Concrete Construction: Methods and Costs by Gillette and Hill
CHAPTER XI.
5159 words | Chapter 58
METHODS AND COST OF HEAVY CONCRETE WORK IN FORTIFICATIONS, LOCKS, DAMS,
BREAKWATERS AND PIERS.
The construction problem in building concrete structures of massive form
and volume is chiefly a problem of plant arrangement and organization of
plant operations. In most such work form construction is simple and of
such character that it offers no delay to placing the concrete as
rapidly as it can be produced. The same is true of the character of the
structure, it is seldom necessary for one part of the work to wait on
the setting and hardening of another part. As a rule, there is no
reinforcement to fabricate and place and where there is it is of such
simple character as not to influence the main task of mixing, handling,
and placing concrete. Stated broadly, the contractor in such work
generally has a certain large amount of concrete to manufacture,
transport and deposit in a certain space with nothing to limit the
rapidity of these operations, except the limitations of plant capacity
and management. Installation and operation of mixing and conveying
plant, then are matters to be considered carefully in heavy concrete
work.
In the following sections we have given one or more examples of nearly
every kind of heavy concrete work excepting bridge foundations and
retaining walls, which are considered in Chapters XII and XIII, and
except rubble concrete work, which is considered in Chapter VI. In each
case so far as the available records made it possible, we have given an
account of the plant used and of its operation.
~FORTIFICATION WORK.~--Concrete for fortification work consists very
largely of heavy platforms and walls for gun foundations and enclosures
and of heavily roofed galleries and chambers for machinery and
ammunition. The work is very massive and in the majority of cases of
simple form. A large number of data are to be found in the reports of
the Chief of Engineers, U. S. A., on all classes of fortification work,
but the manner in which they are recorded makes close analysis of
relative efficiencies of methods or of relative costs almost impossible.
The following data are given, therefore, as examples that may be
considered fairly representative of the costs obtained in fortification
work done under the direction of army engineers; these data are not
susceptible of close analysis because wages, working force, outputs,
etc., are nearly always lacking.
~Gun Emplacements, Staten Island, N. Y.~--The work comprised 5,609 cu.
yds. of concrete in two 12-in. gun emplacements, and 3,778 cu. yds. of
concrete in two 6-in. gun emplacements. Concrete was mixed in a
revolving cube mixer with the exception of 809 cu. yds. in the 6-in.
emplacements which were mixed by hand at a cost of 56 cts. more per
cubic yard than machine mixing cost. The body of the concrete was a
1-3-5 Portland cement, beach sand and broken trap rock mixture. The
floors and upper surface of the concrete had a pavement consisting of 6
ins. of 1-3-5 concrete surfaced with 2 ins. of 1-3 mortar. Wages are not
given, but for the time and place should have been about $1.50 per
8-hour day for common labor. The cost of materials was:
Alpha Portland cement, per bbl. $1.98
Broken trap rock, per cu. yd. 0.81
12-in. emplacement, hauling sand per cu. yd. 0.175
6-in. emplacement, hauling sand per cu. yd. 0.20
The cost of the concrete in place was as follows:
12-in., per 6-in., per
Body Concrete-- cu. yd. cu. yd.
Cement, at $1.98 per bbl. $2.546 $2.546
Broken stone, at 81 cts. per cu. yd. 1.041 1.041
Sand, at 17½ and 20 cts. per cu. yd. 0.225 0.257
Receiving and storing materials at 11.6 cts. per
cu. yd. and 8.4 cts. per bbl. 0.149 0.180
Mixing, placing and ramming 0.879 1.110
Forms, lumber and labor 0.477 0.950
Superintendence and miscellaneous 0.190 0.150
------ ------
Total $5.507 $6.234
Concrete Pavement--
Materials $2.97 $3.06
Labor 4.63 4.72
------ ------
Total $7.60 $7.78
[Illustration: Fig. 68.--Sketch Plans of Concrete Making Plant for
Mortar Battery Platform.]
~Mortar Battery Platform, Tampa Bay, Fla.~--The platform contained 8,994
cu. yds. of concrete composed of a mixture of Portland cement, sand,
shells and broken stone. The broken stone and cement were brought in by
vessel and the sand and shells were obtained from the beach near by. The
plant for the work was arranged as shown by the sketch, Fig. 68. Sand,
stone and shells were stored in separate compartments in the storage
bins. Box cars, divided into compartments of such size that when each
was filled with its proper material, the car would contain the proper
proportions for one batch of concrete, were pushed by hand under the
several compartments of the bin in succession until charged; then they
were hooked to a cable and hauled to the platform over the mixer and
dumped. The charge was then turned over with shovels and shoveled into
the hopper of a continuous mixer, located beneath. Two cars were used
for charging the mixer, running on separate tracks as shown. The mixer
discharged into buckets set on flat cars, which were hauled by mules
under the cableway, which then lifted and dumped the bucket and returned
it empty to the car. By using three bucket cars, one was always ready
to receive the mixer discharge as soon as the preceding one had been
filled, so that the mixer operated continuously. The cableway had a
working span of 270 ft., the cable being carried by traveling towers 69
ft. high; the cableway was very easily operated back and forth along the
work. The cableway complete, with 497 ft. of six-rail track for each
tower, cost $4,700. The cost of materials and labor for the 8,994 cu.
yds. of concrete was as follows:
Per cu. yd.
1 bbl. cement at $2.46 $2.46
0.89 cu. yd. stone, at $2.95 2.622
0.315 cu. yd. shells, at $0.45 0.142
0.51 cu. yd. sand, at $0.12 0.062
Mixing and placing 0.693
-------
Total $5.979
The above batch tamped in place to 30 cu. ft., or 1-1/9 cu. yds., which
gives the cost as follows:
Per cu. yd.
Cost of concrete tamped in place $5.381
Cost of form work 0.370
-------
Total cost $5.751
In the preceding prices of cement and stone, 59 cts. and 29 cts. per
cubic yard, respectively, are included for storage. The costs of sand
and shells are costs of screening and storing. Rough lumber for forms
cost $10.25, and dressed lumber $12.75 per M. ft. B. M.
~Emplacement for Battery, Tampa Bay, Fla.~--The emplacement contained
6,654 cu. yds. of Portland cement, sand, shells and broken stone
concrete. The plant arrangement is shown by Fig. 69. The sand and shells
were got near the site, using an inclined cableway running from a 40-ft.
mast near the mixer to a deadman at the shell bank. All the sand for the
fill around the emplacement was obtained in the same way. The other
materials were brought by vessel to a wharf, loaded by derrick onto cars
operated by an endless cable, and taken to the work. The storage bins
and mixing plant were operated much like those for the mortar battery
work, previously described. A cube mixer was used, and the concrete was
handled from it to the work by a crane derrick covering a circle of 100
ft. in diameter. The cost of materials and concrete was as follows:
Cement, plus 7 cts. for storage per bbl. $ 2.532
Stone, plus 38 cts. for storage per cu. yd. 3.047
Shells, excavating and storage. 0.481
Sand, excavating and storage. 0.250
Lumber, rough per M. ft. B. M. 10.25
Lumber, dressed per M. ft. B. M. 12.75
[Illustration: Fig. 69.--Sketch Plans of Concrete Making Plant for
Battery Emplacement.]
A batch made up as follows, tamped in place to a volume of 30 cu. ft. or
1-1/9 cu. yds.:
1 bbl. cement, at $2.532. $ 2.532
0.315 cu. yd. shells, at $0.481. 0.151
0.51 cu. yd. sand, at $0.25. 0.130
0.89 cu. yd. stone, at $3.047. 2.710
Mixing and placing. 0.761
--------
Total for 30 cu. ft. $ 6.284
This gives a cost per cubic yard of concrete in place as follows:
Concrete in place, per cu. yd. $ 5.655
Forms, per cu. yd. of concrete. 0.220
--------
Total cost of concrete per cu. yd. $ 5.875
~United States Fortification Work.~--The following methods and cost of
mixing and placing concrete by hand and by cubical mixers is given by
Mr. L. R. Grabill for U. S. Government fortification work done in 1899.
_Hand Mixing and Placing._--The work was done by contract, using a 1
cement, 2 sand, 2 pebbles and 3 stone mixture turned four times. A board
large enough for three batches at a time was used; one batch was being
placed, one being mixed and one being removed at the same time so that
the mixers moved without interval from one to the other. Two gangs were
worked, each mixing 64 batches of 0.75 cu. yd., or 48 cu. yds. of
concrete per day at the following cost:
Per Per
Hand Mixing 9,000 Cu. Yds.-- day. cu. yd.
6 men wheeling materials $ 7.50 $0.16
8 men mixing 10.00 0.21
8 men wheeling away 10.00 0.21
6 men placing and ramming 7.50 0.16
1 pump man 1.25 0.02
1 waterboy 1.00 0.02
1 foreman 2.00 0.04
------- -------
Totals $39.25 $0.82
The entire cost of plant for this work was about $500.
_Machine Mixing and Placing._--The concrete was mixed in a 4-ft. cubical
mixer operated by a 12 hp. engine which also hauled the material cars up
the incline to the mixer. These cars passed by double track under the
material bins where the compartments of the car body were filled through
trap doors; they then passed the cement house where the cement was
placed on the load, then up the incline to the mixer and dumped, and
then empty down an opposite incline. Seven turns of the mixer mixed the
charge which was discharged into iron tubs on cars hauled by horses to
two derricks whose booms covered the work. One gang by day labor mixed
and placed 168 batches of 0.7 cu. yd., or 117.6 cu. yds. per day at the
following cost:
Per Per
Machine Mixing 4,000 Cu. Yds.-- day. cu. yd.
32 men at $1.25 $40.00 $0.34
1 pumpman 1.25 0.01
1 teamster and horse 2.00 0.02
2 waterboys at $1 2.00 0.02
1 engineman 1.70 0.02
1 derrickman 1.50 0.01
1 fireman 1.50 0.01
1 foreman 2.88 0.03
Fuel (cement barrels largely) 1.25 0.01
------- -------
Totals $54.08 $0.47
The cost of the plant was about $5,000.
[Illustration: Fig. 70.--Concrete Making Plant for Constructing Lock
Walls, Cascades Canal.]
~LOCK WALLS, CASCADES CANAL.~--Four-fifths or 70,000 cu. yds. of lock
masonry was concrete, the bulk of which was mixed and deposited by the
plant shown by Fig. 70. The concrete was Portland cement, sand, gravel
and broken stone. Cement was brought in in barrels by railway, stored
and tested; from the store house the barrels were loaded onto cars and
taken 250 ft. to a platform onto which the barrels were emptied and from
which the cement was shoveled into the cement hopper and chuted to cars
which took it to the charging hopper of the mixer. The stone was crushed
from spalls and waste ends from the stone cutting yards, where stone for
wall lining and coping and other special parts was prepared. These
spalls and ends were brought in cars and dumped into the hopper of a
No. 5 Gates crusher, with a capacity of 30 tons per hour. From the
crusher the stone passed to a 2½-in. screen, the pieces passing going to
a bin below and the rejections going to a smaller Blake crusher and
thence to the bin. The dust and small particles were not screened out.
The sand and gravel were obtained by screening and washing pit gravel.
The gravel was excavated and brought in cars to the washer. This
consisted of a steel cylinder 2 ft. 6½ ins. in diameter and about 18 ft.
long, having an inclination of 1 in. per foot. An axial gudgeon
supported the cylinder at the lower end and it rested on rollers at the
other end and at an intermediate point. The gravel was fed by hopper and
chute into the upper end and into this same end a 3-in. perforated pipe
projected and extended to about mid-length of the cylinder. The cylinder
shell was solid and provided with internal fins for about half its
length from the feed end. For the remainder of its length nearly to the
end, the shell was perforated with 2½-in. holes. For a length of 4 ft.
beyond mid-point it was encircled by a concentric screen of 1/8-in.
holes, and this screen for 3 ft. of its length was encircled by another
screen of 30 meshes to the inch. The pit mixture fed into the cylinder
was gradually passed along by the combined inclination and rotation,
being washed and screened in the process. The sand fell into one bin and
the gravel into another, and the waste water was carried away by a
flume. The large stones passed out through openings at the lower end of
the shell and were chuted into cars. The cars came to the mixer as
clearly shown by Fig. 70.
The stone and gravel cars were side dump and the cement car was bottom
dump. The mixers were of the cube type 4 ft. on each edge and operated
by a 7×12-in. double cylinder engine at nine revolutions per minute. The
usual charge was 32 cu. ft. of the several ingredients, and it was found
that 15 revolutions requiring about 1½ minutes were sufficient for
mixing. The average work of one mixer was 17 batches or about 13 cu.
yds. per hour, but this could be speeded up to 20 batches per hour when
the materials were freely supplied and the output freely removed. Two
cars took the concrete from the mixer to the hopper, from which it was
fed to the work by chute. The hopper was mounted on a truck and the
chute was a wrought iron cylinder trussed on four sides and having a
45° elbow at the lower end to prevent scattering. The chute fed into a
car running along the wall and distributing the material. It was found
impracticable to move the chute readily enough to permit of feeding the
concrete directly into place. As the concreting progressed upward the
trestle was extended and the chute shortened. It was found that wear
would soon disable a steel chute so that the main trussed cylinder had a
smaller, cheaply made cylinder placed inside as a lining to take the
wear and be replaced when necessary.
The plant described worked very successfully. Records based on 9,614.4
cu. yds. of concrete laid, gave the following:
Cu. yds.
Concrete mixed by hand 1,777.0
Concrete mixed by machine 7,837.4
Total concrete laid 9,614.4
Concrete placed by derricks 2,372.0
Concrete placed by chute 7,242.4
Concrete 1-2-4 mixture 156.0
Concrete 1-3-6 mixture 1,564.0
Concrete 1-4-8 mixture 6,892.0
The average mixture was 1 cement, 3.7 sand, 4.8 gravel and 2.6 broken
stone. The average product was 1.241 cu. yds. concrete per barrel of
cement and 1.116 cu. yds. of concrete per cubic yard of stone and
gravel. The average materials for 1 cu. yd. of concrete were: Cement
0.805 bbl., sand 0.456 cu. yd., gravel 0.579 cu. yd., and stone 0.317
cu. yd.
The cost of these 9,614.4 cu. yds. of concrete in place was:
Hand Mixed and Placed by Derrick-- Per cu. yd.
Labor mixing 1,777 cu. yds $1,072
Repairs, fuel, etc 0.016
-------
Total cost mixing $1,088
Labor placing 2,372 cu. yds. 0.6025
Fuel, tramways, etc. 0.1958
-------
Total cost placing $0.7983
Machine Mixed and Placed by Chute--
Labor mixing 7,837 cu. yds. $0.388
Repairs, fuel, etc 0.046
------
Total cost mixing $0.434
Labor placing 7,242 cu. yds 0.414
Fuel, tramways, etc. 0.045
------
Total cost placing $0.459
Materials and Supplies 9,614 cu. yds.--
Timbering $0.145
Cement 3.289
Sand and gravel 1.073
Broken stone 0.536
Cement testing, repairs, etc. 0.223
------
Total $5,266
Plant and Superintendence, 9,614 Cu. Yds.--
Engineering, superintendence, repairs, etc. $1,508
20% cost of plant 0.165
------
Total $1,673
The comparative cost of hand and machine mixing and handling was thus:
Item-- Hand. Machine.
Mixing per cu. yd. $1.088 $0.434
Placing per cu. yd. 0.798 0.459
Materials, etc., per cu. yd. 5.466 5.466
Plant, etc., per cu. yd. 1.673 1.673
------ ------
Totals $9.025 $8.032
The average total costs of all the concrete placed were:
Mixing per cu. yd. $0.555
Placing per cu. yd. 0.543
Materials per cu. yd. 5.266
Plant, etc., per cu. yd. 1.673
------
Total $8.037
~LOCKS, COOSA RIVER, ALABAMA.~--The following methods and costs are given
by Mr. Charles Firth for constructing lock No. 31 for the Coosa River
canalization, Alabama. This lock is 420 ft. long over all, 322 ft.
between quoins, 52 ft. clear width, 14.7 ft. lift and 8 ft. depth of
water on sills; it contained 20,000 cu. yds. of concrete requiring
21,500 bbls. cement, half Alsen and half Atlas.
Figure 71 shows the concrete mixing plant, consisting of two 4×4 ft.
cube mixer, driven by a 10×16-in. engine. The top floor of the mixer
house stored the cement, 2,000 bbls. The concrete was a 1-3-5½ stone
mixture. Each mixer charge consisted of 3 cu. ft. cement, 9 cu. ft. sand
and 16.5 cu. ft. stone; the charge was turned over four times before and
six times after watering at a speed not exceeding eight revolutions per
minute. The average output of the plant was 200 cu. yds. per 8-hour day,
or 100 cu. yds. per mixer, but it was limited by the means for placing.
[Illustration: Fig. 71.--Concrete Mixing Plant for Lock Construction,
Coosa River, Alabama.]
The concrete was mixed dry, deposited in 6 to 8-in. layers, and rammed
with 30-lb. iron rammers with 6-in. square faces. For all exposed
surfaces a 6-in. facing of 1-3 mortar was placed by setting 2×12-in.
planks 4 ins. from the laggings, being kept to distance by 2×4-in.
spacers, placing and ramming the concrete behind them, then withdrawing
them, filling the 6-in. space with mortar and tamping it to bond with
the concrete. The walls were carried up in lifts, each lift being
completed entirely around the lock before beginning the next; the first
lift was 10.7 ft. high and the others 6 ft., except the last, which was
4.5 ft., exclusive of the 18-in. coping. The coping was constructed of
separately molded blocks 3 ft. long, made of 1-2-3 concrete faced with
1-1 mortar and having edges rounded to 3 ins. radius.
In constructing the forms a row of 6×8-in. posts 24 ft. long and 5 to 7
ft. apart was set up along the inside of each wall and a similar row of
posts 12 ft. long was set up along the outside. From the tops of the
short posts 6×8-in. caps reached across the wall and were bolted to the
long posts; these caps carried the stringers for the concrete car
tracks. The lagging consisted of 3×10-in. planks dressed on all sides.
The backs of the walls were stepped and as each step was completed the
rear 12-ft. posts were lifted to a footing on its top and carried in the
necessary distance. The front posts remained undisturbed until the wall
was completed. The lagging was moved up as the filling progressed. As no
tie bolts were permitted, these forms required elaborate bracing.
From the mixing plant, which was located on the bank above reach of
floods, the concrete cars were dropped by elevator to the level of the
track over the walls and then run along the wall and dumped onto
platforms inside the forms and just below the track. This arrangement
was adopted, because it was found that even a small drop separated the
stone from the mortar. The concrete was shoveled from the platforms to
place and rammed. The cars were bottom dumping with a single door hinged
at the side; this door when swinging back struck the track stringers and
jarred the form so that constant attention was necessary to keep it in
line. It would have been much better to have had double doors swinging
endwise of the car. Another point noted was that unless the track was
high enough to give good head room at the close of a lift the placing
and ramming were not well done.
The cost of 8,710 cu. yds. of concrete placed during 1895 by day labor
employing negroes at $1 per 8-hour day was as follows per cubic yard:
1 bbl. cement $2.48
0.88 cu. yd. stone at $0.76 0.67
0.36 cu. yd. sand at $0.34 0.12
Mixing, placing and ramming 0.88
Staging and forms 0.42
----
Total $4.57
~LOCK WALLS, ILLINOIS & MISSISSIPPI CANAL.~--The locks and practically all
other masonry for the Illinois & Mississippi Canal are of concrete. The
following account of the methods and cost of doing this concrete work is
taken from information published by Mr. J. W. Woermann in 1894 and
special information furnished by letter. The decision to use concrete
was induced by the fact that no suitable stone for masonry was readily
available (the local stone was a flinty limestone, usually without bed,
or, at best, in thin irregular strata, and cracked in all directions
with the cracks filled with fire clay) while good sand and gravel and
good stone for crushing were plentifully at hand. The concrete work done
in 1893-4 comprised dam abutments, piers for Taintor gates and locks.
_Dam Abutments._--Four dam abutments were constructed, three of which
were L-shaped, with sides next to the river 40 ft. long and sides
extending into the banks 20 ft. long; the top thickness was 3 ft., the
faces were vertical and the backs stepped with treads of 14 to 16 ins.,
and the width of base was 0.4 of the height. Each of these abutments was
built in four 30-cu. yd. sections, each section being a day's work. The
forms consisted of 2×8-in. planks, dressed on both sides, 2×8-in. studs
spaced 2 ft. on centers and 4×6-in. braces. For the first two of the
four abutments, the forms were erected in sections, the alternate
sections being first erected and filled. When these sections had
hardened the forms were shifted to the vacant sections and lined up to
and braced against the completed sections. This method did not give well
aligned walls, so in subsequent work the forms were erected all at once.
The concrete was mixed by hand. The sand and cement were mixed dry,
being turned four times and spread in a layer Pebbles and broken stone
previously wetted were spread over the sand and cement and the whole
turned four times, the last turn being into wheelbarrows; about five
common buckets of water were added during the mixing. The mixture sought
was one that would ram without quaking. Two forms of rammers were used;
for work next to forms a 4×6-in. rammer and for inside work 6-in
diameter circular rammer weighing 20 lbs. The gang mixing and placing
concrete consisted usually of:
Item. Per Day. Per Cu. Yd.
2 handling cement and sand $ 3.00 $0.10
3 filling barrows with aggregate 4.50 0.15
8 mixing concrete 12.00 0.40
2 shoveling concrete into barrows 3.00 0.10
5 wheeling concrete to forms 7.50 0.25
1 spreading concrete 1.50 0.05
5 tamping concrete 7.50 0.25
------ -----
Total, 26 men $39.00 $1.30
These cubic yard costs are based on 30 cu. yds. of wall completed per
8-hour day. The cost in detail of two abutments containing 254 cu. yds.
was per cubic yard as follows:
Item. Per Cu. Yd.
1.65 bbls. Portland (Germania) cement $ 5.60
0.5 cu. yd. crushed stone 2.07
0.24 cu. yd. gravel 0.59
0.53 cu. yd. sand 0.24
Lumber, forms, warehouses, platforms[D] 0.55
Carpenter work[E] ($9 per M.) 1.10
Mixing and placing 1.47
20 per cent. first cost of plant 0.31
Engineering and miscellanies 0.31
------
Total $12.24
[Footnote D: Charging ¼ of first cost of $18 per M. ft.]
[Footnote E: Carpenters $3.50, laborers $1.50 per day; there was one
laborer to two carpenters.]
The large amount of cement 1.65 bbls. per cubic yard was due to facing
the abutments with 8 ins. of 1-2 mortar. The concrete in the body of the
wall was 1 cement, 2 sand, 2 gravel and 2 broken stone mixture. A dry
mixture was used and this fact is reflected in the cost of ramming, 25
cts. per cu. yd. The cost of mixing was also high.
[Illustration: Fig. 72.--Concrete Mixing Plant for Lock Walls, Illinois
& Mississippi Canal.]
_Piers for Taintor Gates._--The masonry at this point consisted of three
piers 6×30 ft., and two abutments 30 ft. long, 6 ft. thick at base and 4
ft. thick at top, with wing walls; it amounted to 460 cu. yds. The feet
of the inclined braces were set into gains in the horizontal braces and
held by an 8-in. lag screw; after the posts were plumbed a block was
lag-screwed at the upper end of each brace. These forms proved entirely
satisfactory. The cost of the work per cubic yard was as follows:
Item. Per Cu. Yd.
1.45 bbls. Portland cement $4.330
0.55 cu. yd. crushed stone 0.604
0.252 cu. yd. pebbles 0.328
0.465 cu. yd. sand 0.419
40,000 ft. B. M. lumber (¼ cost of $16 per M.) 0.348
Carpenter work on forms 0.780
Mixing and placing concrete 1.909
20 per cent. cost of plant 0.090
Miscellaneous 0.182
-----
Total $8.99
_Mixing Plant._--The concrete for all the lock work of 1893-4 was mixed
by the plant shown by Figs. 72 and 73. The mixer plant proper consisted
of a king truss carried by two A-frames of unequal height; under the
higher end of the truss was a frame carrying a 4-ft. cubical mixer and
under the lower end a pit for a charging box holding 40 cu. ft. This
charging box was hoisted by ½-in. steel cable running through a pair of
double blocks as shown; the slope of the lower chord of the truss was
such that the cable hoisted the box and carried it forward without the
use of any latching devices. On two sides of the pit were tracks from
the sand and stone piles and on the other two sides were the cement
platform and water tank. The charging box dumped into the hopper above
the mixer and the mixer discharged into cars underneath. A 15-HP. engine
operated the hoist by one pulley and the mixer by the other pulley. Nine
revolutions of the mixer made a perfect mixture. The plant as
illustrated was slightly changed as the result of experience in
constructing the guard lock. The charging hopper was lowered 6 ins. and
the space between the mixer and lower platform reduced by 9 ins.;
diagonal braces were also inserted under the timbers carrying the mixer
axles. This plant cost for framing and erection $300 and for machinery
delivered $706. The crushing plant shown by Fig. 73 consisted of a No. 2
Gates crusher delivering to a bucket elevator.
[Illustration: Fig. 73.--Stone Crushing Plant for Lock Walls, Illinois &
Mississippi Canal.]
[Illustration: Fig. 74.--Forms for Guard Lock, Illinois & Mississippi
Canal.]
_Guard Lock._--The forms employed in constructing the guard lock are
shown by Fig. 74, and in this drawing the trestle and platform for the
concrete cars are to be noted. The walls were concreted in sections. A
batch of concrete consisted of 1 bbl. cement, 10 cu. ft. sand and 20 cu.
ft. crushed stone. The average run per 8-hour day was 40 batches of
facing and 60 batches concrete, representing 100 bbls. cement. The gang
worked was as follows:
Duty. No. Men. P. C. Cost.
Handling cement 3 5.26
Filling and pushing sand car 5 8.77
Filling and pushing stone car 9 15.79
Measuring water 1 1.75
Dumping bucket on top platform 3 5.26
Opening and closing door of mixer 1 1.75
Operating friction clutch 1 1.76
Attending concrete cars under mixer 1 1.76
Dumping cars at forms 2 3.51
Spreading concrete in forms 3 5.26
Tamping concrete in forms 10 17.54
Mixing mortar for facing 6 10.53
Finishing top of wall 2 3.51
Hauling concrete cars with 1 horse 1 3.51
Engineman operating hoist 1 3.51
Engineman operating engine 1 3.51
Foreman in charge of forms 1 3.51
General foreman 1 3.51
-- ------
Total 52 100.00
The percentages of cost in this statement have been calculated by the
authors upon the assumption that each laborer received one-half as much
wages as each engineman, foreman and horse and driver per 8 hours, which
would make the total daily wages equivalent to the wages of 57 men.
Wages of common labor were $1.50 per day. Considering the size of the
gang the output of 40 batches of mortar and 60 batches of concrete per
day was very small. The total yardage of concrete in the guard lock was
3,762 cu. yds., 2,212 cu. yds. in the walls and 1,550 cu. yds. in
foundations, culverts, etc. Its cost per cubic yard was made up as
follows:
Item. Total. Per Cu. Yd.
5,246 bbls. Portland cement $15,604}
} $4.170
152 bbls. natural cement 84}
2,910 cu. yds. stone 2,901 0.771
126 cu. yds. pebbles 113}
} 0.401
1,970 cu. yds. sand 1,398}
145,000 ft. B. M. lumber (¼th cost) 659 0.175
Iron for forms, trestles, etc. 90 0.024
Coal, oil, miscellaneous 327 0.087
Carpenter work 2,726 0.724
Mixing and placing concrete 6,693 1.780
Pumping, engineering, misc. 742 0.197
20 per cent of plant 550 0.146
------- ------
Total $31,887 $8.475
[Illustration: Fig. 75.--Forms for Regular Lock Walls, Illinois &
Mississippi Canal.]
_Lock No. 37._--The character of the forms used in constructing the lock
walls is shown by Fig. 75. The walls were built in sections and work was
continuous with three 8-hour shifts composed about as specified for the
guard lock work except that one or two men were added in several places
making the total number 58 men. The average output per shift was 65
batches of concrete and 31 batches of facing mortar. The cost of the
work, comprising 3,767 cu. yds., was as follows:
Item. Total. Per Cu. Yd.
4,564 bbls. Portland cement $14,181 $3.764
2,460 cu. yds. crushed stone 4,521 1.200
250 cu. yds. pebbles 325 0.086
1,750 cu. yds. gravel 2,335 0.619
450 cu. yds. sand 450 0.119
180,000 ft. B. M. lumber (¼th cost) 990 0.236
Fuel, light, repairs, etc. 1,171 0.311
Carpenter work 2,526 0.671
Pumping 270 0.071
Mixing and placing concrete 6,170 1.632
20% cost of plant 730 0.193
------- ------
Total $33,669 $8.902
_Lock No. 36._--The forms used were of the construction shown by Fig.
Reading Tips
Use arrow keys to navigate
Press 'N' for next chapter
Press 'P' for previous chapter