Concrete Construction: Methods and Costs by Gillette and Hill
15. The trestle work was made of 12×12-in. timbers and was approximately
4637 words | Chapter 48
40 ft. in height. Three tracks occupy the top platform. Under each track
was a material bin; one on each side for gravel and a middle bin for
sand. The sand bin was divided by a partition into two compartments.
These bins discharged into two measuring hoppers one gravel bin and one
compartment of the sand bin into each hopper. Two cement chutes from the
top platform provided for the delivery of the cement to the mixers,
either directly from cars or from the cement storage house. The mixing
was done in two Smith No. 5 mixers, one under each measuring hopper, and
these mixers discharged by chutes into buckets on flat cars. Thus the
concrete materials brought directly from a siding in car load lots to
the top of the platform were handled entirely by gravity to the cars
delivering the mixed concrete to the work. The gang operating the mixing
plant, with the wages paid, was composed as follows: 1 foreman and
engineer at $3 per day, 1 fireman at $2 per day and 15 laborers at $1.50
per day. With this gang the two mixers turned out 400 cu. yds. of
concrete per day and, frequently, 800 cu. yds. in 24 hours. Taking these
figures the labor cost from raw materials in cars on the platform to
mixed concrete in cars on the delivery track was as follows:
1 foreman and engineer at $3 $ 3.00
1 fireman at $2 2.00
15 laborers at $1.50 22.50
-----
Total labor $27.50
Assuming 400 cu. yds. output, this gives a cost of $27.50 ÷ 400 = 6.875
cts. per cu. yd.
~Charging with Wheelbarrows.~--The economics of wheelbarrow haulage are
discussed in some detail in Chapter III. For machine mixer work the
problem of loading, transporting and dumping is complicated by the
greater rapidity with which the mixing is done and by the necessity,
usually, of using inclines to reach the charging hopper level. The
incline cuts down the output of the wheelers or in other words makes
necessary a larger gang to handle the same amount of material.
Conditions being the same, the height of the charging chute of the mixer
determines the height of incline and the size of the charging gang, so
that a mixer with a high charging level costs more to charge with
wheelbarrows than does one with a low charging level. Exact figures of
the increased cost of a few feet extra elevation of the wheelbarrow
incline are not available, but some idea may be had from a brief
calculation. The materials for a cubic yard of concrete will weigh about
3,700 lbs., so that to raise the materials for 100 cu. yds. of concrete,
including weight of barrows, 1 ft. calls for about 400,000 ft. lbs. of
work. A man will do about 800,000 ft. lbs. of useful work in a day, so
that each foot of additional height of incline means an additional
half-day's work for one man.
Wheeling to elevating charging hoppers obviates the use of inclines.
Figure 19 shows a mixer equipped with such a hopper, and the arrangement
provided for other makes of mixer is much similar. When the hopper is
lowered ready to receive its load its top edge over which the
wheelbarrows are dumped is from 12 to 14 ins. above ground level. The
wheeling is all done on the level. The elevating bucket is operated by
the mixer engine and is usually detachable. Where mixers have to be
moved frequently, requiring the erection and moving of the incline each
time, an elevating charging hopper is particularly useful; it can be
hoisted clear of the ground and moved with the mixer, so that it is
ready to use the moment that the mixer is set at its new station.
While the ordinary wheelbarrow is generally used for charging, better
work can be done under some conditions by using special charging barrows
of larger capacity and dumping from the end and ahead of the wheel. Two
forms of charging barrow are shown by Figs. 16 and 17. The Acme barrow
will hold 4 cu. ft. and the Ransome barrow is made in 3 to 6 cu. ft.
capacities. Where inclines are necessary these barrows can often be
hauled up the incline by power. A sprocket chain in the plane of the
incline and operated by the mixer engine is an excellent arrangement. A
prong riveted to the rear face of the barrow and projecting downward is
"caught into" the chain, which pulls the barrow to the top, the man
following to dump and return for another load.
[Illustration: Fig. 16.--Forward Dump Charging Barrow, Sterling
Wheelbarrow Co.]
[Illustration: Fig. 17.--Forward Dump Charging Barrow, Ransome Concrete
Machinery Co.]
~Charging with Cars.~--Cars moved by cable, team or hand are a
particularly economic charging device when the mixer is located a little
distance from the stock piles or bins. Either separate cars for cement,
sand and stone, each holding the proper amount of its material for a
batch, can be used, or a single car containing enough of all three
materials for a batch. The last arrangement is ordinarily more
economical in time and labor, and in plant required. In either case the
car serves as the measuring hopper, there being no further proportioning
of the materials after they have been loaded into the car, and it must
be arranged for measuring. Usually all that is necessary, where one car
is used, is to mark the levels on the sides to which it is to be filled
with sand and then stone; the car is run to the sand stock and filled to
the level marked for sand and then to the stone stock and filled to the
level marked for stone. The cement may be added to the charge either
before or after it is run to the mixer as convenience in storing the
cement stock dictates. Instead of having marks to show the proper
proportions of sand and stone, the car is sometimes divided into two
compartments, one for each material and each holding the proper
proportion of its material when level full. This arrangement makes
proper proportioning somewhat more certain, since the men charging the
car cannot over-run the marks. In case separate cars are used for each
material, they are simply filled level full or to mark, and dumped in
succession into the feeding hopper. Trestle and car plant construction
and costs are given in a preceding section.
~Charging by Shoveling.~--Charging by shoveling directly into the mixer is
seldom practiced except in street work with continuous mixers or in
charging gravity mixers of the trough type. Shoveling is not an economic
method of handling materials where the work involves carrying in
shovels, and it is only in a few classes of concrete work or in
isolated, exceptional cases that charging with shovels does not involve
carrying. The amount of material that men will load with shovels is
given in Chapter III, and the reader who wishes a full discussion of the
subject is referred to Gillette and Hauer, "Earth Excavation and
Embankments; Methods and Cost."
In charging continuous mixers with shovels the usual practice for mixers
without automatic feed devices is to work from a continuous stock pile
of sand, stone and cement spread in layers in the proper proportions.
The shoveling is done in such a manner that each shovelful contains a
mixture of cement, sand and stone, and so that the rate of delivery to
the mixer is as uniform as possible. In charging mixers having automatic
feed devices the sand and stone are simply shoveled into the sand and
stone hoppers, whence they are fed automatically to the mixer. In
charging gravity mixers by shoveling the method is essentially the same;
the cement, sand and stone properly proportioned are spread in layers on
the shoveling board at the head of the mixer and the mixture then
shoveled into the mixer. In both of these cases mixing is performed to a
certain extent by the shoveling, and in both the provision of the
combination stock pile from which the men work involves labor which
comes within the meaning of the term charging as we have used it here.
Examples of street work in which the mixers were charged by shoveling
are given in Chapter XIV.
~Charging with Derricks.~--When the stock piles are located close to the
mixer and the plant is fixed or is not frequently moved derricks can be
used economically for charging, particularly if the mixer be elevated so
that inclines become expensive. The following mode of operation will be
found to work well: Set the derrick so that its boom "covers" the sand
and stone piles and the mixer, and provide it with three buckets so that
there will always be one bucket at the stone pile and another at the
sand pile while the third is being handled. The derrick swinging from
the mixer, where it has discharged a bucket, drops the empty bucket at
the stone pile and picks up the bucket standing there, which has
received its proper charge of stone, and swings it to the sand pile and
drops it to get its charge of sand. Here it picks up the bucket standing
at the sand pile and which has its charges of both stone and sand, and
swings it to the mixer. By this arrangement the work of the derrick and
of the men filling the buckets is practically continuous. The buckets
can be provided with marks on the inside to show the proper points to
which to fill the stone and the sand or a partition may be riveted in
making a compartment for sand and another for stone. A special
charging-bucket that is arranged with a wheel and detachable handles
which permit it to be handled like a wheelbarrow is shown by Fig. 18.
This bucket can be used to advantage where the stock piles are too far
from the mixer for the derrick to reach both, the bucket being loaded
and wheeled to within reach of the derrick.
[Illustration: Fig. 18.--Charging Bucket With Wheel and Detachable
Handle.]
~TYPES OF MIXERS.~--There are two types of concrete mixing machines or
concrete mixers as they are more commonly called: (1) Batch mixers and
(2) continuous mixers. In mixers of the first type a charge of cement,
sand, aggregate and water is put into the machine which mixes and
discharges the batch before taking in another charge; charging, mixing
and discharging is done in batches. In continuous mixers the cement
sand, stone and water are charged into the machine in a continuous
stream and the mixed concrete is discharged in another continuous
stream. While all concrete mixers are either batch or continuous mixers,
it is common practice because of their distinctive character to separate
gravity mixers, whether batch or continuous, into a third type. In
gravity mixers the concrete materials are made to mingle by falling
through specially constructed troughs, or tubes, or hoppers. We shall
describe mixers in this chapter as (1) batch mixers, (2) continuous
mixers, and (3) gravity mixers. No attempt will be made, however, to
describe all or even all the leading mixers of each type; a
representative mixer or two of each type will be described, enough to
give an indication of the range of practice, and the reader referred to
manufacturers' literature for further information.
~Batch Mixers.~--Batch mixers are made in two principal forms which may be
designated as tilting and non-tilting mixers. In the first form the
mixer drum is tilted as one would tilt a bucket of water to discharge
the batch. In non-tilting mixers the mixer drum remains in one position,
the batch being discharged by special mechanism which dips it out a
portion at a time. In both forms the charge is put into the mixer as a
unit and kept confined as a unit during the time of mixing, which may be
any period wished by the operator.
[Illustration: Fig. 19.--Chicago Improved Cube Concrete Mixer with
Elevating Charging Hopper.]
_Chicago Improved Cube Tilting Mixer._--Figure 19 shows the improved
cube mixer made by the Municipal Engineering & Contracting Co., Chicago,
Ill. The drum consists of a cubical box with rounded corners and edges.
This box has hollow gudgeons at two diagonally opposite corners and
these gudgeons are open as shown to provide for charging and
discharging. The box is rotated by gears meshing with a circumferential
rack midway between gudgeons and another set of gears operate to tilt
the mixer. The inside of the box is smooth, there being no deflectors,
as its shape is such as to fold the batch repeatedly and thus accomplish
the mixing.
[Illustration: Fig. 20.--Ransome Concrete Mixer.]
_Ransome Non-Tilting Mixer._--Figure 20 shows a representative
non-tilting mixer made by the Ransome Concrete Machinery Co., Dunellen,
N. J. It consists of a cylindrical drum riding on rollers and rotated by
a train of gears meshing with circumferential racks on the drum. The
drum has a circular opening at each end; a charging chute enters one
opening and a tilting discharge chute may be thrown into or out of the
opposite opening. The cylindrical shell of the drum is provided inside
with steel plate deflectors, which plow through and pick up and drop the
concrete mixture as the drum revolves. The shape and arrangement of the
deflectors are such that the batch is shifted back and forth axially
across the mixer. To discharge the batch the discharge chute is tilted
so that its end projects into the mixer, in which position the material
picked up by the deflectors drops back onto the chute and runs out. The
discharge chute being independent of the mixing drum it can be thrown
into and out of discharge position at will without stopping the rotation
of the drum, and so can discharge any part or all of the batch at once.
The top edge of the charging chute ranges from 30½ to 38 ins. in height
above the top of the frame, varying with the size of the mixer.
[Illustration: Fig. 21.--Smith Concrete Mixer.]
_Smith Tilting Mixer._--Figure 21 shows a tilting mixer, known as the
Smith mixer, made by the Contractors' Supply & Equipment Co., Chicago,
Ill. The drum consists of two truncated cones with their large ends
fastened together and their small ends open for receiving the charge and
discharge of the batch. The drum is operated by a train of gears meshing
into a rack at mid-length where the cones join. In addition there is
another set of gears which tilt the drum to make the concrete flow out
of the discharge end. The inside of the drum is provided with steel
plate deflectors, which plow through and pick and drop the concrete
mixture shifting it back and forth axially in the process.
~Continuous Mixers.~--Continuous mixers are those in which the cement,
sand and stone are fed to the charging hopper in a continuous stream and
the mixed concrete is discharged in another continuous stream. They are
built in two principal forms. In one form the cement, sand and stone
properly proportioned are shoveled directly into the mixing drum. In the
other form these materials are dumped into separate charging hoppers and
are automatically fed into the mixing drum in any relative proportions
desired. One form of continuous mixer with automatic feed is described
in the succeeding paragraph and another form is described in Chapter
XIV. The continuous mixer without automatic feed consists simply of a
trough with a rotating paddle shaft and its driving mechanism. The
charging, the mixing and the discharging are done in what is virtually a
succession of very small batches.
[Illustration: Fig. 22.--Eureka Automatic Feed Continuous Mixer.]
_Eureka Automatic Feed Mixer._--Figure 22 shows the construction of the
continuous mixer built by the Eureka Machine Co., Lansing, Mich. The
cement bin and feeder is the small one in the foreground. There is a
pocketed cylinder revolving between concave plates, opening into the
hopper above, from which the pockets in the feeder are filled, and
discharging directly into the mixing trough below. Back of this is
shown the feeder for sand or gravel up to 2-in. screen size. This is a
pocketed cylinder similar to that used in the cement feeder, except that
it is larger, and instead of being provided on the discharge side with a
concave plate, is surmounted by a roller, held by springs. This serves
to cut off the excessive flow of material, but provides sufficient
flexibility to allow the rough coarse material to be fed through the
machine without its catching. The feeder for crushed stone is a similar
construction on larger lines, to handle material up to 3-in. size. These
several feeders can be set to give any desired mixture. On any material
fit to be used in concrete, they will measure with an error of less than
5 per cent., an agitator being provided in the sand bin to prevent damp
sand from bridging over the feeder, and preventing its action. The mixer
consists of a trough, with a square shaft, on which are mounted 37
mixing paddles, which are slipped on in rotation, so as to form
practically a continuous conveyor, but as each paddle is distinct, and
is shaped like the mold board of a plow, the material, as it passes from
one to the next, is turned over and stirred. Water is sprayed into the
mass at the center of the trough. The result is a dry mix, followed by a
wet mix. The mixing trough is made of heavy gage steel, well reinforced,
and practically indestructible. To take care of the discharge of
material while changing wheelbarrows, a hood is provided on the
discharge end of the machine, which can be lowered, and will hold about
a wheelbarrow load.
~Gravity Mixers.~--Gravity mixers are constructed in two general forms.
The first form is a trough whose bottom or sides or both are provided
with pegs, deflectors or other devices for giving the material a zig-zag
motion as it flows down the trough. The second form consists of a series
of hoppers set one above the other so that the batch is spilled from one
into the next and is thus mixed.
The chief advantage claimed for gravity mixers is that no power is
required to operate them. This is obviously so only in the sense that
gravity mixers have no power-operated moving mechanism, and the fact
should not be overestimated. The cost of power used in the actual
performance of mixing is a very small item. The distance between feed
and discharge levels is always greater for gravity mixers than for
machine mixers, and the power required to raise the concrete materials
the excess height may easily be greater than the power required to
operate a machine mixer. On the other hand the simplicity of the gravity
mixer insures low maintenance costs.
_Gilbreth Trough Mixer._--Figure 23 shows the construction of one of the
best known makes of gravity mixers of the trough form. In operation the
cement, sand and stone in the proper proportions are spread in
superimposed layers on a shoveling board at hopper level and are then
shoveled as evenly as possible into the hopper. From the hopper the
materials flow down the trough, receiving the water about half way down,
and are mixed by being cut and turned by the pins and deflectors. The
trough of the mixer is about 10 ft. long.
[Illustration: Fig. 23.--Gilbreth Gravity Mixer, Trough Form.]
[Illustration: Fig. 24.--Hains Gravity Mixer, Fixed Hopper Form.]
_Hains Gravity Mixer._--The form of gravity mixer made by the Hains
Concrete Mixer Co., Washington, D. C., is shown by Figs. 24 and 25. The
charge passes through the hoppers in succession. Considering first the
stationary plant, shown by Fig. 24, the four hoppers at the top have a
combined capacity of one of the lower hoppers. Each top hopper is
charged with cement, sand and stone in the order named and in the proper
proportions. Water is then dashed over the tops of the filled hoppers
and they are dumped simultaneously into the hopper next below. This
hopper is then discharged into the next and so on to the bottom.
Meanwhile the four top hoppers have been charged with materials for
another batch. It will be observed that (1) the concrete is mixed in
separate batches and (2) the ingredients making a batch are accurately
proportioned and begin to be mixed for the whole batch at once. The best
arrangement is to have the top of the hopper tower carry sand and stone
bins which chute directly into the top hoppers. In the telescopic mixer
shown by Fig. 25 the purpose has been to provide a mixer which, hung
from a derrick or cableway, will receive a charge of raw materials at
stock pile and deliver a batch of mixed concrete to the work, the
operation of mixing being performed during the hoist to the work. By
providing two mixers so that one can be charged while the other is being
hoisted continuous operation is secured. The following are records of
operation of stationary gravity mixers of this type.
[Illustration: Fig. 25.--Hains Gravity Mixer, Telescoping Hopper Form.]
In building a dock at Baltimore, Md., a plant consisting of two large
hoppers and four charging hoppers with sand and stone bins above was
used. One man at each large conical hopper tending the gates and two men
charging the four pyramidal hoppers composed the mixer gang. A scow load
of sand and another of stone were moored alongside the work and a
clam-shell bucket dredge loaded the material from these barges into the
mixer bins. Each batch was 25 cu. ft. of 1-2-5 concrete rammed in place.
The men at the upper hoppers would empty a sack of cement in each, and
then by opening gates in the bottom of the bins above, allow the
necessary amounts of sand and stone to flow in, marks having been
previously made on the sides of the hoppers to show the correct
proportion of each of the ingredients. The amount of water found by
experience to be necessary, would then be dashed into the hoppers, and
the charges allowed to run into the first cone hopper below. Refilling
would begin at the top while the men were caring for the first charge in
the lower hoppers. The process was thus continuous. The concrete was
chuted directly into place from the bottom hopper. The record of output
was 110 batches per 10-hour day. Wages of common labor were $1.50 per
day. The labor cost per cubic yard of concrete in place was 35 cts.
In constructing the Cedar Grove reservoir at Newark, N. J., a Hains
mixer made the following records of output:
Cu. yds.
Best output per 10-hour day 403
Average daily output for best month 302
Average daily output for whole job 225
The stone, sand and cement were all raised by bucket elevators to the
top of the high wooden tower that supported the bins and mixer. There
were 10 men operating the mixer so that (exclusive of power, interest
and depreciation) the labor cost of mixing averaged only 7 cts. per cu.
yd.; during one month it was as low as 5 cts. per cu. yd. This does not
include delivering the materials to the men at the mixer, nor does it
include conveying the concrete away and placing it. The work was done by
contract.
~OUTPUT OF MIXERS.~--With a good mixer the output depends upon the methods
of conveying the materials to and from the mixer. Most makers of mixers
publish capacities of their machines in batches or cubic yards output
per hour; these figures may generally be taken as stating nearly the
maximum output possible. Considering batch mixers, as being the type
most commonly used, it may be assumed that where the work is well
organized and no delay occurs in delivering the materials to the mixer
that a batch every 2 minutes, or 300 batches in 10 hours, will be
averaged, and there are a few records of a batch every 1½ minutes.
To illustrate to how great an extent the output of a mixer depends on
the methods adopted in handling the materials to and from the mixer we
compare two actual cases that came under the authors' observation. The
mixers used were of the same size and make. In one case the stone was
shoveled into the charging hopper by four men and the sand and cement
were delivered in barrows by four other men; six men took the concrete
away in wheelbarrows. The output of the mixer was one batch every 5
minutes, or 120 batches, or 60 cu. yds., in 10 hours. In the other case
the sand and the stone were chuted directly into the charging hopper
from overhead bins and the mixer discharged into one-batch buckets on
cars. The output of the mixer was one batch every 2 minutes, or 300
batches in 10 hours. In the first case the capacity of the mixer was
limited by the ability of a gang of workable size to get the raw
materials to and the mixed concrete away from the mixer. In the second
case the capacity was limited only by the amount of mixing deemed
necessary.
While the necessity of rapid charging of a mixer to secure its best
output is generally realized it is often forgotten that the rapidity of
discharge is also a factor of importance. The size of the conveyor by
which the concrete is removed affects the time of discharge. By timing a
string of wheelbarrows in line the authors have found that it takes
about 7 seconds to fill each barrow; as a rule slight delays will
increase this time to 10 seconds. With a load of 1 cu. ft. per barrow it
requires 13 barrow loads to take away a ½ cu. yd. batch. This makes the
time of discharging a batch 130 seconds, or say 2 minutes. The same
mixer discharging into a batch size bucket will discharge in 15 to 20
seconds, saving at least 1½ minutes in discharging each batch.
~MIXER EFFICIENCY.~--Various attempts have been made to rate the
efficiency of concrete mixers. In all cases a percentage basis of
comparison has been adopted; arbitrary values are assigned to the
several functions of a mixer, such as 40 per cent. for perfect mixing,
10 per cent. for time of mixing and 25 per cent. for control of water,
the total being 100 per cent., and each mixer analyzed and given a
rating according as it is considered to approach the full value of any
function. Such percentage ratings are unscientific and misleading; they
present definite figures for what are mere arbitrary determinations. The
values assigned to the several functions are purely arbitrary in the
first place, and in the second place the decision as to how near those
values any mixer approaches are matters of personal judgment.
_The most efficient mixer is the one that gives the maximum product of
standard quality at the least cost for production._
This rule recognizes the fact that in practical construction different
standards of quality are accepted for different kinds of work. No
engineer demands, for example, the same quality of mixture for a
pavement base that he does for a reinforced concrete girder. If mixer A
turns out concrete of a quality suitable for pavement base cheaper than
does mixer B, then it is the more efficient mixer for the purpose, even
though mixer B will make the superior quality of concrete required for a
reinforced girder while mixer A will not. This method of determining
efficiency holds accurate for any standard of quality that may be
demanded.
Reading Tips
Use arrow keys to navigate
Press 'N' for next chapter
Press 'P' for previous chapter