Concrete Construction: Methods and Costs by Gillette and Hill
CHAPTER XV.
1864 words | Chapter 66
METHODS AND COST OF CONSTRUCTING SIDEWALKS, PAVEMENTS AND CURB AND
GUTTER.
Next to pavement foundations the most extensive use of concrete in
street work is for cement walks and concrete curb and gutter. Usually
the mixing and placing of the concrete is hand work, practically the
only exceptions being where pavement base, curbing and sidewalks are
built all at once, using machine mixers. The same objections that have
been raised to machine mixers in laying pavement foundation are raised
against them for curb and walk construction, and owing to the much
smaller yardage per lineal foot of street in walk and curb work these
objections carry more force than they do in case of paving work. Another
argument against the use of mixers is that both walk and curb and gutter
work involve the use of forms and the application of mortar finish, the
placing of which are really the limiting factors in the rate of progress
permissible, and this rate is too slow to consume an output necessary to
make a mixer plant economical as compared with hand mixing where so much
transportation is involved. Concrete sidewalk and curb work are
essentially hand mixing work; they, therefore, involve a careful study
of the economies of hand mixing and wheelbarrow haulage which are fully
discussed in Chapter II.
CEMENT SIDEWALKS.
Sidewalk construction consists in molding on a suitably prepared
sub-base a concrete slab from 3½ to 7½ ins. thick, depending on
practice, and finishing its top surface with a ½ to 1½-in. wearing
surface of cement mortar.
~GENERAL METHOD OF CONSTRUCTION.~--The excavation and preparation of the
sub-grade call for little notice beyond the warning that they should
never be neglected. The authors have seen many thousands of feet of
cement walk laid in the middle West in which the sub-base was placed
directly on the natural sod, often covered with grass and weeds a foot
high. Such practice is wholly vicious. The sod should always be removed
and the surface soil excavated to a depth depending upon the climate and
nature of the ground and the foundation bed well tamped. From 4 to 6
ins. depth of excavation will serve where the soil is reasonably hard
and there are no heavy frosts; with opposite conditions a 12-in.
excavation is none too deep. The thickness of the broken stone, gravel,
cinder or sand sub-base should likewise be varied with the character of
the soil, the conditions of natural drainage and the prevalence of
frost. In well drained sandy soils 6 to 8 ins. of sub-base are
sufficient, but in clayey soils with poor natural drainage the sub-base
should be from 10 to 12 ins. thick at least; the local conditions will
determine the thickness of sub-base necessary and in places it may be
desirable to provide by artificial drainage against the accumulation of
water under the concrete. Tile drains are better and cheaper than
excessively deep foundations. The thorough tamping of the sub-base is
essential to avoid settling and subsequent cracking of the concrete
slab. This is a part of sidewalk work which is often neglected.
Portland cement concrete, sand and broken stone or gravel mixtures in
the proportions of 1-3-5 and 1-3-6 are used for base slabs. For walks up
to 7 ft. wide the slab is made 3½ ins. thick for residence streets and
4½ to 5 ins. thick for business streets; for wider walks the thickness
is increased to 7 ins. for 8-ft. width and 7½ ins. for 9 to 10-ft.
width. Roughly the thickness of the walk in inches (base and top
together) is made about equal to its width in feet. The concrete is
deposited in a single layer and tamped thoroughly, either in separate
blocks behind suitable forms or in a continuous slab which is while
fresh cut through to make separate blocks. For walks up to 8 ft. wide
the slab is divided by transverse joints spaced about the width of the
walk apart, but for the wider walks the safety of this division depends
upon the thickness of the base; an 8-ft. walk with a 5-in. base can
safely be laid with joints 8 ft. apart, but if the slab is only 4 ins.
thick it had better be laid in 4×4-ft. squares. The mode of procedure in
base construction is as follows:
The sub-base being laid, side forms held by stakes are placed as shown
by Fig. 116, with the top edges of the boards exactly to the grade of
the top surface of the finished walk. The concrete is then deposited
between these side forms and tamped until it is brought up to the level
marked by the templet A. If the plan is to deposit the base in
sections transverse plates of 3/8 to ¼ in. steel are set across the walk
between the side boards at proper intervals and the concrete tamped
behind them; sometimes the concreting is done in alternate blocks. When
the steel plate is withdrawn an open joint is left for expansion and
contraction. Where the plan is to lay the base in one piece which is
afterwards cut into blocks, the cutting is done with a spade or cleaver.
[Illustration: Fig. 116.--Sketch Showing Method of Constructing Cement
Walks.]
[Illustration: Fig. 117.--"Jointer" for Cement Sidewalk Work.]
Portland cement mortar mixed 1 to 1½ to 1 to 2 is used for the wearing
surface, and is laid from ½ in. to 1½ ins. thick, depending upon the
width of the walk and the thickness of the base. As a rule the mortar is
mixed rather stiff; it is placed with trowels in one coat usually, but
sometimes in two coats, and less often by tamping. The mortar coat is
brought up flush with the top edges of the side forms by means of the
templet B, and the top finished by floating and troweling. The
wearing coat is next divided into sections corresponding with the
sections into which the base is divided, by cutting through it with a
trowel guided by a straight edge and then rounding the edges of the cut
with a special tool called a jointer and shown by Fig. 117. An edger,
Fig. 118, is then run around the outside edges of the block to round
them. The laying of the mortar surface must always follow closely the
laying of the base so that the two will set together.
[Illustration: Fig. 118.--"Edger" for Cement Sidewalk Work.]
~BONDING OF WEARING SURFACE AND BASE.~--Trouble in securing a perfect bond
between the wearing surface and the base usually comes from one or more
of the following causes: (1) Applying the surface after the base
concrete has set. While several means are available for bonding fresh to
old concrete as described in Chapter XXIV, the better practice is not to
resort to them except in case of necessity but to follow so close with
the surfacing that the base will not have had time to take initial set.
(2) Poor mixing and tamping of this base concrete. (3) Use of clayey
gravel or an accumulation of dirt on the surface. In tamping clayey
gravel the water flushes the clay to the surface and prevents the best
bond. (4) Poor troweling, that is failure to press and work the mortar
coat into the base concrete. Some contractors advocate tamping the
mortar coat to obviate this danger. Conversely, to make the surface coat
adhere firmly to the base it must be placed before the base concrete has
set; the base concrete must be thoroughly cleaned or kept clean from
surface dirt; the surface coat must be tamped or troweled forcibly into
the base concrete so as to press out all air and the film of water which
collects on top of the concrete base.
~PROTECTION OF WORK FROM SUN AND FROST.~--Sun and frost cause scaling and
hair cracks. For work in freezing weather the water, sand and gravel
should be heated or salt used to retard freezing until the walk can be
finished; it may then be protected from further action of the frost by
covering it first with paper and then with a mattress of sawdust,
shavings or sand and covering the whole with a tarpaulin. Methods of
heating concrete materials and rules for compounding salt solutions are
given in Chapter VII. The danger from sun arises from the too rapid
drying out of the surface coating; the task then is to hold the moisture
in the work until the mixture has completely hardened. Portable frames
composed of tarpaulin stretched over 2×4-in. strips may be laid over the
finished walk to protect it from the direct rays of the sun; these
frames can be readily removed to permit sprinkling. Practice varies in
the matter of sprinkling, but it is the safe practice in hot weather to
sprinkle frequently for several days. Moisture is absolutely necessary
to the perfect hardening of cement work and a surplus is always better
than a scarcity. In California the common practise is to cover the
cement walk, as soon as it has hardened, with earth which is left on for
several days.
~CAUSE AND PREVENTION OF CRACKS.~--Cracks in cement walks are of two
kinds, fractures caused by any one of several construction faults and
which reach through the surface coating or through both surface and
base, and hair cracks which are simply skin fractures. Large cracks are
the result of constructive faults and one of the most common of these is
poor foundation construction; other causes are poor mixing and tamping
of the base, too large blocks for thickness of the work, failure to cut
joints through work. Hair cracks are the result of flushing the neat
cement to the surface by excessive troweling or the use of too wet a
mixture. The prevention of cracks obviously lies in seeing that the
construction faults cited do not exist. If expansion joints are not
provided, a long stretch of cement walk will expand on a hot day and
bulge up at some point of weakness breaking the walk.
~COST OF CEMENT WALKS.~--The cost of cement walks is commonly estimated in
cents per square foot, including the necessary excavation and the cinder
or gravel foundation. The excavation usually costs about 13 cts. per
cu. yd., and if the earth is loaded into wagons the loading costs
another 10 cts. per cu. yd., wages being 15 cts. per hr. The cost of
carting depends upon the length of haul, and may be estimated from data
given in Chapter III. If the total cost of excavation is 27 cts. per cu.
yd., and if the excavation is 12 ins. deep, we have a cost of 1 ct. per
sq. ft. for excavation alone. Usually the excavation is not so deep, and
often the earth from the excavation can be sold for filling lots.
In estimating the quantity of cement required for walks, it is well to
remember that 100 sq. ft. of walk 1 in. thick require practically 0.3
cu. yd. concrete. If the concrete base is 3 ins. thick, we have 0.3 × 3,
or 0.9 cu. yd. per 100 sq. ft. of walk. And by using the tables in
Reading Tips
Use arrow keys to navigate
Press 'N' for next chapter
Press 'P' for previous chapter