a 40-ft. section were for
the isolated sections closed by timber bulkheads carrying box forms to
mold grooves into which the concrete of the intermediate sections would
bond.
[Illustration: Fig. 92.--Traveler for Concreting Dam, Chaudiere Falls,
Quebec.]
The concrete used was a 1-3-5 mixture, the stone ranging in size from 2
to 5 ins. Rubble stone from one man size to ½ ton were bedded in the
concrete. The capacity of the concrete plant was 2,000 cu. yds. per day
or about 250 cu. yds. per mixer per 10-hour day.
~DAM, CHAUDIERE FALLS, QUEBEC.~--The dam was 800 ft. long and from 16 to
20 ft. high, constructed of 1-2-4 concrete with rubble stone embedded.
The rubble stones were separated at least 9 ins. horizontally and 12
ins. vertically and were kept 20 ins. from faces. At one point the
rubble amounted to 40 per cent. of the volume, but the average for the
dam was 25 to 30 per cent. The stone was broken at the work, some by
hand, but most by machine, all to pass a 2-in. ring. Hand-broken stone
ran very uniform in size and high in voids, often up to 50 per cent.
Stone broken by crusher with jaws 2 ins. apart would run 20 to 30 per
cent. over 2 ins. in size and give about 45 per cent. voids; with
crusher jaws 1½ ins. apart from 98 to 100 per cent. was under 2 ins. in
size and contained about 42 per cent. of voids. It was found that if the
crushers were kept full all the time the product was much smaller,
particularly with Gates gyratory crusher, though a little more than
rated power was required when the crusher was thus kept full. This
practice secured increased economy in both quantity and quality of
product. The concrete was made and placed by means of a movable traveler
shown by Fig. 92. Concrete materials were supplied to the charging
platform of the traveler by means of a traveling derrick moving on a
parallel track. In placing the concrete on the rock bottom it was found
necessary in order to secure good bond to scrub the rock with water and
brooms and cover it with a bed of 2 ins. of 1-2 mortar. The method of
concreting in freezing weather is described in Chapter VII.
Reading Tips
Use arrow keys to navigate
Press 'N' for next chapter
Press 'P' for previous chapter