Concrete Construction: Methods and Costs by Gillette and Hill
CHAPTER V.
3469 words | Chapter 49
METHODS AND COST OF DEPOSITING CONCRETE UNDER WATER AND OF SUBAQUEOUS
GROUTING.
Mixed concrete if emptied loose and allowed to sink through water is
destroyed; the cement paste is washed away and the sand and stone settle
onto the bottom more or less segregated and practically without
cementing value. In fact, if concrete is deposited with the utmost care
in closed buckets and there is any current to speak of a considerable
portion of cement is certain to wash out of the deposited mass. Even in
almost still water some of the cement will rise to the surface and
appear as a sort of milky scum, commonly called _laitance_. Placing
concrete under water, therefore, involves the distinctive task of
providing means to prevent the washing action of the water. It is also
distinguished from work done in air by the fact that it cannot be
compacted by ramming, but the main problem is that of preventing wash
during and after placing.
~DEPOSITING IN CLOSED BUCKETS.~--Special buckets for depositing concrete
under water are made by several manufacturers of concrete buckets. These
buckets vary in detail but are all similar in having doors to close the
concrete away from the water and, generally, in being bottom dumping.
The bucket shown by Fig. 26 was designed by Mr. John F. O'Rourke, and is
built by the Cockburn Barrow & Machine Co., of Jersey City, N. J. This
bucket was used in depositing the concrete for the City Island Bridge
foundations described in Chapter XII and also in a number of other
works. It consists of a nearly cubical shell of steel open at top and
bottom, and having heavy timbers rivetted around the bottom edges. The
open top has two flat flap doors. Two similar doors hinged about midway
of the sides close to form a V-shaped hopper bottom inside the shell and
serve when open, to close the openings in the sides of the shell. In
loading the bucket the bottom doors are drawn inward and upward by the
chains and held by a temporary key. The loaded bucket is then lifted by
the bail and the key removed, since when suspended the pull on the bail
holds the chains taut and the doors closed. As soon as the bucket rests
on the bottom the pull of the concrete on the doors slides the bail down
and the doors swing downward and back discharging the concrete. The
timbers around the bottom edges keep the bucket from sinking into the
deposited concrete, and the doors and shell exclude all water from the
batch until it is finally in place.
[Illustration: Fig. 26.--O'Rourke Bucket fur Depositing Concrete Under
Water.]
The subaqueous concrete bucket shown by Figs. 27 and 28 is made by the
Cyclopean Iron Works Co., Jersey City, N. J. Fig. 27 shows the bucket
suspended full ready for lowering; the cover is closed and latched and
the bail is held vertical by the tag line catch A. Other points to be
noted are the eccentric pivoting of the bail, the latch unlocking lever
and roller B and C, and the stop D. In the position shown the
bucket is lowered through the water and when at the proper depth just
above bottom the tag line is given a sharp pull, uncatching the bail.
The body of the bucket turns bottom side up, revolving on the bail
pivots, and just as the revolution is completed the bail engages the
roller C on the latch unlocking lever and swings the lever enough to
unlatch the top and allow it to swing down as shown by Fig. 28 and
release the concrete. The stop D keeps the body of the bucket from
swinging beyond the vertical in dumping.
[Illustration: Fig. 27.--Cyclopean Bucket for Depositing Concrete Under
Water (Closed Position).]
[Illustration: Fig. 28.--Cyclopean Bucket for Depositing Concrete Under
Water (Open Position).]
Figures 29 and 30 show the subaqueous concrete bucket made by the G. L.
Stuebner Iron Works, Long Island City, N. Y., essentially the same
bucket, omitting the cover and with a peaked bail, is used for work in
air. For subaqueous work the safety hooks A are lifted from the angles
B and wired to the bail in the position shown by the dotted lines, and
a tag line is attached to the handle bar C. The bucket being filled
and the cover placed is lowered through the water to the bottom and then
discharged by a pull on the tag line.
~DEPOSITING IN BAGS.~--Two methods of depositing concrete in bags are
available to the engineer; one method is to employ a bag of heavy tight
woven material, from which the concrete is emptied at the bottom, the
bag serving like the buckets previously described simply as means of
conveyance, and the other method is to use bags of paper or loose woven
gunnysack which are left in the work, the idea being that the paper will
soften or the cement will ooze out through the openings in the cloth
sufficiently to bond the separate bagfuls into a practically solid mass.
[Illustration: Fig. 29.--Stuebner Bucket for Depositing Concrete Under
Water (Closed Position).]
[Illustration: Fig. 30.--Stuebner Bucket for Depositing Concrete Under
Water (Open Position).]
[Illustration: Fig. 31.--Bag for Depositing Concrete Under Water.]
[Illustration: Fig. 32.--Form for Molding Footing for Block Concrete
Breakwater.]
The bag shown by Fig. 31 was used to deposit concrete for leveling up a
rough rock bottom and so provide a footing for a concrete block pier
constructed in 1902 at Peterhead, N. B., by Mr. William Shield, M. Inst.
C. E. Careful longitudinal profiles were taken of the rock bottom one at
each edge of the footing. Side forms were then made in 20-ft. sections
as shown by Fig. 32; the lagging boards being cut to fit the determined
profile and the top of the longitudinal piece being flush with the top
of the proposed footing. The concrete was filled in between the side
forms and leveled off by the T-rail straight-edge. In placing the side
forms the longitudinal pieces were placed by divers who were given the
proper elevations by level rods having 10 to 15-ft. extension pieces to
raise the targets above the water surface. When leveled the side pieces
were anchor-bolted as shown to the rock, the anchor-bolts being wedged
into the holes to permit future removal. The concrete was then lowered
in the bag shown by Fig. 31, the divers assisting in guiding the bag to
position. The mouth of the bag being tied by one turn of a line having
loops through which a wooden key is slipped to hold the line tight, a
sharp tug on the tripping rope loosens the key and empties the bag. The
bags used on this work had a capacity of 2¼ cu. ft. To permit the
removal of the side forms after the concrete had hardened, a strip of
jute sacking was spread against the lagging boards with a flap
extending 15 to 18 ins. under the concrete. The forms were removed by
divers who loosened the anchor bolt wedges.
In placing small amounts of concrete for bridge foundations in Nova
Scotia, bags, made of rough brown paper were used to hold the concrete.
Each bag held about 1 cu. ft. The bags were made up quickly and dropped
into the water one after the other so that the following one was
deposited before the cement escaped from the former one. The paper was
immediately destroyed by submersion and concrete remained. The bags cost
$1.35 per hundred or 35 cts. per cu. yd. of concrete. Concrete was thus
deposited in 18 ft. of water without a diver.
[Illustration: Fig. 33.--Steel Tremie for Depositing Concrete Under
Water.]
~DEPOSITING THROUGH A TREMIE.~--A tremie consists of a tube of wood or,
better, of sheet metal, which reaches from above the surface to the
bottom of the water; it is operated by filling the tube with concrete
and keeping it full by successive additions while allowing the concrete
to flow out gradually at the bottom by raising the tube slightly to
provide the necessary opening. A good example of a sheet steel tremie is
shown by Fig. 33. This tremie was used by Mr. Wm. H. Ward in
constructing the Harvard Bridge foundations and numerous other
subaqueous structures of concrete. In these works the tube was suspended
from a derrick. Wheelbarrows filled the tube and hopper with concrete
and kept them full; the derrick raised the tube a few inches and swung
it gently so as to move it slowly over the area to be filled. Care being
taken to keep the tube at one height, the concrete was readily deposited
in even layers. Concrete thus deposited in 18 ft. of water was found to
be level and solid on pumping the pit dry.
[Illustration: Fig. 34.--Tremie and Traveler Used at Charlestown, Mass.,
Bridge.]
Another method of handling a tremie was employed in constructing the
foundations for the Charlestown Bridge at Boston, Mass. Foundation piles
were driven and sawed off under water. A frame was built above water and
supported by a curbing attached to certain piles in the outer rows of
the foundation reserved for this purpose. In this frame the vertical
members were Wakefield sheet-piling plank, spaced 6 to 10 ft. apart, and
connected by three lines of double waling bolted to the verticals at
three different heights. This frame was lowered to the bottom so as to
enclose the bearing piles. The posts or verticals were then driven, one
by one, into the bottom, the frame being flexible enough to permit this.
The spaces between the posts or verticals were then filled by
sheet-piling and the frame was bolted to the curbing piles. This curbing
afterward supported the traveler used in laying the concrete. Thus a
coffer dam was formed to receive the concrete as shown in Fig. 34. The
1-2-5 concrete was deposited up to within 5½ ft. of the mean low water
level, the last foot being laid after water was pumped out. The tremie
used to deposit the concrete was a tube 14 ins. in diameter at the
bottom and 11 ins. at the neck, with a hopper at the top. It was made in
removable sections, with outside flanges, and was suspended by a
differential hoist from a truck moving laterally on a traveler, Fig. 34.
The foot of the chute rested on the bottom until filled with concrete;
then the chute was slowly raised and the concrete allowed to run but
into a conical heap, more concrete being dumped into the hopper. As the
truck moved across the traveler a ridge of concrete was made; then the
traveler was moved forward and another parallel ridge was made. The best
results were obtained when the layers were 2½ ft. thick, but layers up
to 6 ft. thick were laid. If the layer was too thick, or uneven, or if
the chute was moved or raised too quickly, the charge in the tube was
"lost." This was objectionable because the charging of the chute anew
resulted in "washing" the cement more or less out of the concrete until
the chute was again filled. To reduce this objection the contractor was
directed to dump some neat cement into the tube before filling with
concrete. A canvass piston was devised which could be pushed ahead of
the concrete when filling the chute. It consisted of two truncated cones
of canvass, one flaring downward to force the water ahead, and the other
flaring upward to hold the concrete. The canvass was stiffened and held
against the sides of the chute by longitudinal ribs of spring steel
wire; the waist was filled by a thick block of wood to which all the
springs were attached; and to this block were connected additional steel
guides to prevent overturning and a rope to regulate the descent. Very
little water forced its way past this piston and it was a success, but
as the cost was considerable and a piston was lost each time, its use
was abandoned as the evil to be avoided did not justify the outlay.
The chute worked best when the concrete was mixed not quite wet enough
to be plastic. If mixed too wet the charge was liable to be "lost," and
if dry it would choke the chute. An excess of gravel permitted water to
ascend in the tube; and an excess of sand tended to check the flow of
concrete.
In constructing the piers for a masonry arch bridge in France in 1888
much the same method was followed, except that a wooden tremie 16 ins.
square made in detachable sections was used. This tremie had a hopper
top and was also provided with a removable cap or cover for the bottom
end, the latter device being intended to keep the water out of the tube
and prevent "washing" the first charge of concrete. The piers were
constructed by first driving piles and sawing them off several feet
above the bottom but below water level, and then filling them nearly to
their tops with broken stone. An open box caisson was then sunk onto the
stone and embracing the pile tops and then filled around the outside
with more broken stone. The caisson was then filled with concrete
through the tremie which was handled by a traveling crane. The crane was
mounted and traveled transversely of the pier on a platform which in
turn moved along tracks laid lengthwise of the caisson. The tube was
gradually filled with concrete and lowered, the detachable bottom of the
tube was then removed, allowing the concrete to run out. The tube was
first moved across the caisson and then downstream and back across the
caisson, and this operation repeated until a 16-in. layer was completed.
The tube was then raised 16 ins. and the operations repeated to form
another layer. There was almost no _laitance_. From 90 to 100 cu. yds.
were deposited daily.
Still another example of tremie work is furnished by the task of
depositing a large mass of concrete under water in the construction of
the Nussdorf Lock at Vienna. This lock has a total width of 92 ft. over
all, and is 49.2 ft. clear inside. The excavation, which was carried to
a depth of 26.24 ft. below water level, was made full width, between
sheet piling, and the bottom was filled in with rammed sand and gravel,
forming a kind of invert with its upper surface horizontal in the middle
and sloping upwards a trifle at both sides. A mass of concrete having a
total thickness of 13.12 ft. was built on this foundation in the center
where the upper surfaces were 13.12 ft. below the water level. Concrete
walls were carried up at the sides of the lock to a height of 3.28 ft.;
these walls were 8.2 ft. thick. The methods used in placing the concrete
were as follows: Three longitudinal rows of piles were driven on each
side of the axis of the lock, these piles supporting a 6-rail track
about 7 ft. above the water level. Three carriages spanning the full
width of the lock transversely moved on this track. Each carriage had
three trolleys, one in each of the main panels of the transverse pile
bends. These trolleys each carried a vertical telescopic tube, by means
of which the concrete was deposited at the bottom of the lock. These
tubes or chutes were of different lengths in the three carriages; the
first ones deposited the concrete up to a level of 23 ft. below the
surface; the next set deposited the concrete between that level and 19.7
ft., and the last set completed the subaqueous work up to the final
height of 16.4 ft. below the surface. The tops of the tubes were level
with a transverse track extending the full length of the carriage. The
ends of these tracks just cleared the outside rows of piles, which, on
one side of the lock, supported a distribution track parallel to the
axis of the lock. Dump cars running on this distribution track delivered
the concrete to smaller dump cars on the carriage tracks, and in turn
these smaller cars dumped into either of these chutes on each carriage.
The carriages were moved from end to end of the lock, the whole area of
the lock coming under the nine chutes, inasmuch as each chute moved
one-third the length of the carriage. The concrete was deposited in
three horizontal layers 3.28 ft. thick, the layers being built in
comparatively narrow banks, so that the different layers would key
together and form a corrugated mass. The chutes were shortened as the
concrete was deposited, three layers being placed successively. The main
body of the bottom and the side walls were built by this method, and
then the water was pumped out and a 2.3 ft. layer of concrete rammed
over the bottom and completed with a finished surface 9 ft. thick.
~GROUTING SUBMERGED STONE.~--Masses of gravel, broken or rubble stone
deposited under water may be cemented into virtually a solid concrete by
charging the interstices with grout forced through pipes from the
surface. Mr. H. F. White gives the following records of grouting
submerged gravel:
In experiment No. 1 a reservoir 10 ft. square was filled to a depth of
18 ins. with clean gravel ballast (1½ to 2-in. size) submerged in water.
A 2-in. gas pipe rested on the gravel and was surmounted with a funnel.
A 1:1 Portland grout was poured in. After 21 days set the water was
drawn off, and it was found that the grout had permeated the ballast
for a space of 8 ft. square at the bottom and 6 ft. square at the top,
leaving a small pile of pure cement mortar 6 ins. high about the base of
the pipe; 16 cu. ft. of cement and 16 cu. ft. of sand concreted 100 cu.
yds. of ballast. In experiment No. 2, under the same conditions, a grout
made of 1 part lime, 1 part surki (puzzulana or trass) and 1 part sand,
was found to have spread over the entire bottom, 10 ft. square, rising 5
ins. on the sides, and making the concreted mass about 3½ ft. square at
the top; 25 cu. ft. of the dry materials concreted 100 cu. ft. of
ballast. In experiment No. 3 the ballast was 2½ ft. deep. A grout (using
8 cu. ft. of each ingredient) made as in experiment No. 2 covered the
bottom, rose 14 ins. on the sides and made a top surface 4½ ft. square;
32 cu. ft. of the dry materials grouted 100 cu. ft. of ballast. In
experiment No. 4 the ballast was of bats and pieces 3 or 4 ins. in size
laid 7 ft. deep. A grout made as in experiment No. 2 (using 88 cu. ft.
of each ingredient) concreted the whole mass to a depth of 6 ft. up the
sides, and 2½ ft. square at the pipe on the surface of the ballast. Mr.
White says that a grout containing more than 1 part of sand to 1 of
Portland cement will not run freely through a 2-in. pipe, as the sand
settles out and chokes the pipe. Even with 1:1 grout it must be
constantly stirred and a steady flow into the pipe maintained. The
lime-trass grout does not give the same trouble.
Mr. W. R. Knipple describes the work of grouting rubble stone and gravel
for the base of the Hermitage Breakwater. This breakwater is 525 ft.
long, 50 ft. wide at base and 42 ft. wide at top, and 68 ft. high, was
built on the island of Jersey. Where earth (from 0 to 8½ ft. deep)
overlaid the granite rock, it was dredged and the trench filled in with
rubble stones and gravel until a level foundation was secured. Cement
grout was then forced into this filling through pipe placed 8 to 10 ft.
apart. The grouting was done in sections 12½ ft. long, from 7 to 10 days
being taken to complete each. Upon this foundation concrete blocks,
4×4×9 to 12 ft., were laid in courses inclined at an angle of 68°. The
first four courses were laid by divers, the blocks being stacked dry two
courses high at a time. The joints below water were calked by divers and
above water by masons, and a section was then grouted. When two courses
had been laid and grouted, two more courses were laid and grouted in
turn, and so on. In places, grouting was done in 50 ft. of water. The
grout should be a thick paste; a 30-ft. column of grout will balance a
60-ft. column of water.
Reading Tips
Use arrow keys to navigate
Press 'N' for next chapter
Press 'P' for previous chapter