Concrete Construction: Methods and Costs by Gillette and Hill
CHAPTER IV.
2973 words | Chapter 47
METHODS AND COST OF MAKING AND PLACING CONCRETE BY MACHINE.
The making and placing of concrete is virtually a manufacturing process.
This process as performed by manual labor is discussed in the preceding
chapter; it will be discussed here as it is performed by machinery. The
objects sought in using machinery for making and placing concrete are:
(1) The securing of a more perfectly mixed and uniform concrete, and (2)
the securing of a cheaper cost of concrete in place. As in every other
manufacturing process both objects cannot be obtained to the highest
degree without co-ordinate and universal efficiency throughout in plant
and methods. For example, the substitution of machine mixing for hand
mixing will not alone ensure cheaper concrete. If all materials are
delivered to the machine in wheelbarrows and if the concrete is conveyed
away in wheelbarrows, the cost of making concrete even with machine
mixers is high. On the other hand, where the materials are fed from bins
by gravity into the mixer and when the mixed concrete is hauled away in
cars, the cost of making the concrete may be very low. Making and
placing concrete by machinery involves not one but several mechanical
operations working in conjunction--in a word, a concrete making plant is
required.
The mechanical equipment of a concrete making plant has four duties to
perform. (1) It has to transport the raw materials from the cars or
boats or pits and place them in the stock piles or storage bins; (2) it
has to take the raw materials from stock and charge them to the mixer;
(3) it has to mix the raw materials into concrete and discharge the
mixture into transportable vehicles; and (4) it has to transport these
vehicles from the mixer to the work and discharge them. As all these
operations are interrelated component parts of one great process, it is
plain why one operation cannot lag without causing all the other
operations to slow up.
The mechanical devices which may be used for each of these operations
are various, and they may be combined in various ways to make the
complete train of machinery necessary to the complete process. In this
chapter we shall describe the character and qualities of each type of
devices separately. The practicable ways of combining them to form a
complete concrete making plant are best illustrated by descriptions and
records of work of actual plants, and such descriptions and records for
each class of structure considered in this book are given in the
following chapters and may be found by consulting the index. In
describing the various machines and devices we have made one
classification for those used in handling raw materials and mixed
concrete, for the reason that nearly all of them are suitable for either
purpose.
~UNLOADING WITH GRAB BUCKETS.~--The orange-peel or clam-shell bucket is an
excellent device for unloading sand or stone from cars or barges. The
cost of unloading, including cleaning up the portions not reached by the
bucket, is not more than from 2 to 5 cts. per cu. yd. A grab bucket of
either of these types can be applied to any derrick. In unloading broken
stone from barges at Ossining, N. Y., a Hayward clam-shell on a
stiff-leg derrick unloaded 100 cu. yds. of broken stone per day from
barge into wagons, with one engineman and one helper. In addition to the
bucket work there was 24 hours' labor cleaning on each 500-cu. yd. barge
load. The labor cost of unloading a 500-cu. yd. barge was as follows:
Per Cu. Yd.
One engineman, at $2.50 2.5 cts.
One helper, at $1.50 1.5 cts.
Labor cleaning, at $1.50 0.7 cts.
--------
Total cost per cubic yard 4.7 cts.
~INCLINES.~--Inclines to reach the tops of mixer and storage bins and the
level of concrete work can be operated on about the following grades:
For teams hauling wagons or cars, 2 per cent. maximum grade. A single
heavy team will haul a 5-cu. yd. car, with ordinary bearings, weighing
2½ tons empty and 12 tons loaded, with ease on a 1½ per cent. grade,
and with some difficulty on a 2 per cent. grade. A locomotive will
handle cars on a grade of from 4 to 5 per cent. For team haulage 20-lb.
rails may be used, and for locomotives 30-lb. rails. Grades steeper than
about 5 per cent. require cable haulage.
~TRESTLE AND CAR PLANTS.~--Trestle and car plants for handling both
concrete materials and mixed concrete have a wide range of application
and numerous examples of such plants are described in succeeding
chapters, and are noted in the index at the end of the book. The
following estimates of the cost of a trestle and car plant are given by
Mr. Wm. G. Fargo. The work is assumed to cover an area of 100×200 ft.
and to have three-fourths of its bulk below the economical elevation of
the mixer, which stands within 50 ft. of the near side of the work. If
the work is under 3,000 cu. yds. in bulk and there is a reasonable time
limit for completion one mixer of 200 cu. yds. capacity per 10-hour day
is assumed to be sufficient. The items of car plant cost will be about
as follows:
150 ft. trestle, at $1.50 $225
5 split switches with spring bridles, at $18 90
2 iron turntables, at $30 60
3-2/3 cu. yd. steel cars with roller bearings 190
------
Total $565
The trestle assumed is double 24-in. gage track, 6 ft. on centers;
stringers 6×8 ins.×22 to 24 ft.; ties 2×6 ins., 2½ ft. on centers;
running boards 2×12 ins. for each track, and 12-lb. rails; trestle legs,
average length 30 ft., of green poles at 5 cts. per foot. This outfit
with repairs and renewals amounting to 10 per cent., is considered good
for five season's work and the timber work for several jobs if not too
far apart. The yearly rental on the basis of five seasons' work would be
$124.30, or $1 per working day for a season of five months. Three cars
delivering ½ cu. yd. batches can deliver 200 cu. yds. of concrete, an
average of 100 ft. from the mixer in 10 hours. Five men, including a man
tending switches and turntable and one man to help dump, can operate the
plant. With wages at $1.75 per day the labor cost of handling 200 cu.
yds. of concrete would be 4-1/8 cts. per cu. yd.
~CABLEWAYS.~--Cableways arranged to span the work and if the area is wide
to travel across the work at right angles to the span will handle
concrete, concrete materials, forms, steel and supplies with great
economy. They are particularly suitable for bridge and dam work, filter
and reservoir work, building foundations and low buildings. The
arrangement of a cableway plant for bridge work is described in Chapter
XVII. A cableway of 800 ft. clear span on fixed towers 45 ft. high will
cost complete from $4,500 to $5,000, and will handle 200 cu. yds. of
concrete per 10-hour day. To put the cableway on traveling towers will
cost about $1,000 more. In constructing the Pittsburg filtration work
four traveling cableways from 250 to 600 ft. span were used. The towers
were from 50 to 60 ft. in height and each traveled on a 5-rail track.
The cableways were self-propelling. With conditions favorable each
cableway delivered 300 cu. yds. of concrete per day. A cableway plant
for heavy fortification work is described in Chapter XI.
~BELT CONVEYORS.~--Belt conveyors may be used successfully for handling
both concrete materials and mixed concrete. For handling wet concrete
the slope must be quite flat, and the belt must be provided with some
means of cleaning off the sticky mortar paste. In several cases rotating
brushes stationed at the end of the belt, where it turns over the tail
pulley, have worked successfully; these brushes sweep the belt clean.
Except for the cleaning device the ordinary arrangement of belt conveyor
for dry materials serves for concrete.
In constructing a large gas works at Astoria, Long Island, near New York
city, belt conveyors were used to handle both the sand, gravel and
cement bags and the mixed concrete. The belt for handling sand and
gravel is shown by Fig. 13. A derrick operating a clam-shell unloaded
the sand and gravel into a small hopper, discharging into dump cars
operated by a "dinky" up an incline, passing over sand and gravel
storage bins. A 20-in. belt conveyor ran horizontally 105 ft. under the
bins, then up an incline of 3.4 ft. in 125 ft. to feeding hoppers over
the mixers. This conveyor received alternately sand and gravel by chute
from the storage bins and bags of cement loaded by hand, and carried
them to the feeding bins and mixer platform. The speed of the belt was
350 ft. per minute, and it required 6 h.p. to operate it when carrying
100 tons per hour. The mixing was done in two Smith mixers, which turned
out 70 cu. yds. or 35 cu. yds. each per hour. The mixed concrete was
delivered onto a 50-ft. 24-in. belt conveyor traveling at a speed of 400
ft. per minute and dumping through a chute into cars. Only 1 h.p. was
required to run the concrete conveyor. A rotating brush was used to keep
the belt clean at the dumping end. It will be noted that only a small
amount of power is required for operation.
[Illustration: Fig. 13.--Belt Conveyor Transporting Sand and Gravel.]
~CHUTES.~--Chutes of wood or iron are among the simplest and most
efficient means of moving the cement, sand and stone and the mixed
concrete when the ground levels permit such devices.
Bags of cement if given a start in casting will slide down a steel or
very smooth wooden chute with a slope of 1 ft. in 5 or 6 ft. A wooden
trough 12 ins. deep and 24 ins. wide with boards dressed on the inside
may be used. When the inclination is steep and the fall is great, some
device is necessary to diminish the velocity of descent; the following
is an example of such a device which was successfully employed in a
chute of the above dimensions, 400 ft. long and having a drop of 110 ft.
This chute had a maximum inclination of 45° and its lower end curved to
a horizontal tangent, running into the storehouse. Near the bottom of
the chute a horizontal strip was nailed across the upper edges and to it
was nailed the upper end of a 20 ft., 1×12-in. board, the lower end of
which rested on the bottom of the chute. Several pieces of timber spiked
to the upper side loaded the lower end of this board. The cement bag in
descending wedged itself into the angle between the chute and the board
and lifted the latter, the spring of the board and the weight at the
lower end offering enough resistance to cut down the velocity. After the
chute had been in use for some time and had worn smooth it was found
necessary to add two more brakes to check the bags.
Broken stone will slide down a steel or steel lined chute with a slope
of 1 in 3 or 4 ft. if given a start in casting. Damp sand will not slide
down a chute with a slope of 1½ in 1.
A wet cement grout will flow down a smooth plank chute, with a slope of
1 in 4 ft., and wet concrete will move on the same slope; comparatively
dry concrete requires a slope of nearly 1 in 1, or 45°, to secure free
movement. Mr. W. J. Douglas gives the following examples of conveying
concrete by chute, prefaced by the statement that his experience
indicates that concrete can thus be conveyed considerable distances
without material injury if proper precautions are taken.
In the first case a semi-circular steel trough about 2 ft. wide and 1
ft. deep and 15 ft. long set on a slope of 45° was used. A lift gate of
sheet steel was set in the chute about 2 ft. from the upper end. The
concrete was allowed to accumulate behind this gate until a wheelbarrow
load was had, when the batch was let loose by lifting the gate and was
discharged into barrows at the bottom. In another case a vertical chute
15 ft. long, consisting of a 15-in. square box with a canvas end, was
used. The concrete was dumped into the chute in batches of about 8 cu.
ft.; two men at the bottom "cut down" the pile with hoes to keep it from
coning and causing separation of the stone. In a third case a continuous
mixer fed into a sheet iron lined rectangular chute about 2½ ft. wide
and 1 ft. deep, with a vertical drop of 60 ft. on a slope of 1 in 1, or
45°. A gate was fixed in the chute 2 ft. from the top and at the bottom
the chute fed into a pyramidal hopper 3 ft. square at the top, 1 ft.
square at the bottom and 4½ ft. deep. This hopper was provided with a
bottom gate and was set on legs so that its top was about 10 ft. above
ground. As the concrete filled in the hopper was raised and the chute
cut off. The hopper was kept full all the time and was discharged by
bottom gate and spout into wheelbarrows. In a fourth case the apparatus
shown by the sketch, Fig. 14, was used. The continuous mixer discharged
onto an 18-in. rubber conveyor belt on conical rollers and 18 ft. long.
The inner end of the conveyor frame was carried on the ground at the
edge of the pit and the outer end was supported by ropes from the top of
a gallows frame standing on the pit bottom. The belt discharged over end
into a vertical steel chute 12 ins. in diameter and 8 ft. long; this
chute was fastened to the conveyor frame. Encircling and overlapping the
12-in. chute was a second slightly larger chute suspended by means of
two ropes from the gallows frame. The bottom of this second chute was
kept about 6 ins. below the top edges of a pyramidal hopper like the one
described above. In operation the chutes and the hopper were kept filled
with concrete so that the only drop of the concrete was 3 ft. from the
conveyor belt into the topmost chute.
[Illustration: Fig. 14.--Belt Conveyor and Chute for Handling Concrete.]
Concrete may be handled in long flat chutes by stationing men along the
chute with shovels which they work like paddles to keep the mixture
moving. In one case concrete was so handled in a chute 200 ft. long
having a slope of 1 in 10 ft. The chute was a V-shaped trough made of
1×12-in. boards in sections 16 ft. long. The men paddling were stationed
10 ft. apart, so that with wages at $1.50 per day the cost would be 1½
cts. per cu. yd. for every 10 ft. the concrete was conveyed. In
connection with this particular work we are informed that a Eureka
continuous mixer was used. The gravel was dumped near the mixer and a
team hitched to a drag scraper delivered the gravel alongside the mixer.
Four men shoveled the gravel into the measuring hopper, but only two men
worked at a time, shoveling for a period of 15 minutes and then resting
for a corresponding period while the other two men worked. In this
manner the four men shoveled enough gravel to make 100 cu. yds. of
concrete per day. A fifth man opened the cement bags and kept the cement
hopper filled.
~METHODS OF CHARGING MIXERS.~--By charging is meant the process of
delivering raw materials from stock into the mixer. Several methods are
practiced and will be considered in the following order: (1) By gravity
from overhead bins; (2) by wheelbarrow or hand cart (a) to charging
chute and (b) to elevating charging hoppers; (3) by charging cars
operated by cable or other means; (4) by shoveling directly into mixer;
(5) by derricks or other hoists.
~Charging by Gravity from Overhead Bins.~--Chuting the sand and stone from
overhead bins to the charging hopper is a simple, rapid and economical
method of charging mixers. The bottoms of the bins should always be high
enough above the charging floor to give ample head room for men to move
about erect, and the length of chute may be anything reasonable more
than this that conditions such as the side hill delivery of material may
necessitate. When the mixer is located to one side of the bins the slope
of the chute will have to be watched. Broken stone or pebbles will move
on a comparatively flat slope but sand, particularly if damp, requires a
steep chute. The measuring hopper is best kept entirely independent of
the mixer so that it can be filled with a new charge while the mixer is
turning and discharging the preceding batch. One man can attend the sand
and cement chutes if they be conveniently arranged, and one man can open
and empty the cement bags if they be stacked close at hand. A third man
will level off the sand and stone in the measuring hopper and help in
the chuting. A gang of this size will easily measure up a charge every 2
minutes when no delays occur.
[Illustration: Fig. 15.--Side Hill Mixing Plant.]
A number of plants charging by gravity from overhead bins are described
in succeeding chapters and are referenced in the index. As a general
example a side hill plant of conventional construction is shown by Fig.
Reading Tips
Use arrow keys to navigate
Press 'N' for next chapter
Press 'P' for previous chapter