Concrete Construction: Methods and Costs by Gillette and Hill
CHAPTER XVII.
7017 words | Chapter 69
METHODS AND COST OF CONSTRUCTING ARCH AND GIRDER BRIDGES.
The construction problems in arch and girder bridges of moderate spans
are simple, and with the exception of center construction and
arrangement of plant for making and placing concrete, are best explained
by citing specific examples of bridge work. This is the arrangement
followed in this chapter.
~CENTERS.~--The construction of centers is no less important a task for
concrete arches than for stone arches. This means that success in the
construction of concrete arches depends quite as much upon the
sufficiency of the center construction as it does upon any other portion
of the work. The center must, in a word, remain as nearly as possible
invariable in level and form from the time it is made ready for the
concrete until the time it is removed from underneath the arch, and,
when the time for removal comes, the construction must be such that that
operation can be performed with ease and without shock or jar to the
masonry. The problem of center construction is thus the two-fold one of
building a structure which is immovable until movement is desired and
then moves at will. Incidentally these requisites must be obtained with
the least combined expenditure for materials, framing, erection and
removal, and with the greatest salvage of useful material when the work
is over. The factors to be taken count of are it, will be seen, numerous
and may exist in innumerable combinations.
[Illustration: Fig. 148.--Center for 50 ft. Arch Span (Supported).]
[Illustration: Fig. 149.--Center for 50-ft. Arch Span (Cocket).]
Centers may be classified into two types: (1). Centers whose supports
must be arranged so as to leave a clear opening under the center for
passing craft or other purposes, and (2) centers whose supports can be
arranged in any way that judgment and economy dictate. Centers of the
first class are commonly called cocket centers. As examples of a cocket
and of a supported center and also as examples of well thought out
center design we give the two centers shown by Figs. 148 and 149, both
designed for a 50-ft. span segmental arch by the same engineer. The
development of the center shown by Fig. 148 into the cocket center shown
by Fig. 149 is plainly traceable from the drawings. In respect to the
center shown by Fig. 149 which was the construction actually adopted we
are informed that 16,464 ft. B. M. were required for a center 36 ft.
long, that the framing cost about $12 per M. ft. B. M., with carpenters'
wages at $4 per day, and that the cost of bolts and nuts was about $1.50
per M. ft. B. M. With lumber at $20 per M. ft. B. M., this center framed
and erected would cost about $35 per M. ft. B. M. As an example of
framed centers for larger spans we show by Fig. 158 the centers for the
Connecticut Avenue Bridge at Washington, D. C., with costs and
quantities; other references to costs are contained in the index.
A center of very economical construction is shown by Fig. 159, and is
described in detail in the accompanying text. The distinctive feature of
this center is the use of lagging laid lengthwise of the arch and bent
to curve. Another example of this form of construction may be found in a
3-span arch bridge built at Mechanicsville, N. Y., in 1903. The viaduct
was 17 ft. wide over all, and consisted of two 100-ft. spans and one
50-ft. span. Pile bents were driven to bed rock, the piles being spaced
6 ft. apart and the bents 10 ft. apart. Each bent was capped with
10×12-in. timber. On these caps were laid four lines of 10×12-in.
stringers, and 8×10-in. posts 3 ft. apart were erected on these
stringers, and each set of four posts across the arch was capped with
8×10-in timbers the ends of which projected 3 ft. beyond the faces of
the arch. The tops of these cross caps were beveled to receive the
lagging which was put on parallel with the center line of the viaduct,
sprung down and nailed to the caps. This lagging consisted of rough
1-in. boards for a lower course, on top of which was laid 1-in. boards
dressed on the upper sides. Hardwood wedges were used under the posts
for removing the centers. In the centers, forms and braces for the three
arches there were used 140,000 ft. B. M. of lumber. The structure
contained 2,500 cu. yds. of concrete.
Another type of center that merits consideration in many places is one
developed by Mr. Daniel B. Luten and used by him in the construction of
many arches of the Luten type of reinforced concrete arch. The
particular feature of this type of arch is that in shallow streams for
bridges of ordinary span the ends of the arch ring are tied together
across stream by a slab of concrete reinforced to take tension. This
slab is intended to serve the double purpose of a tie to keep the arch
from spreading and thus reduce the weight of abutments and of a pavement
preventing scour and its tendency to undermine the abutments.
Incidentally this concrete slab, which is built first, serves as a
footing for the supports carrying the arch center.
As an illustration of the center we choose a specific structure. In
building a 95-ft. span, 11-ft. 1-in. rise arch bridge at Yorktown, Ind.,
in 1905, the centers were designed so as to avoid the use of sand boxes
or wedges. Ribs of 2×12-in. pieces cut to the arc of the arch soffit
were supported on uprights standing on the concrete stream bed pavement.
The uprights were so proportioned by Gordon's formula for columns that
without bracing they would be too light to support the load of concrete
and earth filling that was to come upon them, but when braced at two
points dividing the uprights approximately into thirds they would
support their loading rigidly and without buckling. The design in detail
was as follows: The uprights near the middle of the span were about 15
ft. long and were spaced 7 ft. apart across the stream and 3 ft. apart
across the bridge. Each upright then was to support a loading of
concrete of 7 ft.×3 ft.×26 ins. and an earth fill 1 ft.×7 ft.×3 ft., or
a total load of about 9,000 lbs. Applying Gordon's formula for struts
with free ends,
f S
P = -------------------
l²
I + --------
125h²
where P is the total load = 9,000 lbs., f is fibre stress for
oak--1,600 lbs., l is length of strut in inches and h is least
diameter of strut in inches, it was found that for a length of 15 ft. a
7×7-in. upright would be required to satisfy the formula, but for a
length of 5 ft., which would result from bracing each strut at two
points, a 4×4-in. timber satisfied the formula. Therefore, 4×4-in.
timbers braced at two points were used for the longest uprights. About
30 days after the completion of the arch the bracing was removed from
the uprights, beginning at the ends of the span and working towards the
middle. As the bracing was being removed the uprights gradually yielded,
buckling from 4 to 6 ins. from the vertical and allowing the arch to
settle about ¼ in. at the crown. This type of center has been
successfully employed in a large number of bridges.
Figure 150 shows a center for a 125-ft. span parabolic arch with the
amount and character of the stresses indicated and with a diagram of the
actual deflections as measured during the work.
[Illustration: Fig. 150.--Center for 125-ft. Span Parabolic Arch with
Diagram of Deflections.]
In calculating centers of moderate span there is seldom need of more
than the simple formulas and tables given in Chapter IX. When the spans
become larger, and particularly when they become very large--over 200
ft.--the problem of calculating centers becomes complex. None but an
engineer familiar with statics and the strengths of materials and
knowing the efficiency of structural details should be considered for
such a task. Such computations are not within the intended scope of this
book, and the design of large centers will be passed with the
presentation of a single example, the center for the Walnut Lane Bridge
at Philadelphia, Pa.
The main arch span of the Walnut Lane Bridge consists of twin arches
spaced some 16 ft. apart at the crowns and connected across by the
floor. Each of the twin arch rings has a span of 232 ft. and a rise of
70¼ ft., is 9½ ft. thick and 21½ ft. wide at the skewback and 5½ ft.
thick and 18 ft. wide at the crown. The plan was to build a center
complete for one arch ring and then to shift it along and re-use it for
building the other arch ring. The centering used is shown in diagram by
Fig. 151. It consists of five parts: (1) Six concrete piers running the
full width of the bridge upon which the structure was moved; (2) a steel
framework up to E G, called the "primary bent"; (3) a separate timber
portion below the heavy lines E I and W' I'; (4) the "main staging"
included in the trapezoid E I W' I', and (5) the "upper trestle"
extending from I I' to the intrados.
[Illustration: Fig. 151.--Center for 232-ft. Span Arch at Philadelphia,
Pa.]
The primary bent consists of four I-beam post bents having channel
chords, the whole braced together rigidly by angles. Each bent is
carried on 1½ ft.×6 in. steel rollers running on a track of 19×½ in.
plate on top of the concrete piers. Between the primary bents and the
main staging, and also between the main staging and the upper trestles
are lifting devices. The mode of operation planned is as follows: When
the center has been erected as shown and the arch ring concreted the
separate stagings under K I and K' I' are taken down. Next the
portions under the lines I E and I' W' will be taken down and
erected under the second arch. Finally the remainder of the center will
be shifted sidewise on the rollers to position under the second arch.
~MIXING AND TRANSPORTING CONCRETE.~--The nature of the plant for mixing
and handling the concrete in bridge work will vary not only with varying
local conditions but with the size and length of the bridge. For single
span structures of moderate size the concrete can be handled directly by
derricks or on runways by carts and wheelbarrows. For bridges of several
spans the accepted methods of transport are cableways, cars and cars and
derricks. Typical examples of each type of plant are given in the
following paragraphs, and also in the succeeding descriptions of the
Connecticut Avenue Bridge at Washington, D. C., and of a five-span arch
bridge.
~Cableway Plants.~--The bridge was 710 ft. long between abutments and 62
ft. wide; it had a center span of 110 ft., flanked on each side by a
100-ft., a 90-ft. and an 80-ft. span. The mixing plant was located at
one end of the bridge and consisted of a Drake continuous mixer,
discharging one-half at the mixer and one-half by belt conveyor to a
point 50 ft. away, so as to supply the buckets of two parallel
cableways. The mixer output per 10-hour day was 400 cu. yds. and the
mixing plant was operated at a cost of $27 per day, making the cost of
mixing alone 6¾ cts. per cu. yd. The sand and gravel were excavated from
a pit 4½ miles away and delivered by electric cars to the bridge site at
a cost of 50 cts. per cu. yd. Two 930-ft. span Lambert cableways set
parallel with the bridge, one 25 ft. each side of the center axis, were
used to deliver the concrete from mixer to forms. The cableway towers
were 70 ft. high and the cables had a deflection of 35 ft.; they were
designed for a load of 7 tons, but the average load carried was only 3
or 4 tons. These cableways handled practically all the materials used in
the construction of the bridge. They delivered from mixer to the work
400 cu. yds. of concrete 450 ft. in 10 hours at a cost of 2 cts. per cu.
yd. for operation.
[Illustration: Fig. 151a.--Cableway for Concreting Bridge Piers.]
Another example of cableway arrangement for concreting bridge piers is
shown by Fig. 151a. The river was about 800 ft. wide, about 3 ft. deep
and had banks about 20 ft. high. The piers were about 21 ft. high. The
towers for the cableway consisted of a 55-ft. derrick without boom,
placed near the bank on the center line of the piers and well guyed and
a two-leg bent placed in the middle of the river and held in place by
four cable guys anchored to the river bottom. A ¾-in. steel hoisting
cable was stretched from a deadman on shore, about 150 ft. back of the
derrick, and followed along the center line of the piers, past the
derrick just clearing it, to the bent in the middle of the river. At the
top of this bent was a 16-in. cable block. Through this block the cable
passed down and was made fast to a weight, consisting of a skip loaded
with concrete until the cable had the required tension, and a pitch of
18 to 20 ft. from center of river to anchor on shore. In order to secure
the required pitch from the shore to the river bent the boom fall of the
derrick was hooked onto the cable at the foot of the mast, and then, by
going ahead on the single drum hoisting engine, was raised to the mast
head. This gave the cable a pitch of 18 to 20 ft. from mast head to top
of bent in river. The carriage vised on the cableway consisted of two
16-in. cable sheaves with iron straps, forming a triangle, with a chain
hanging from the bottom point, to which was attached the 5 cu. ft.
capacity concrete bucket. The concrete was mixed on a platform at the
foot of the mast. When ready for operation the chain on the carrier was
hooked to the bucket of concrete, the engine started, and both bucket
and cable raised, the former running by gravity to the pier. The speed
of descent was governed by the height to which the cable was raised on
the derrick, and as the bucket neared the dumping point the engine was
slacked off and the cable leveled. The bucket was dumped by a man on a
staging erected on the pier form. For the return of the bucket the
engine was slacked off and the weight on the river bent would pull the
cable tight so that the pitch would be toward the shore and the bucket
could run down the grade to the mixing platform, the speed being
governed as before by leveling the cable. When the piers were completed
to the middle of the river the engine and derrick were taken over to
opposite side of the river, the bent being left in the middle, and the
work continued. By using the extreme grade of the cable it was found
that the bucket would run from the platform to the bent (400 ft.) in
less than 35 seconds.
[Illustration: Fig. 152.--Sketch Showing Car and Trestle Plant for
Concreting an Arch Bridge.]
~Car Plant for 4-Span Arch Bridge.~--The bridge had four 110-ft. skew
spans, and a total length of 554 ft. The mixing plant was located
alongside one abutment on a side hill so that sand and stone could be
stored on the slope above. The mixer was set on a platform high enough
to clear cars below. Above it and to the rear a charging platform
reached back to the stone and sand piles. Side dump cars running on a
track on the charging platform took sand and stone to the mixer and
cement was got from a cement house at charging platform level. The
concrete for the abutment adjacent to the mixer was handled in buckets
by a guy derrick. A trestle, Fig. 152, was then built out from the mixer
to the first pier; this trestle was so located as to clear the future
bridge about 20 ft. and was carried out from shore parallel to the
bridge until nearly opposite the pier site, where it was swung toward
and across the pier. The concrete was received from the mixer in bottom
dump push cars; these cars were run out over the pier site and dumped.
When the first pier had been concreted to springing line level, the main
trestle was extended to opposite the second pier and the branch track
was removed from over the first pier and placed over the second pier.
This operation was repeated for the third pier. The last extension of
the main track was to the far shore abutment, where the bodies of the
cars were hoisted by derrick and dumped into the abutment forms. The
derrick was the same one used for the first abutment having been moved
and set up during the construction of the intermediate piers. To
construct the arches a second trestle was built composed partly of new
work and partly of the staging for the arch centers. This trestle rose
on an incline from the mixer to the first pier across which it was
carried at approximately crown level of the arch. The concrete for the
portion of the pier above springing line and for the lower portions of
the haunches was dumped direct from the cars. For the upper parts of the
arch the concrete was brought to the pier track in two-wheel carts on
push cars and thence these carts were taken along the arch toward shore
on runways. When the first arch had been concreted the second trestle
was extended to pier two and the operation repeated to concrete the
second arch.
~Hoist and Car Plant for 21-Span Arch Viaduct.~--The double track concrete
viaduct replaced a single track steel viaduct, being built around and
embedding the original steel structure which was maintained in service.
The concrete viaduct consisted of 21 spans of 26 ft., 7 spans of 16 ft.,
and 2 spans of 22 ft. With piers it required about 15,000 cu. yds. of
concrete. Two Ransome concrete hoists, one on each side of the original
steel structure near one end, were supplied with concrete by a No. 4
Ransome mixer. The mixer discharged direct into the bucket of one hoist
and by means of a shuttle car and chute into the bucket of the other
hoist.
The shuttle car ran from the mixer up an incline laid with two tracks,
one narrow gage and one wide gage, having the same center line. The car
was open at the front end and its two rear wheels rode on the broad gage
rails and its two forward wheels rode on the narrow gage rails. At the
top of the incline the narrow gage rails pitched sharply below the grade
of the broad gage rails so that the rear end of the car was tilted up
enough to pour the concrete into a chute which led to the bucket of the
hoist. The sand and gravel bins were elevated above the mixer and
received their materials from cars which dumped directly from the steel
viaduct.
The hoist buckets discharged into two hoppers mounted on platforms on
the old viaduct. These platforms straddled two narrow gage tracks, one
on each side of the old viaduct parallel to and clearing the main track.
These side tracks were carried on the cantilever ends of long timbers
laid across the old viaduct between ties. At street crossings the
overhanging ends of the long timbers were strutted diagonally down to
the outside shelf of the bottom chords of the plate girder spans. Six
cars were used and the concrete was dumped by them directly into the
forms; the fall from the track above being in some cases 40 ft. The
hoists and shuttle car were operated by an 8½×12-in. Lambert derrick
engine, the boiler of which also supplied steam to the mixer engine. The
concrete cars were operated by cable haulage by two Lambert 7×10-in.
engines.
The labor force employed in mixing and placing concrete, including form
work, was 45 men, and this force placed on an average 200 cu. yds. of
concrete per day. Assuming wages we get the following costs of different
parts of the work for labor above:
Item. Per day. Per cu. yd.
1 timekeeper at $2.50 $ 2.50 $0.0125
1 general foreman at $5 5.00 0.0250
3 enginemen at $5 15.00 0.0750
1 carpenter foreman at $4 4.00 0.0200
12 carpenters at $3.50 42.00 0.2100
1 foreman at $4 4.00 0.0200
8 men mixing and transporting at $1.75 14.00 0.0700
13 men placing concrete at $1.75 22.75 0.1137
1 foreman finishing at $4 4.00 0.0200
4 laborers finishing at $1.75 7.00 0.0350
------ -------
45 men at $2.70 $120.25 $0.6012
It is probable that the carpenter work includes merely shifting and
erecting forms and not the first cost of framing centers. No materials,
of course, are included. It should be kept in mind that while the output
and labor force are exact the wages are assumed.
~Traveling Derrick Plant for 4-Span Arch Bridge.~--The bridge consisted of
four 70-ft. arch spans and was built close alongside an old bridge which
it was ultimately to replace. The approach from the west was across a
wide flat; at the east the ground rose more abruptly from the stream.
Conditions prevented the use of a long spur track and also made it
necessary to install all plant at and to handle all material from the
west bank. A diagram sketch of the arrangement adopted is shown by Fig.
153.
[Illustration: Fig. 153.--Sketch Showing Traveling Derrick Plant for
Concreting an Arch Bridge.]
The track from the west approached the existing bridge on an embankment
25 ft. high. A spur track 175 ft. long from clear post to end was built
on trestle as shown. The cement house and mixer platform were placed at
the foot of the embankment at opposite ends of the spur track. Between
the two the slope of the embankment was sheeted with 1-in. boards and a
timber bulkhead 4 ft. high was built along the toe of the sheeting.
Stone, sand and coal were stored behind the bulkhead on the sheeting. A
runway close to the bulkhead connected the cement house with the mixer
platform, all materials to the mixer being wheeled in barrows on this
runway. A ¾-cu. yd. Smith mixer was set on a platform 5 ft. above ground
with its discharge end toward the stream. Beginning under this platform
a service track was carried across the flat and stream to the extreme
end of the east abutment. This track consisted of three rails, two rails
4 ft. apart next to the work and a third rail 25 ft. from the first. The
4-ft. gage provided for cars carrying concrete buckets from the mixer
and the 25-ft. gage provided for a traveling derrick; 18-lb. rails were
used and they proved to be too light, 40-lb. rails are suggested. The
derrick consisted of a triangular platform carrying a stiff leg derrick
with a 25-ft. mast and mounted on five wheels. The wheels were double
flange 16 ins. diameter and cost $30 each, being the most expensive part
of the derrick. The derrick was made on the ground and took four
carpenters between 3 and 4 days to build. Derrick and 350 ft. of service
track, including pole trestle across the stream, cost between $600 and
$800. The derrick was moved by means of a cable wrapped around one spool
of the Flory double-drum hoisting engine and leading forward and back to
deadmen set at opposite ends of the service track. Cars carrying
concrete buckets were run out on the 4-ft. gage track and the buckets
were hoisted by the derrick and dumped into a ½-cu. yd. car running on a
movable transverse track across the bridge. This transverse track was
necessary to handle the concrete to the far side of the work, the
derrick being set too low and the boom being too short to reach. The
derrick was used to handle material excavated from the pier foundations
and also to tear down the centers and spandrel forms. Some rather
general figures on the cost of this bridge are given by Mr. H. C.
Harrison, the contractor. They are:
Materials: Total.
6,000 bbls. cement at $2.05 $12,300
2,500 cu. yds. sand at $0.80 2,000
5,000 cu. yds. stone at $0.85 4,250
260 M. ft. B. M. lumber at $17 4,420
-------
Total $22,970
Labor:
Cofferdams, excavation and pumping $ 3,000
Forms, falseworks and centers 2,000
Mixing and placing concrete 4,000
Placing reinforcement 400
Removing falseworks, forms, etc. 1,200
One coat pitch and paper 150
Building plant, etc. 2,250
-------
Total $13,000
Mr. Harrison states that including plant cost, delays, floods and
incidentals the cost per cubic yard of concrete was $8 and that
excluding these items the cost was $6 per cu. yd.
~COST OF CONSTRUCTING CONCRETE HIGHWAY BRIDGE, GREENE COUNTY, IOWA.~--The
following is the itemized cost of constructing a reinforced concrete
slab highway bridge, one of several built by the Highway Commissioners
of Greene County, Iowa, in 1906. The figures are given by Messrs. Henry
Haag and D. E. Donovan, the last being the foreman of the concrete gang
doing the work. All bridges consist of 10 to 12-in. slabs reinforced
with old steel rails and of abutments and wing walls reinforced with old
rods, bars or angles selected from junk. This junk metal cost 0.6 cts.
per pound and the rails cut to length cost 1.15 cts. per pound f. o. b.
cars. The work was done by a special gang, the men receiving $1.50 per
day and board. As a rule the footings were made 2 ft. wide and as high
as need be to get above the water and dirt. Before the footing concrete
set steel rods, bars or angles were placed; they were long enough to
reach the height of the wall and 3 to 6 ins. into the slab. The forms
for the abutment and wing walls and for the floor slab were then erected
complete before any more concrete was placed. No carpenter was employed,
every man on the job having been taught to take his certain place in the
work, then, the forms being erected, every man had his particular place
in the work of mixing and placing the concrete. The foreman saw that the
reinforcement was properly placed and watched over the accuracy of the
work generally. The concrete was allowed to set on the centers for from
30 to 40 days; the other form work was taken down after three days and
travel over the bridge permitted after three or four days. The concrete
was mixed wet. The bridge whose cost is given was 22 ft. wide and 16 ft.
span with 2-ft. wing walls.
The foundations are 4 ft. deep and 2½ ft. wide. The walls on top of the
foundations are 7 ft. high, 18 ins. wide at the base, and battered up to
14 ins. at the top for wings and 12 ins. at top for walls. The floor is
22 ft. by 18 ft. and 1 ft. thick. The wheel guard is 12 ins. thick by 14
ins. wide and 32 ft. long. The itemized cost of this bridge, containing
73 cu. yds. of concrete, is as follows:
Materials. Total. Per cu. yd.
70 cu. yds. gravel at 70 cts $ 49.00 $0.6726
10 cu. yds. broken stone at 70 cts 7.00 0.0959
75 bbls. cement at $2.20 165.00 2.2603
7,000 lbs. steel rails at 1.15 cts 80.50 1.1027
1,000 lbs. junk rails at 0.6 cts 6.00 0.0819
200 ft. B. M. lumber wasted at $29 5.80 0.0794
15 lbs. nails at 3 cts 0.45 0.0061
Labor and Supplies:
2 days excavation at $14 28.00 0.3835
¾ day foundation at $14 10.00 0.1369
1½ days building forms at $14 21.00 0.2876
2 days filling forms at $14 28.00 0.3835
Hauling lumber and tools 8.00 0.1096
Hauling cement and tools 18.00 0.2465
Taking off forms 2.30 0.0315
1,000 lbs. coal at $4 per ton 2.00 0.0274
------ -------
Total cost $431.05 $5.9054
In round figures the cost per cubic yard of concrete in the finished
bridge was $5.90. Summarizing we have the following cost per cubic yard
of concrete in place:
Item. Per cu. yd.
Cement $2.26
Steel 1.22
Lumber 0.22
Gravel and stone 0.76
Labor 1.41
Coal 0.03
-----
Total $5.90
The average cost of concrete in place for all the work done in Greene
County by day labor was $6.25 per cu. yd. In the job itemized above the
bank caved in, causing an extra expense for removing the earth. The
gravel used in this bridge was very good clean river gravel.
~METHOD AND COST OF CONSTRUCTING TWO HIGHWAY GIRDER BRIDGES.~--The
following account of the methods and costs of constructing two slab and
beam highway bridge decks on old masonry abutments is taken from
records kept by Mr. Daniel J. Hauer. The first bridge was a single span
15 ft. long that replaced wooden stringers and floor that had become
unsafe; the second was two short spans of a steel bridge that was too
light for the traffic of the road, and it was torn down and moved
elsewhere, by the county authorities. The work was done by contract, and
in each case consisted of building the reinforced floor and girders on
the old masonry walls that were in good condition. While the work was
going on traffic was turned off the bridges, fords being used instead.
Figure 154 shows a sketch of the cross-section of the floor and girders.
In Example I the girders had a depth below the floor of 12 ins. and were
of the same width. In Example II the girders were 14 ins. wide and had a
depth below the floor of 18 ins. The floors on both bridges were 6 ins.
thick. Kahn bars were used for reinforcement.
[Illustration: Fig. 154.--Cross-Section of Concrete Girder Bridge.]
_Example I._--This bridge was but little more than 5 ft. above the
stream, which was shallow and not over 7 ft. wide, unless swollen by
floods. The bottom for several hundred feet on either side of the bridge
was covered with coarse sand and gravel, that had pebbles in it from the
size of a goose egg down. This was taken from the stream by men with
picks and shovels and hauled to the site of the work with wheelbarrows,
and then screened so as to separate the gravel from the sand. As it was
found that the sand was so coarse that it would take more cement than
the specifications called for in a 1-2½-5 mixture, some much finer sand
was bought and mixed with it. For the privilege of taking the sand from
the stream $1 was paid the property owner. This was done to get a
receipt and release from him, rather than as an attempt to pay royalty
on the gravel and sand. This dollar is included in the cost of the labor
in getting these materials.
The cost of materials per cubic yard for the bridge was as given below,
the mixture being as stated above. The cement cost $1.40 per barrel,
delivered at the bridge.
Per Cu. Yd.
Steel $2.50
Gravel and sand .75
Sand (bought) .30
Cement 1.57
-----
Per cubic yard $5.12
It is of interest to note the cost of the gravel and sand, as this
includes the cost of digging it, wheeling it in a wheelbarrow an average
distance of 100 ft., and then screening it and putting it in two stock
piles. The proportion of bought sand used with the creek sand was
one-half.
The old wooden floor and stringers had to be torn down. This was done at
a cost of $1.30 per M. ft. B. M., and furnished 60 per cent. of the
lumber needed for forms. The floor boards were 3-in. yellow pine planks,
and the stringers 6×12-in. timbers, rather heavy, but money was saved by
using them. The 6×12-in. timbers were used for props for the centering.
Additional lumber was bought, delivered at the site of the bridge, for
$20.84 per M. ft. B. M.
In framing and erecting the forms the carpenter had laborers helping
him, he doing only carpenter's work, the laborers carrying and lifting
all pieces wherever possible. The carpenter's work was about 40 per
cent. of the total labor cost, which was as follows per cubic yard of
concrete:
Tearing down old bridge $0.08
Lumber .85
Nails .15
Labor, carpenter .77
Labor, laborers .96
-----
$2.81
The forms were torn down by laborers, with the assistance of a man and
his helper, who were given the boards for this labor and to haul them
away. This reduced this item somewhat, as it only amounted to 20 cts.
per cu. yd.
The cost of the forms per thousand feet board measure was:
New lumber $20.82
Nails 1.44
Labor, carpenter 7.60
Labor, laborers 9.50
Tearing down 2.00
------
$41.36
All the men, including the carpenter, worked 10 hours per day, and were
paid at the following rates:
Carpenter $2.50
Sub-foreman 2.00
Laborers 1.50
A regular foreman was not employed, but an intelligent and handy workman
was given 50 cts. additional to lead the men and look after them when
the contractor was not present.
A gang of six men did the work of mixing and placing, and as the stock
piles were close by the mixing board no extra men were needed to handle
materials. Water was secured from the stream in buckets for mixing. The
mixture was made very wet. The cost per cubic yard for the entire
structure was as follows:
Preparing for mixing $0.04
Cleaning out forms .06
Handling steel .03
Mixing and placing 1.15
Ramming .23
-----
$1.51
The cost of the contractor's expense of bidding, car fare, etc., is
listed under general expense, and gives a total cost per cubic yard of:
Materials $ 5.12
Erecting forms 2.81
Tearing down forms .20
Labor 1.51
General expense 2.00
------
$11.64
_Example II._--For this bridge both the stone and sand had to be bought.
The bridge floor was nearly 14 ft. above the bottom of the stream, which
was shallow. The wages paid were as follows for a 10-hour day:
Foreman $3.00
Laborers 1.50
Carpenters were paid $3 for an 8-hour day and time and a half for all
overtime, which they frequently made.
For the girders a 1-2-4 mixture was used. The cement, delivered at the
bridge, cost $1.21 per barrel, there being 8 cts. a barrel storage and 8
cts. a barrel for hauling included in this. The sand was paid for at an
agreed price per cartload delivered, which averaged $1.34 per cu. yd.
The stone was crushed so as to pass a 1½-in. ring in all directions. It
was delivered at the bridge for $2.75 per cu. yd. This makes the cost
per cubic yard for materials as follows:
Steel $1.41
Cement 2.18
Sand .67
Stone 2.75
-----
$7.01
For the floor a 1-3-5 mixture was used, making a cost for material of:
Steel $1.02
Cement 1.69
Sand .67
Stone 2.75
-----
$6.13
Two-inch rough pine boards were used to make the troughs for the
girders, while 1-in. rough boards were used for the floors. These were
all supported by 3×4-in. pine scantlings. This lumber cost delivered
$17.50 per M. ft. B. M. Carpenters did all the framing, and erected it
with the help of laborers. All the carrying of the lumber was done by
laborers. This reduced the cost of the work, as the laborers' wages
amounted to one-third of the whole cost. As soon as the forms were all
in place, which was before the mixing of concrete commenced, the
carpenters were discharged. The cost per cubic yard for forms was:
Lumber $2.82
Nails .05
Labor, carpenters 1.24
Laborers .62
-----
$4.73
The tearing down of the forms was done entirely by laborers at a cost of
61 cts. per cu. yd.
On concrete work it is also advisable to keep the cost of forms per
thousand feet board measure, so as to have such data for estimating on
new work. The cost per M. ft. on this job was:
Lumber $17.50
Nails .30
Labor, carpenters 7.65
Laborers 3.85
Tearing down 3.80
------
$33.10
The concrete was mixed by hand, water being carried in buckets from the
creek. Ten to twelve men were worked in the gang under a foreman, and
the concrete was wheeled from the mixing board to the forms in
wheelbarrows. The mixture was made wet enough to run. The cost per cubic
yard for the girders in detail was as follows:
Foreman $0.41
Preparing for mixing 0.14
Cleaning out forms 0.07
Handling materials 0.30
Handling and placing steel 0.40
Mixing and placing 0.87
Ramming 0.45
-----
$2.64
The cost of labor for the floor was:
Foreman $0.28
Preparing for mixing 0.08
Cleaning out forms 0.05
Handling materials 0.14
Handling and placing steel 0.08
Mixing and placing 0.87
Ramming 0.36
-----
$1.86
This gives a total cost per cubic yard for the concrete in the girders
in the completed bridge as follows:
Materials $ 7.01
Erecting forms 4.73
Tearing down forms 0.61
Labor 2.57
General expense 1.60
------
$16.52
The cost per cubic yard for the floor was:
Materials $ 6.13
Erecting forms 4.73
Tearing down forms 0.61
Labor 1.86
General expense 1.60
------
$14.93
Included with this is an item for general expense, being expenses of the
contractor in bidding on the work, car fare, and other items of expense
in looking after the contract.
It will be noticed that a record is here given of three different
mixtures and that the labor cost of mixing and placing increases with
the richness of the mixture. This is because it takes a greater number
of batches to the cubic yard. Record has also been given of cost of
preparing the mixing board and other work necessary to start and clean
up each day; also when stock piles could not be arranged close to the
mixing board, of the cost of handling the materials. These items, it
will be noticed, are large enough to be considered in estimating on new
work. The cost of sweeping and cleaning out the forms has also been
listed, as this work is extremely important.
The cost of the reinforcing steel is given in with the materials, but
the labor of handling it and placing it in the forms is listed under
labor. This naturally varies with the amount of steel needed, and with
the Kahn bar it will vary from 10 cts. to 75 cts. per cubic yard, as the
prongs of the bar must be bent into proper position and at times
straightened, when bent in shipment. This cost seems large, but it is
done with the ordinary labor, while with round rods a large amount of
blacksmith work has to be done and a smith and his helper frequently
must place them. The patent bars are all lettered and numbered as
structural steel is, and can be placed under the direction of the
foreman.
One striking lesson can be learned from the forming. It will be noticed
that the cost for common labor for handling and helping to erect the
forms was much larger in Example I than in Example II, although the
bridge was higher in the latter instance. This was caused by the heavy
timber that was used, and equaled an extra cost nearly 50 per cent. of
the price of new lumber. It certainly speaks volumes against the use of
unnecessarily heavy timber for concrete forms.
In bridge work the height of the floor above the stream to some extent
governs the cost of the forms. This is made so by the extra lumber
needed as props or falsework to support the forming, and also by the
fact that men at some height above the ground do not work as quickly or
as readily as they do nearer the ground. For high and long spans a
derrick is sometimes needed for the work of placing the centering.
On these jobs the concrete was made so wet that with the proper tamping
and cutting of the concrete in the forms the surfaces were so smooth
that no plastering was needed.
~MOLDING SLABS FOR GIRDER BRIDGES.~--The bridges carry railway tracks
across intersecting streets; the slabs rest on two abutments and three
rows of columns so that there are two 24¼-ft. spans over the street
roadway and one 10¾-ft. span over each sidewalk. The larger slabs were
24 ft. 3 ins. long, 33 ins. thick and 7 ft. wide; each contained 16¾
cu. yds. of concrete and weighed 36¾ tons. The smaller slabs were 10 ft.
9 ins. long, 17 ins. thick and 7 ft. wide; each contained 3.65 cu. yds.
of concrete and weighed 7.8 tons. The weights were found by actual
weighing. They make the weight of the reinforced slab between 160 and
162 lbs. per cu. ft. The concrete was generally 1 part cement and 4
parts pit gravel. The reinforcement consisted of corrugated bars. The
method of molding was as follows:
[Illustration: Fig. 155.--Arrangement of Tracks and Forms for Molding
Slabs for Girder Bridge.]
[Illustration: Fig. 156.--Form for Molding Slabs for Girder Bridge.]
A cinder fill yard was leveled off and tamped, then the forms were set
up on both sides of two lines of railway track arranged as shown by Fig.
Reading Tips
Use arrow keys to navigate
Press 'N' for next chapter
Press 'P' for previous chapter