Concrete Construction: Methods and Costs by Gillette and Hill
part 1/8 to ½-in. stone or screenings. The sand was one-half river sand
3235 words | Chapter 51
and one-half crusher sand. The following shows the amounts by weight of
the several materials for each of the several classes of concrete per
cubic yard:
-------------Stone----------
Class. Excess Mortar. 1¼-2. ½-1¼. 1/8-½. Sand. Cement.
A 7.5% 1,500 661½ 333¼ 804 434
B 12.5 1,433-1/3 637 318 858½ 463
C 12.5 1,434 637 318½ 859 474
D 15 1,402 623 312 884 484
[Illustration: Fig. 37.--Apparatus Used for Weighing Concrete Materials
at Barossa Dam.]
The average composition of the concrete was 1-1½-3½. Its cost per cubic
yard in place including rubble was 38s 9d per cu. yd. or about $9.30. In
proportioning the mixture on the work use was made of the device shown
by Fig. 37 to weigh the aggregate. The measuring car is pushed back
under the stone hopper chute until the wheels drop into shallow notches
in the balanced track rails; stone is then admitted until the lead
weight begins to rise, when the car is pushed forward and dumps
automatically as indicated.
~Other Rubble Concrete Dams.~--Rubble concrete containing from 55 to 60
per cent. rubble was used in constructing the Boonton Dam at Boonton, N.
J. The stones used measured from 1 to 2½ cu. yds. each; the concrete was
made so wet that when the stones were dropped into it, it flowed into
every crevice. The materials were all delivered on cars, from which they
were delivered to the dam by derricks provided with bull-wheels. On the
dam there were 4 laborers and 1 mason to each derrick, and this gang
dumped the concrete and joggled the rubble stones into it. Records of
125 cu. yds. per 10 hours, with one derrick, were made. With 35
derricks, 20 of which were laying masonry and 15 either passing
materials or being moved, as much as 21,000 cu. yds. of masonry were
laid in one month. The amount of cement per cubic yard of masonry is
variously stated to have been 0.6 to 0.75 bbl. The stone was granite.
The Spier Falls Dam on the upper Hudson River was built of rubble
concrete containing about 33 per cent. rubble stone. The concrete was a
1-2½-5 mixture, and the engineer states that about 1 bbl. of cement was
used per cubic yard of rubble concrete. This high percentage of cement
may be accounted for by the fact that there was a considerable amount of
rubble masonry in cement mortar included in the total. The stones and
concrete were delivered along the dam by cableways and stiff-leg
derricks set on the downstream sloping face of the dam delivered them
from the cableways into place. There were two laborers to each mason
employed in placing the materials, wages being 15 and 35 cts. per hour,
respectively. The labor cost of placing the materials was 60 cts. per
cubic yard of masonry. The stone was granite.
Granite rubble laid in layers on beds of concrete and filled between
with concrete was used in constructing the Hemet Dam in California. The
concrete was a 1-3-6 mixture, and was thoroughly tamped under and
between the stones. For face work the stones were roughly scabbled to
shape and laid in mortar. The stone was taken from the quarry 400 ft.
away and delivered directly on the dam by cableways; here two derricks
handled the stone into place, the dam being only 246 ft. arc length on
top, though it was 122½ ft. high. The cableways would take a 10-ton
load; stones could be taken from the quarry, hoisted 150 ft. and
delivered to the work in 40 to 60 seconds. Common labor at $1.75 per day
was used for all masonry except facing, where masons at $3.50 were
employed. Cement cost delivered $5 per barrel, of which from $1 to $1.50
per barrel was the cost of hauling 23 miles by team over roads having 18
per cent. grades in places. Sand was taken from the stream bed and
delivered to the work by bucket conveyor. "Under favorable conditions
some of the masonry was put in for as low as $4 per cu. yd." There were
31,100 cu. yds. of masonry in the dam, which required 20,000 bbls. of
cement, or 0.64 bbl. per cubic yard.
The following novel method of making rubble concrete was employed in
enlarging two old dams and in constructing two new dams for a small
water-works. The available time was short, the amount of work was too
small and too scattered to justify the installation of a stone crusher,
and suitable gravel was not at hand. Sufficient small boulders in old
walls, and borrow pits and on surface of fields were available, and were
used with thin Portland cement mortar. One part of Alpha or Lehigh
cement and three parts sand were mixed dry at first and then wet with
just enough water to make the resulting mortar flow by gravity. This
mortar was shoveled into the forms continuously by one set of men while
other men were throwing into the mortar in the forms the boulders which
were cleaned and broken so as not to be more than 7 ins. long. In
general the performance was continuous. Three mortar beds were placed
parallel with, and against, one side of the forms, with spaces of about
4 ft. between the ends of the beds. The boulders were dumped on the
opposite side of the forms. Two men shoveled in all the mortar and did
nothing else. While they were emptying one bed the mortar was being
mixed in the preceding bed by two other men and the materials placed in
the third bed by still others. Another gang was continually throwing in
the boulders and small stones and still another was breaking stone. One
man should keep the mortar well stirred while the bed is being emptied.
About 20 men were necessary to do all parts of the work. The forms were
of 2-in. planed plank tongued and grooved. Especial pains were taken to
make the forms tight, and all leaks that appeared were quickly stopped
with dry cement. Some pains were taken to prevent a flat side of large
stones from coming in direct contact with the forms, but round boulders
and small stones needed no care to prevent their showing in the finished
work.
[Illustration: Fig. 38.--Bridge Abutment of Rubble Concrete.]
In conclusion it is interesting to note, perhaps, the earliest use of
rubble concrete for dam construction in this country in constructing the
Boyd's Corner Dam on the Croton River near New York. This dam was begun
in 1867 and for a time rubble concrete was used, but was finally
discontinued, due to the impression that it might not be watertight. The
specifications called for dry concrete to be thoroughly rammed in
between the rubble stones, and to give room for this ramming the
contractor was not permitted to lay any two stones closer together than
12 ins. As a result not more than 33 per cent. of the concrete was
rubble.
~Abutment for Railway Bridge.~--Figure 38 shows a bridge abutment built of
rubble concrete at a cost of about $4.50 per cu. yd. The concrete was a
1-2½-4½ mixture laid in 4-in. layers. On each layer were laid large
rubble stones bedded flat and spaced to give 6-in. vertical joints; the
vertical joints were filled with concrete by ramming and then another
layer of concrete placed and so on. A force of 28 men and a foreman
averaged 40 cu. yds. of rubble concrete per day. The following is the
itemized cost per cubic yard, not including forms, for 278 cu. yds:
Item. Per Cu. Yd.
0.82 bbls. cement, at $2.60 $2.14
0.22 cu. yd. sand, at $1.00 0.22
0.52 cu. yd. broken stone, at $0.94 0.49
0.38 cu. yd. rubble stone, at $0.63 0.24
Water 0.07
Labor, at 15 cts. per hour 1.19
Foreman 0.09
-------
Total $4.44
~Some English Data on Rubble Concrete.~--Railway work, under Mr. John
Strain, in Scotland and Spain, involved the building of abutments, piers
and arches of rubble concrete. The concrete was made of 1 part cement to
5 parts of ballast, the ballast consisting of broken stone or slag and
sand mixed in proportions determined by experiment. The materials were
mixed by turning with shovels 4 times dry, then 4 times more during the
addition of water through a rose nozzle. A bed of concrete 6 ins. thick
was first laid, and on this a layer of rubble stones, no two stones
being nearer together than 3 ins., nor nearer the forms than 3 ins. The
stones were rammed and probed around with a trowel to leave no spaces.
Over each layer of rubble, concrete was spread to a depth of 6 ins. The
forms or molds for piers for a viaduct were simply large open boxes, the
four sides of which could be taken apart. The depth of the boxes was
uniform, and they were numbered from the top down, so, that, knowing the
height of a given pier, the proper box for the base could be selected.
As each box was filled, the next one smaller in size was swung into
place with a derrick. The following bridge piers for the Tharsis &
Calanas Railway were built:
Length Height No. Cu. Yds. Weeks
of of of in to
Name. Bridge. Piers. Spans. Piers. Build.
Ft. Ft.
Tamujoso River 435 28 12 1,737 14½
Oraque 423 31 11 1,590 15
Cascabelero 480 30 to 80 10 2,680 21
No. 16 294 28 to 50 7 1,046 16½
Tiesa 165 16 to 23 8 420 4
It is stated that the construction of some of these piers in ordinary
masonry would have taken four times as long. The rock available for
rubble did not yield large blocks, consequently the percentage of pure
concrete in the piers was large, averaging 70 per cent. In one case,
where the stones were smaller than usual, the percentage of concrete was
76½ per cent. In other work the percentage has been as low as 55 per
cent., and in still other work where a rubble face work was used the
percentage of concrete has been 40 per cent.
In these piers the average quantities of materials per cubic yard of
rubble concrete were:
448 lbs. (0.178 cu. yd.) cement.
0.36 cu. yd. sand.
0.68 cu. yd. broken stone (measured loose in piles).
0.30 cu. yd. rubble (measured solid).
Several railway bridge piers and abutments in Scotland are cited. In one
of these, large rubble stones of irregular size and weighing 2 tons each
were set inside the forms, 3 ins. away from the plank and 3 ins. from
one another. The gang to each derrick was: 1 derrick man and 1 boy, 1
mason and 10 laborers, and about one-quarter of the time of 1 carpenter
and his helper raising the forms. For bridges of 400 cu. yds., the
progress was 12 to 15 cu. yds. a day. The forms were left in place 10
days.
To chip off a few inches from the face of a concrete abutment that was
too far out, required the work of 1 quarryman 5 days per cu. yd. of
solid concrete chipped off.
Concrete was used for a skew arch over the River Dochart, on the Killin
Railway, Scotland. There were 5 arches, each of 30 ft. span on the
square or 42 ft. on the skew, the skew being 45°. The piers were of
rubble concrete. The concrete in the arch was wheeled 300 ft. on a
trestle, and dumped onto the centers. It was rammed in 6-in. layers,
which were laid corresponding to the courses of arch stones. As the
layers approached the crown of the arch, some difficulty was experienced
in keeping the surfaces perpendicular. Each arch was completed in a day.
In a paper by John W. Steven, in Proc. Inst. C. E., the following is
given:
Rubble Per Cent.
Concrete Concrete of Rubble
Per Per in Rubble
Cu. Yd. Cu. Yd. Concrete.
Ardrossan Harbor $6.00 $5.00 20.0
Irvine Branch 7.00 3.68 63.6
Calanas & Tharsis Ry 7.08 3.43 30.3
Mr. Martin Murphy describes some bridge foundations in Nova Scotia.
Rubble concrete was used in some of the piers. The rubble concrete
consisted of 1 part cement, 2 parts sand, 1 part clean gravel, and 5
parts of large stones weighing 20 lbs. each and upwards. The sand,
cement and gravel were turned three times dry and three times wet, and
put into the forms. The rubble stones were bedded in the concrete by
hand, being set on end, 2 or 3 ins. apart. No rubble stones were placed
within 6 ins. of the forms, thus leaving a face of plain concrete; and
the rubble stones were not carried higher than 18 ins. below the top of
the pier. One cubic yard of this rubble concrete required 0.8 to 0.9
bbl. of cement.
~ASPHALT CONCRETE.~--Asphalt or tar concrete in which steam cinders or
broken stone or gravel and sand are mixed with asphaltum or tar instead
of cement paste are used to some extent in lining reservoirs,
constructing mill floors, etc. Such mixtures differ in degree only from
the mixtures used for asphalt street paving, for discussion of which the
various books on paving and asphalts should be consulted. The two
examples of asphalt concrete work given here are fairly representative
of the mixtures and methods employed for concrete work as distinguished
from asphalt work.
~Slope Paving for Earth Dam.~--Mr. Robert B. Stanton describes a small log
dam faced upstream with earth, upon which was laid an asphalt concrete
lining to make it water tight. The stone was broken to 2-in. pieces,
all the fines being left in and sufficient fine material added to fill
the voids. The stone was heated and mixed in pans or kettles from a
street paving outfit; and the asphaltum paste, composed of 4 parts
California refined asphaltum and 1 part crude petroleum, was boiled in
another kettle. The boiling hot paste was poured with ladles over the
hot stone, and the whole mixed over the fire with shovels and hoes. The
asphalt concrete was taken away in hot iron wheelbarrows, placed in a
4-in. layer rammed and ironed with hot irons. The concrete was laid in
strips 4 to 6 ft. wide, the edges being coated with hot paste. After the
whole reservoir was lined, it was painted with the asphalt paste, boiled
much longer, until when cold it was hard and stone was broken to 2-in.
pieces, all the fines being left in and sufficient fine material added
to fill the voids. The stone was heated and mixed in pans or kettles
from a street paving outfit; and the asphaltum paste, composed of 4
parts California refined asphaltum and 1 part crude petroleum, was
boiled in another kettle. The boiling hot paste was poured with ladles
over the hot stone, and the whole mixed over the fire with shovels and
hoes. The asphalt concrete was taken away in hot iron wheelbarrows,
placed in a 4-in. layer rammed and ironed with hot irons. The concrete
was laid in strips 4 to 6 ft. wide, the edges being coated with hot
paste. After the whole reservoir was lined, it was painted with the
asphalt paste, boiled much longer, until when cold it was hard and
brittle, breaking like glass under the hammer. This paste was put on
very hot and ironed down. It should not be more than {1/8}-in. thick or
it will "creep" on slopes of 1½ to 1. After two hot summers and one cold
winter there was not a single crack anywhere in the lining. A mixture of
sand and asphalt will creep on slopes of 1½ to 1, but asphalt concrete
will not. With asphalt at $20 a ton, and labor at $2 a day, the cost was
15 cts. a sq. ft. for 4-in. asphalt concrete. On a high slope Mr.
Stanton recommends making slight berms every 6 ft. to support the
concrete and prevent creeping. Asphalt concrete resists the wear of wind
and water that cuts away granite and iron.
~Base for Mill Floor.~--In constructing 17,784 sq. ft. of tar concrete
base for a mill floor, Mr. C. H. Chadsey used a sand, broken stone and
tar mixture mixed in a mechanical mixer. The apparatus used and the mode
of procedure followed were as follows:
Two parallel 8-in. brick walls 26 ft. long were built 4 ft. apart and 2½
ft. high to form a furnace. On these walls at one end was set a 4×6×2
ft. steel plate tar heating tank. Next to this tank for a space of 4×8
ft. the walls were spanned between with steel plates. This area was used
for heating sand. Another space of 4×8 ft. was covered with 1½ in. steel
rods arranged to form a grid; this space was used for heating the broken
stones. The grid proved especially efficient, as it permitted the hot
air to pass up through the stones, while a small cleaning door at the
ground allowed the screenings which dropped through the grid to be
raked out and added to the mixture. A fire from barrel staves and refuse
wood built under the tank end was sufficient to heat the tar, sand and
stone.
For mixing the materials a Ransome mixer was selected for the reason
that heat could be supplied to the exterior of the drum by building a
wood fire underneath. This fire was maintained to prevent the mixture
from adhering to the mixing blades, and it proved quite effective,
though occasionally they would have to be cleaned with a chisel bar,
particularly when the aggregate was not sufficiently heated before being
admitted to the mixer. A little "dead oil" applied to the discharge
chute and to the shovels, wheelbarrows and other tools effectually
prevented the concrete from adhering to them.
The method of depositing the concrete was practically the same as that
used in laying cement sidewalks. Wood strips attached to stakes driven
into the ground provided templates for gaging the thickness of the base
and for leveling off the surface. The wood covering consisted of a layer
of 2-in. planks, covered by matched hardwood flooring. In placing the
planking, the base was covered with a ¼-in. layer of hot pitch, into
which the planks were pressed immediately, the last plank laid being
toe-nailed to the preceding plank just enough to keep the joint tight.
After a few minutes the planks adhered so firmly to the base that they
could be removed only with difficulty. The hardwood surface was put on
in the usual manner. The prices of materials and wages for the work were
as follows:
Pitch, bulk, per lb. $ 0.0075
Gravel, per cu. yd. 1.50
Spruce sub-floor, per M. ft. B. M. 15.00
Hardwood surface, per M. ft. B. M. 33.00
Laborers, per 10-hour day. 1.50
Foreman, per 10-hour day. 4.00
Carpenters, per 10-hour day. 2.00
At these prices and not including a small administration cost or the
cost of tools and plant, the cost of the floor consisting of 4½ ins. of
concrete, 2 ins. of spruce sub-flooring and 7/8-in. hardwood finish was
as follows per square foot:
Pitch $0.04
Gravel 0.02
Spruce, for sub-floor 0.03
Hardwood for surfacing 0.035
Labor, mixing 0.03
Labor, laying 0.015
Carpenter work 0.025
------
Total per square foot $0.195
Reading Tips
Use arrow keys to navigate
Press 'N' for next chapter
Press 'P' for previous chapter