Waterways and Water Transport in Different Countries by J. Stephen Jeans
5. Freedom from duties on its imports.
7597 words | Chapter 116
It was provided that the canal and works were to be finished, save for
unavoidable delays, within six years. Native labour was to be employed
to the extent of four-fifths of the whole, a special convention
settling the terms on which the Government supplied or authorised such
labour. The tolls were fixed at 10 frs. per “ton of capacity” (an
expression which gave rise to difficulties subsequently), and 10 frs.
for each passenger.
A contract was made with M. Hardon for the execution of the works,
under which the company were to receive 60 per cent. of the prices
fixed by the original estimates of the International Commission. The
drawing up of the plans, the general superintendence, and the supply
of the machinery and stores, were, however, to be left in the hands of
the company. This agreement was subsequently cancelled, and the company
took the works under its own control, making contracts with four
different firms, who undertook to complete the principal undertakings
for a total sum of 4,588,800_l._[148] With these arrangements, the canal
was fairly launched. From 1861 till 1869 the whole line of the canal
was the busiest centre of industrial activity in Europe. The total
amount of excavation required was 107 millions of cubic metres. This
is a larger amount of digging than has been accomplished in the case
of any other work on record.[149] The operations were required to be
carried on at the same time with the fresh-water canal from Nefiche to
Suez, and with the maritime canal from Suez to Port Said, so that two
distinct undertakings were concurrently being constructed. Some details
as to the annual progress of the works may here be suitably introduced.
In 1861, the works were chiefly confined to digging wells along the
line of the maritime canal, to erecting sheds for 10,000 labourers, and
providing dock basins, water condensers, forges and workshops, steam
saw-mills, and opening a water supply by a canal which should join the
Nile to Lake Timsah.
In 1862, the eastern mole at Port Said was begun, together with a
landing stage 70 yards by 22, in 16 feet of water, and an arsenal dock
160 yards by 135 and 5 feet depth. Seven Arab villages were built, and
north of Lake Timsah, a sea-water cutting was continued from Kantara
to El Ferdane. A large dredging plant ordered from various makers in
England and France was delivered.
In 1863, four dredgers and cranes were got to work at Port Said, and
south of Lake Timsah twenty-one dredgers were at work, and three others
were nearly ready. Provision was made for adding twenty more dredgers,
each estimated to be capable of raising 1,050,000 cubic feet per month.
The fresh-water canal from Nefiche to Suez was begun, and 24 miles
were finished. This canal was 64 feet at the water-line, 26 feet at
the bottom, and had 6 feet draught of water. The excavations required
were about 50 millions of cubic feet. On the north of Lake Timsah,
18,000 men were at work, digging a trench 50 feet by 4 to 6 feet
deep, connecting the Mediterranean and Lake Timsah, and 153,600,000
cubic feet of excavation was done at 0·68 fr. per cubic metre, being
within the original estimate, despite the heavy labour of carrying the
earth up an incline of 70 feet. From Lake Timsah to Toussoum Plateau
on the south, the canal was made 190 feet wide and 6 feet below the
Mediterranean level, involving 21,200,000 cubic feet of excavation.
In 1864, 20 new dredgers, with barges and accessories, were fitted
up, 43,000,000 cubic feet of excavation was done, from Port Said to
El Ferdane, and 7,600,000 cubic feet between Timsah and Serapeum, as
well as 4,500,000 cubic feet of gypsous stone along Lake Ballah. A
large area of land was also reclaimed, in order to provide for new
works, quays were extended, and the canal Cheikh Carponti, connecting
Port Said with the lake and Damietta, was completed. The fresh-water
canal was also completed to the sea, over 55 miles, having occupied
thirteen months, and involved 118,000,000 cubic feet of excavation.
Corvées, or native forced labour, were abolished, and 7954 European
labourers, with 10,806 others, were set to work.
In 1865 the general works of the Maritime Canal were extended.
In 1866 Messrs. Borel and Levalley got 32 trough dredgers at work along
35 miles of the canal, and the canal from Port Said to Timsah was
widened to 325 feet, thus allowing of the formation of strands for the
protection of banks from passing vessels, and economising the stone
embankments. The Viceroy set 80,000 men to work at the canal from
Cairo to Wady, so as to allow of the passage of the Nile waters at all
seasons.
In 1867, 353,000,000 cubic feet of dredging was accomplished, and long
trough dredgers were applied to the work between Port Said and Timsah,
which was filled to sea level. The large lake to Chalouf, and the small
lake to Suez, were excavated by hand labour. Of the contract of M.
Couvreux to excavate 146,000,000 cubic feet, 122,500,000 cubic feet had
been completed on 1st June.
In 1868 excellent progress was made. Messrs. Borel and Levalley had
dredged at Port Said 123,000,000 out of their total quantity of
165,000,000 cubic feet. On the 15th April 1,200,000,000 cubic feet
still remained to be excavated in the Maritime Canal. Between Port
Said and Timsah, 5¼ miles had been done with 156,000,000 cubic feet of
excavation, and at El Ferdane, 3¾ miles had been done with 34,000,000,
Couvreux thereby finishing six months in advance of the contract time.
The monthly work at this time was 74,500,000 cubic feet, accomplished
with 8 elevator dredgers, 30 dredgers with barges, 22 long trough
dredgers, 22 inclined planes, and 7500 labourers.
Besides the ordinary work of canalisation along the line of route,
very extensive harbour operations had to be undertaken at Port Said
and Suez. In the former case, two moles were erected, the western 2700
yards long, and the eastern 1950 yards, and requiring 250,000 blocks of
artificial stone, each of 350 cubic feet and weighing 20 tons. A dock
basin, 76 acres in extent had to be provided, and another basin, called
the Basin de Commerce, of 10 acres extent and 37 feet deep. At Suez,
the roadstead had to be dredged, and dykes and embankments constructed,
the latter involving the submergence of 2,300,000 cubic feet of stone.
The Suez breakwater, when finished, had over 1600 yards of stonework.
In 1869, early in the year, the moles at Port Said were completed, and
the maritime canal, from Port Said to the Bitter Lakes Canal, was fully
open. In March the flooding of the Bitter Lakes was commenced, and they
were excavated to the Red Sea, for a distance of 22 miles, by hand, and
for three miles by dredgers. Later on, the canal was fully opened.
The total length of quays at Port Said is over 3 miles. The inner port
has an area of 130 acres, and the outer port an area of over 4000
acres. There are, besides, 120 acres of docks, and 10 acres of channel.
Port Said has now a permanent population of over 17,000, and Suez one
of 11,000, whereas the total population of the Isthmus in 1859 was only
150 inhabitants.
The Suez Canal can boast of having achieved many triumphs. It has
abridged time and space in a way and to an extent that no other
enterprise has ever before done in the history of the world. It has
brought India and Australasia almost within half their former distance
of Europe. It has revolutionised the shipping trade of the world. It
has brought about remarkable changes in the values of Eastern produce.
It has greatly reduced the cost of transport, and it has placed at the
disposal of England, France, and Egypt a source of revenue which in
its steady upward growth may properly be described as an El Dorado.
But, after all, there is one of the phases of this remarkable work
which is entitled to quite as much attention as any of these, although
the world in general hears less about it. The canal gave an enormous
impetus to engineering invention, skill, and enterprise, the effects of
which have since then been felt in a hundred different works undertaken
and carried out for the good of mankind. The appliances with which
the canal was eventually completed were, for the most part, designed
specially for the purpose. Until then, no such machinery was available.
But the opportunity once found, the men were found who could utilise
it. A description of the numerous different descriptions of elevators,
dredgers, inclined planes, engines, and other appliances employed at
Suez would fill a large volume. Compare some of these mighty machines,
with their weight of 500 or 600 tons,[150] and extracting at the rate
of a million and a half cubic feet of earth per month, with the
_Couffins_, or rude Arab baskets, used by the native fellaheen, by whom
the work was begun in 1860![151] The contrast represents the void that
divides barbarism from civilisation.
The effect of the opening of the Suez Canal has been to reduce the
distance between England and the Australian and Indian possessions
of the British Crown by distances varying from 545 to 4393 nautical
miles, the greatest saving having occurred in the case of the voyage
to Bombay. The voyage to India, China, and Australia has been so
much shortened that some of the most important of the ports of those
possessions are now reached in little more than one half the time that
was formerly taken up by the voyage round the Cape.[152]
The total cost of the Suez Canal at the end of 1870 was placed on the
company’s balance-sheet for that year at 16,613,000_l._[153] At the end
of 1886 this amount had swollen, with various items of expenditure
incurred in the interval, to 19,782,000_l._ Of the former amount only
11,653,000_l._ were expended in the work of construction proper.
The financial success of the Suez Canal has exceeded the wildest dreams
of its promoters. The increase of tonnage that has passed through it
has been extraordinary. So, also, has been the income and the net
receipts of the company. The net tonnage that used the canal in 1870
was only 436,609 tons. Ten years later the tonnage had increased to
3,057,421 tons. In 1885 the tonnage had further increased to 6,335,752
tons, which was the greatest that had passed through in a single year
up to that time. In the last-named year the shipping that used the
canal was more than thirteen times as much as it had been fifteen years
before.
The income and working expenses of the Suez Canal have varied as
follows, compared with the annual income:—
───────────┬──────────────┬───────────────┬─────────────────────
│ │ │Percentage of Working
Year. │ Income. │ Working │ Expenses on
│ │ Expenses. │ Income.
───────────┼──────────────┼───────────────┼─────────────────────
│ £ │ £ │ ..
1870 │ 754,532 │ 754,532 │ ..
1875 │ 1,233,785 │ 717,860 │ ..
1880 │ 1,672,836 │ 682,457 │ ..
1883 │ 2,740,933 │ 758,861 │ ..
1886 │ .. │ 754,567 │ ..
───────────┴──────────────┴───────────────┴─────────────────────
The heaviest items on the expenditure side are the interest and charges
on capital, the administrative charges, transit, navigation, and
telegraph charges, and maintenance of plant and warehouses. The two
latter items, with water supply, make up the working expenses, less
administration, and they amount unitedly to less than 180,000_l._ a
year, or about 7 per cent. on the total gross annual receipts.
There is a not uncommon impression that the trade for the East is now
carried on almost exclusively with steamships _viâ_ the Suez Canal.
Those who are actually engaged in the shipping trade, of course, know
differently, but it is not unimportant that the general public should
also know the facts, and we have, therefore, taken some pains to
ascertain them.
──────────────────┬─────────────┬──────────────┬──────────────
│ Total. │ Steam Ships. │Sailing Ships.
├─────────────┼──────────────┼──────────────
│ tons. │ tons. │ tons.
Vessels entered │ 1,957,000 │ 1,112,000 │ 845,000
Do. cleared │ 3,099,000 │ 1,921,000 │ 1,178,000
├─────────────┼──────────────┼──────────────
Totals │ 5,056,000 │ 3,033,000 │ 2,023,000
──────────────────┴─────────────┴──────────────┴──────────────
From the annual statement of the navigation and shipping of the United
Kingdom, we have extracted the foregoing particulars of the tonnage of
vessels that entered and cleared from the United Kingdom in 1884, in
the Indian and Australian trades distinguishing steamers and sailing
ships.
As sailing ships cannot make use of the canal, it is quite evident
that there must be a use of sailing tonnage to the extent of over two
millions of tons a year in the trade between the United Kingdom and
her Indian and Australasian possessions. Such a fact is not a little
remarkable when we remember that the opening of the canal has shortened
the distance to Bombay by 41 per cent.; to Madras, by 35 per cent.;
and to Calcutta by 32 per cent.[154] In some cases, the sailing tonnage
employed was fully one-half of the whole. The following figures show
how the proportions compare for the different provinces of India, as
regards entrances into British ports:—
──────────────┬──────────────┬──────────────┬────────────────
│ Total. │ Steamers. │ Sailing Ships.
├──────────────┼──────────────┼────────────────
│ tons. │ tons. │ tons.
Bombay │ 336,377 │ 327,039 │ 9,338
Madras │ 74,371 │ 32,251 │ 42,120
Bengal, &c. │ 810,946 │ 426,524 │ 384,222
Ceylon │ 18,373 │ 5,483 │ 12,890
├──────────────┼──────────────┼────────────────
Total │ 1,239,867 │ 791,297 │ 448,570
──────────────┴──────────────┴──────────────┴────────────────
The clearances followed much the same course in the same period. Even
with India, therefore, about 37 per cent. of all our trade passes by
sailing ships round the Cape of Good Hope, instead of going through the
canal, thus proving that the shortening of distance and of time is not
the only consideration that determines the adoption of one route in
preference to another.
One remarkable phase of the Suez Canal traffic is the great increase
that has taken place in the size of the ships passing between the two
seas. When the canal was first put forward by M. de Lesseps, it was
seriously argued that all that was wanted was a canal from the Damietta
branch of the Nile to Suez, which, “with a very little piling and
dredging at either end,” would be accessible to vessels of 300 or 400
tons burthen. Such a canal, it was maintained, “would suffice for all
the wants of Egypt, and for all the local traffic of the two seas.”[155]
It was also maintained, that as the tendency was to increase the
size of the ships employed on the Indian service, the canal would be
compelled to refuse the only traffic ever likely to be offered to
it.[156] The average size of the vessels using the canal in 1870 was only
898 net tons. From this point a gradual increase of size has taken
place, until in 1888 the average size had increased to 1883 tons.
The intervening period of eighteen years had therefore witnessed an
increase of 109 per cent.
[Illustration: M. DE LESSEPS.]
[Illustration: MAP OF THE =SUEZ CANAL= AND PART OF LOWER EGYPT.]
[Illustration: SECTION OF THE SUEZ CANAL.]
Singularly enough, it has been contended that the opening of the
Suez Canal has injured both English and Egyptian interests—English
interests, because it has economised tonnage, saved time, or in other
words, minimised interest on capital, injured our entrepôt trade, and
brought about our occupation of Egypt, with all the heavy expenditure,
loss of life, and international complications which that fact has
involved; Egyptian interests, because the Government of that country
has had to pay large indemnities to the Suez Canal Company, and has
really profited by the success of the enterprise to a much less extent
than it ought to have done, had it not very improvidently sacrificed
the royalties to which it was entitled under the original agreement.
It is, no doubt, unfortunate that our occupation of Egypt, and the
inglorious campaigns in the Soudan, should have been entailed upon
us by our interest in keeping open the canal, but the statistics of
our trade with the East conclusively prove that the canal has had
an important share in the enormous development that has occurred
since it was opened. The movement has, however, been aided by other
influences, and more especially by the opening of telegraph lines,
the improvements that have been effected in steamships and marine
engines, the smaller commissions accepted by merchants or agents, the
lower rates of freight, the reduced charges for insurance, and many
collateral changes, that have all tended, in a greater or less degree,
to facilitate commerce and navigation.
Whether or no M. de Lesseps and his allies have conferred any
substantial advantages on England by their completion of the Suez
Canal, it is quite beyond controversy that the English people have not
rendered much aid in the promotion of that great waterway. The part
which England took when the preliminary arrangements were being made in
1856 is one of which many Englishmen are now a little ashamed. England
was invited to co-operate in the project at an early stage. Not only
did we refuse co-operation, but we refused it with that species of
incivility of which we are occasionally guilty when we have our insular
prejudices offended. The canal was first of all, opposed by the British
Government, as such. Lord Palmerston was then Prime Minister. On the
8th of July, 1857, he declared the opposition to be—(1) that the
construction of the canal would tend to the more easy separation of
Egypt from Turkey, and would, therefore, be in direct violation of a
policy “supported by war and the Treaty of Paris”; and (2) that there
were “remote speculations with regard to easier access to our Indian
possessions, only requiring to be indistinctly shadowed forth to be
fully appreciated,” which rendered the canal undesirable. How much
better it would have been for the memory of genial “old Pam,” if, in
announcing his judgment, he had recollected the rule that “you should
never give your reasons.” History is rapidly made in the nineteenth
century. It is not in the least discreditable to Palmerston that he
should have failed to realise how completely his anticipations would
be falsified by events. No one at that time could have foreseen that,
in less than thirty years from that date, the Suez Canal would not
only have become an accomplished fact, but would have become perhaps
the most successful industrial enterprise of modern times; that it
would have revolutionised our shipping and transit trades; and that
our Indian and Australian possessions would have participated in its
advantages to an enormous degree. Prescience of this kind is given to
few men. But while the lack of this ability to discern the “coming
events” which “throw their shadows before” is not common, so neither
is the example of the representative of a great nation describing as
a “bubble,” and denouncing with all the eloquence and power at his
command, an enterprise which has conferred upon his country, as the
first maritime power in the world, advantages which generally transcend
those that are enjoyed by any other country.
But Lord Palmerston is very far from being a monopolist of this
discredit. Robert Stephenson was at this time one of the leading
English engineers. As the great son of a great father, he enjoyed vast
influence, honourably and justly acquired, and employed, with one
exception, discriminatingly and in a manner worthy of its possessor.
That exception was the position which he took up in reference to the
Suez Canal. Appointed to represent England on a commission of experts
instructed to report on the question of isthmian transit, Stephenson
satisfied himself that the idea of a canal was impracticable, and
reported against it. So far, Stephenson was quite alone. His two
colleagues on the commission—M. Talabot, representing France, and M.
Negrelli, representing Austria—were both in favour of the canal in
preference to the railroad which Stephenson recommended.[157] His brother
engineers in England appear to have stood loyally by Stephenson. They
gave very little countenance to M. de Lesseps or his scheme. Both were,
indeed, denounced from platform and press in the most unsparing manner.
The leading daily journals, which write in haste, and the sober,
scholarly quarterlies, which are supposed to write at leisure and after
much reflection, were alike opposed to it. The _Edinburgh Review_
spoke of it as “utterly impracticable,” and urged that, “the available
population or resources of Egypt could not execute such a work in a
hundred years;” that “an army of foreign navvies would be required to
keep in repair such a work, with its locks, viaducts, steam engines,
and a floating capital hardly inferior to the original outlay”; that
“a vessel in Aden harbour would rather take 3_l._ per ton for England,
if allowed to go _viâ_ the Cape, than she would take 5_l._ if forced
to go through the canal”; that if the principles on which the _Great
Eastern_, was then being built, were sound,[158] there was “an end,
not only of the canal, but the Red Sea may again be restored to its
pristine solitude, undisturbed even by the weekly visit of the passing
steamers”; and, finally, that until different experiences were at
command, “the Suez Canal may fairly be relegated among the _questions
diseuses_ which may interest and amuse, but can hardly ever benefit
mankind.”[159]
So also the ‘Quarterly Review,’ which believed the scheme to be
“commercially unsound,” and set forth a number of objections to it in
categorical form. The great expense of building the masonry harbours
at the two outlets of the canal, the difficulties and dangers of the
navigation of the Red Sea, the cost of the embankments and the expense
of maintenance, the “probability of steamers like the _Great Eastern_
being built to perform the voyage round the Cape to the island of
Ceylon in less time than would be occupied in performing that through
the Suez Canal,”[160] and the impossibility of ensuring the maintenance
of the canal and necessary locks in proper working condition, were
marshalled in battle array as a phalanx of obstacles that could not be
overcome. But the opponents of the canal went further, and declared
that, as a vessel using the canal would take about three days to
get through,[161] would require one day to coal, and another to sail
from Pelusium to the meridian of Alexandria, the saving on goods, as
compared with the railway, would only be one to two days, while on
passengers and mails there would be a loss of four to five days.
The British shipping interest have had some reason to complain of the
way in which they have been treated from first to last by the Suez
Canal Company. It is perfectly true that England did not contribute
anything to the building of the canal, but English shipping has
provided the shareholders with much the larger part of their revenue.
France, which practically owns the canal, only contributes from 6
to 9 per cent. of its income, as against from 75 to 80 per cent. of
the whole contributed by Great Britain. The shipowners of the latter
country not unnaturally thought, some years ago, that they should
have a larger share in the management of the canal, and threatened
the construction of a rival waterway if the existing canal were not
deepened, and other arrangements made for facilitating the shipping
that used it. After a good deal of negotiation between the canal
company and the shipowners, a commission was appointed in 1884 to
determine what new measures, in respect of works and navigation, should
be undertaken to enable the ship canal to meet fully the exigencies of
a traffic exceeding 10,000,000 tons per annum. Its report was presented
in February 1885. The commission considered three methods of increasing
the carrying capacity of the canal, namely:—(1) widening the existing
canal; (2) construction of a second canal; and (3) doubling the
capacity of the canal by a combination of the first two methods.
When the canal was first designed, in 1856, it was supposed that two
vessels, being towed, could easily pass where the bottom width was 144
feet, or double the normal width adopted. At the present day, however,
when vessels of nearly 200 feet in width propel themselves through the
canal, a bottom width of 230 feet has been proposed for the 81 miles
from Port Said to the southern end of the Bitter Lakes, where the tidal
currents do not exceed one knot an hour, and 262 feet for the rest of
the distance to Suez, where the currents often exceed two knots, in
order that the vessels may pass each other freely. The cost of this
widening was estimated at 8,240,000_l._, supposing the depth of the
canal remained as at present, 26¼ feet below low-water of ordinary
spring tides, but it would be increased by 975,200_l._ if the depth was
augmented to 29½ feet, unless the proposed width could be reduced to 18
feet.
The construction of a second canal, within the limits of the company’s
lands, having, like the existing canal, a bottom width of 72 feet,
widened out to 131 feet through the small Bitter Lakes, was estimated
at from 8,200,000_l._ to 8,920,000_l._, with an additional cost of
698,800_l._ if made 29½ feet deep.
The third plan took into consideration the different velocities of
the tidal currents north and south of the Bitter Lakes. Assuming that
the greater velocity might lead to collisions between vessels passing
on a single enlarged canal, it would be advisable to restrict the
enlargement to the northern portion, and to form a second canal between
the Bitter Lakes and Suez. For reasons which are fully set forth in
their Report, the Commission decided in favour of the enlargement of
the existing canal. The estimated cost of the works, which are now in
progress, is rather over 8,000,000_l._
It has been suggested, with some show of reason, that it would be to
the advantage of the commerce of the world that the maritime Powers
should make arrangements to acquire the Suez Canal, and throw it open,
free of any charge or impost whatsoever, to the navigation of all
nations, in the same way that the Scheldt and the Sound have been. The
canal has hitherto been employed almost entirely for the transport
of passengers, mails, and such traffic as will bear a high rate of
freight, the charge of 7_s._ to 10_s._ per ton being prohibitory in
respect to much of the commerce that passes from the East to the West.
The proposal is one that is entitled to every consideration. There
is, however, a high probability, amounting almost to a certainty,
that the proprietors would demand a very large sum in excess of their
original expenditure. The canal has cost from first to last, including
financing, some 20,000,000_l._ At their recent prices, the canal
shares may be considered as worth about four times that amount. If the
property were to be purchased on such a basis, it would require an
expenditure of at least 80,000,000_l._, which sum, although by no means
impossible, is yet little likely to be realised for such a purpose. If
the canal had been taken over in 1880 it could have been purchased for
one-half the sum that would now be required to buy it.[162]
At the same time that the Suez canal route was being advocated with all
his wonted energy and enthusiasm by M. de Lesseps, other two routes to
India were being seriously discussed. As one at least of these is still
on the carpet we may fitly say something of it here.
Up to the sixteenth century the best known and the most frequented
route to India was that by the valleys of the Euphrates and the Tigris.
These two great rivers of Mesopotamia are among the most celebrated
in the world’s history. The Euphrates has its source in the northern
highlands of Armenia; the Tigris in the southern slopes of the same
mountainous region, being fed by many rivers that traverse the boundary
line between Persia and Turkey. Almost at the dawn of recorded history,
we find that the Assyrians and the Babylonians connected these two
rivers by a series of canals. Two of these, constructed parallel to the
rivers Euphrates and Tigris, were large enough to be navigated, but the
system was constructed mainly with a view to irrigating the surrounding
plains, which, for nearly six months, were liable to be burnt up by the
scorching sun. As the Arabs and Turcomans gained greater ascendancy in
this region, the arts of husbandry were less practised, and the canals
and water-courses were allowed to fall into desuetude and decay. Their
embankments still, however, remain to attest the remarkable skill,
labour, and industry with which, at this early date, the fertility
of the soil was stimulated and increased, until the extraordinary
productiveness of Assyria and Babylonia became a favourite theme of
Herodotus and other historians.
Through this region, until the trade of the East was drawn into the
newer channel _viâ_ the Cape of Good Hope, European merchants sought
an outlet for their trade with the East. Bagdad and Bussora were
then great entrepôts of commerce. Mosul and Aleppo were the ancient
counterparts of Suez and Port Said. The route was, however, never
a safe or a satisfactory one. The Syrian desert, close at hand,
claimed many victims. The wild Arab tribes committed depredations on
travellers. The “unspeakable” Turk was exacting and intolerant. The
journey to India and back lasted for a lengthened period—often two
or three years—where it now scarcely extends over so many months.
But in spite of all this, the indomitable spirit and energy of the
English race led it to establish a secure footing on such ungenial
soil, and amid such inhospitable surroundings. An English factory long
flourished at Aleppo. A fleet of boats was, in the reign of Elizabeth,
maintained on the Euphrates for the use of British traders. When the
Levant Company was founded in 1582, it was deemed a veritable Eldorado
to have the exclusive privilege of trading with this part of the globe.
All this has long ceased to be, but the proposal to have the Euphrates
and the Tigris utilised as a trade route to India has been again and
again revived. In 1834, the British Government determined to fit out
an expedition to test the capabilities of the Euphrates for steam
navigation. The expedition was placed under the charge of Colonel
Chesney, upon whose recommendation it was adopted by Parliament. It
was found that the Euphrates was in some places a broad and deep
stream, and in others navigation was impeded by shallows, sandbanks,
rapids, and stone dams of large size, built for irrigation purposes.
One of the two vessels fitted out for the use of the expedition
foundered in a storm, and many lives were lost. The Government,
deeming the result unsatisfactory, declined to take any further part
in exploring the Euphrates. In 1840, however, the East India Company
commissioned Lieutenant Campbell to attempt the ascent of the river.
This expedition sailed up the Tigris to within a few miles of Mosul.
They found a canal uniting the Euphrates and Tigris near Bagdad,
which, however, has long been closed. They also navigated the great
canal which is said to have been constructed by the Emperor Valerian
during his captivity, nearly as far as Shushtir, and several rivers
in Persia. One of the vessels employed on this expedition was for
many years afterwards accustomed to make occasional voyages between
Bagdad and Bussora, mainly in order that our privilege to navigate
the river should be maintained, and our influence in Western Asia
preserved.
The proposal put forward by the promoters of the Euphrates Valley route
in 1856, was to navigate the rivers Euphrates and Tigris from about the
latitude of Aleppo to the sea, to construct a harbour at Suedia, and a
railway thence to Kalah Jaber. From this point it was proposed that
steamers should convey mails, passengers, and merchandise to Bussora,
whence sea-going vessels should run to India.[163] The route to India
would thus be reduced to 4715 miles, and the time necessary for the
journey to less than sixteen days, giving a saving of thirteen days out
and nine days home upon the Suez voyage.
The cost involved in this undertaking, not to speak of its mechanical
and physical difficulties, led to its abandonment, although it is by
no means certain that the engineering problems to be dealt with are
more considerable than those which have had to be solved at Panama. One
serious difficulty, which has been deemed all but insuperable, is the
fact that the waters of the Jordan are just sufficient to balance the
evaporation from the surface of the Dead Sea, so that if that sea were
increased to five or six times its superficial area, as proposed, it
would require a much larger volume of water than the Jordan can furnish
to meet the deficiency. The project also labours under the defects of
climate, a thin population, and an absence of food and water supplies.
In the last century the Marquis of Wellesley endeavoured to utilise
the Euphrates Valley route; and the House of Commons has been asked
to grant sums of money for various purposes in connection with it at
different times. In 1871 the House of Commons ordered an official
inquiry, with a view to place upon record all the useful information
available, including the evidence of Colonel Chesney and others, as to
this route.
It has not been supposed by the promoters of a railway to India that
such a railway would be in any way antagonistic to the Suez Canal,
which would, in all probability, monopolise the heavy traffic, and
still exist as the chief means of communication with Southern India.
But, on the other hand, the Euphrates line would benefit the north-west
provinces, and, as far as passengers and mails are concerned, would
effect a saving in time of at least a fortnight, taking the voyage
out and home. The saving in distance would be about 1000 miles in a
straight line, and, as vessels proceeding by way of the Red Sea are
compelled to deviate from their courses to the extent of 500 or 600
miles during the monsoon months, the saving that might accrue, taking
an average of voyages, would be somewhere about one thousand miles each
voyage. On the other hand, the railway would always suffer from the
fact that two trans-shipments would have to be effected in every case,
and this, where the goods are bulky, is a serious consideration. Prior
to the opening of the Suez Canal only goods of small bulk were sent to
India by way of the Isthmus Railway, although the voyage by the Cape
occupied eight days, and it is regarded as probable that the canal
would still retain heavy traffic.
Besides the Euphrates Valley, two other routes to India have been
proposed. One of these aimed at the substitution of the Black Sea for
the Mediterranean, and making the terminus of the line at Trebizonde.
By the champions of this scheme it is contended that the long and
dangerous voyage necessitated by a Mediterranean terminus would be
avoided, by making use of the Danube and the short passage across the
Black Sea. On the European side, however, there is the liability to
having the Danube, or, indeed, the Black Sea, closed, the effect of
which would be that the railway would be simply useless, as long as the
restrictions remained in force; and on the Asiatic side there would be
serious practical obstacles in the mountain ranges near Trebizonde.
The Tigris Valley route has also been recommended on the ground that
it would open out a better country, and one peopled by more peaceful
tribes. Of the respective advantages of the two routes in regard to
facilities of construction, it is enough to say that the Valley of the
Euphrates is practically flat, and that nothing better could be desired
in the matter of level, while it is not easy to say what difficulties
the Tigris Valley may or may not present. Mr. Eastwick has visited
various parts of the Euphrates route, and he states that the facilities
there for making a good road are great, and that in certain districts
the local traffic would, in all probability, be very considerable.
Another plan was proposed some thirty-five years ago, for forming a
water communication between the Red Sea and the Mediterranean.
This proposal, made by Captain W. Allen, of H.M.’s navy, was based on
the knowledge we now possess that the level of the Dead Sea is at least
1300 feet below that of the Mediterranean or Red Seas, and that the Sea
of Galilee is, in like manner, depressed to the extent of about 650
feet; so that the mean level of the valley of the Jordan, with its two
lakes, may be taken at 1000 feet below the neighbouring seas, and its
extent as covering about 2000 square miles. This vast area Captain
Allen proposed to convert into a great inland sea by cutting a canal
from Acre across the plain of Esdraëlon to the Jordan, a distance of
about 40 miles on the map, and another from Akabah, on the Red Sea, to
the southern limit of the Dead Sea, a distance of about 120 miles.
The summit level of the plain of Esdraëlon may be as low as 100 feet
above the sea level, or as high as 200 feet, and from the appearance of
the banks of the brook Kishon, near its junction with the sea, and the
hills that bound the plain on both sides, the ground is rocky nearly
throughout its whole extent at a small distance below the surface. The
proposal, therefore, as described in the ‘Edinburgh Review,’ was to dig
a canal through a rocky country for 30 or 35 miles in length, and with
a mean depth of 80 to 100 feet.
A plan has quite recently been put forward for the construction of
a parallel canal to that across the Isthmus of Suez, by way of the
Euphrates Valley, the Persian Gulf, and Syria. The proposal is to
create a navigable highway from Sonëidich to the Persian Gulf, by
making the Euphrates flow to the Mediterranean and Antioch. The river
from Beles to Felondjah (near ancient Babylon) would be deepened, and
the waterway would be carried from the Euphrates to the Tigris by the
canal of Saklavijah. Thence the route would be by the Tigris from
Bagdad to Kornah, Bassora, and Fao on the Gulf. The author of this
proposal[164] estimates that the canal would shorten the route to Bombay
by six days, and it would irrigate and restore fertility to a great
part of the country through which it would pass. The estimated capital
required would be 1,500,000,000 francs (60,000,000_l._ sterling).
FOOTNOTES:
[138] The immediate cause of this occurrence does not appear, but
it is obvious that there would not be much employment for a canal
at this early date. The first ship would no doubt be constructed
anterior to this period, but the vessels of that day were rude and
small.
[139] The Red Sea is 1500 miles in length, and, besides being
narrowed in its middle channel, is so deep that there is hardly any
place where a vessel can anchor. Sailing vessels have to contend with
currents that are blowing steadily to the northward for a great part
of the year, while for some months there is little or no wind.
[140] Herodotus, book ii., secs. 159 and 160, Cary’s translation.
[141] Washington Irving’s ‘Successors of Mahomet.’
[142] Rubino’s “Statistical Story of the Suez Canal,” in the
‘Journal’ of the Royal Statistical Society for 1887.
[143] ‘Mémoire sur le Canal des deux Mers.’
[144] ‘Quarterly Review,’ January 1856, p. 257.
[145] Since then, of course, this difficulty has been conquered by
the use of steam dredgers.
[146] This letter is reproduced from an excellent article on the
subject of the Suez Canal in _Engineering_ of December 7, 1883, p. 52.
[147] In 1886 the transit and navigation receipts were over
2,500,000_l._
[148] The following are the details of the contracts for works on
Suez Canal:—
──────────────────────┬───────────────────
Dussaud frères, │ Aiton, Glasgow.
Marseilles. │
──────────────────────┼───────────────────
_20th October, 1863._ │ _13th January, 1864._
250,000 blocks of │ 21,700,000 cubic
artificial stone of │ metres of
1 cubic metre │ excavations
each (35⅓ cubic │ at 1·35 fr.
feet), and weighing │ The plant ceded
20 tons, at │ to the contractor
40 frs. each. │ by the company
10,000,000 frs. │ brings the price
400,000_l._ │ up to 1·60 fr.
│ 34,720,000 frs.
│ 1,388,800_l._
│ Contract
│ afterwards
│ cancelled, and
│ transferred
│ to Borel and
│ Levalley.
──────────────────────┼───────────────────
Couvreux, Paris. │ Borel and Levalley,
│ Paris.
──────────────────────┼───────────────────
_1st October, 1863._ │ _1st April, 1864._
9,000,000 cubic │ 24,500,000 cubic
metres of │ metres of
excavations at │ excavations at
1·60 frs. │ 2·28 frs.
14,000,000 frs. │ 56,000,000 frs.
560,000_l._ │ 2,240,000_l._
Enlargement and │ Continuation and
deepening of the │ completion of 53
great El Guisr │ miles of cutting
trench, over 8 │ from Lake Timsah
miles long. │ to Red Sea.
│
│ _Second contract._
│ Transfer of Aiton’s
│ contract.
──────────────────────┴───────────────────
[149] We do not, of course, include the Panama Canal, which is not,
and may never be, completed.
[150] One long trough dredger, set to work in June 1885, weighed 760
tons.
[151] It is stated that the number of these baskets used at the
trench of El Guisr alone would, if extended in line, reach three
times round the world. Of course when the fellaheen were withdrawn in
1864 these baskets were less largely used.
[152] The following table shows the principal distances and the
saving by the canal:—
───────────────┬───────────┬───────────┬───────────────────────
│ │ │ Saving by Canal.
│ │ ├───────────┬──────────
Ports. │ By Cape. │ By Canal. │ │ Per Cent.
│ │ │ Amount. │ of Voyage
│ │ │ │ (Cape.)
───────────────┼───────────┼───────────┼───────────┼──────────
│ nautical │ nautical │ nautical │
│ miles. │ miles. │ miles. │
│ │ │ │
Bombay │ 10,667 │ 6,274 │ 4,393 │ 41·2
Madras │ 11,280 │ 7,313 │ 3,967 │ 35·2
Calcutta │ 11,900 │ 8,083 │ 3,817 │ 32·1
Singapore │ │ │ │
(_viâ_ Straits│ │ │ │
of Sunda) │ 11,740 │ 8,362 │ 3,378 │ 28·8
Hong Kong │ 13,180 │ 9,799 │ 3,381 │ 25·6
Shanghai │ 14,050 │ 10,669 │ 3,381 │ 24·1
Adelaide │ 11,780 │ 11,100 │ 680 │ 5·8
Melbourne │ 12,140 │ 11,585 │ 555 │ 4·6
Sydney │ 12,690 │ 12,145 │ 545 │ 4·3
Wellington, │ │ │ │
New Zealand │ 13,610 │ 13,055 │ 555 │ 4·1
───────────────┴───────────┴───────────┴───────────┴──────────
[153] This amount was made up as follows:—
£
Construction of canal 11,653,218
Transit, estate, and other services 533,552
Management charges (11 years) 567,296
Interest on shares (11 years) 2,673,864
Interest and repayment of debentures 585,118
Banking charges, stamps, loss in bonds, &c. 618,905
───────────
£16,631,953
═══════════
[154] “The Statistical Story of the Suez Canal,” in the ‘Journal’ of
the Royal Statistical Society for 1887.
[155] ‘Edinburgh Review,’ January 1856, p. 245.
[156] It was assumed that the canal could not take vessels like the
_Himalaya_ and the _Persia_, or indeed any vessel over 350 feet in
length.
[157] The preference of Stephenson for a railway is not difficult to
understand. He had “won his spurs” in railroad construction, and was
familiar with every phase of their working and capabilities, but he
had had comparatively little knowledge experimentally of canals. He
was, indeed, the apostle of the new era—the railway against the canal.
[158] It was expected that the _Great Eastern_ steamship would attain
a speed of 25 knots an hour, and the proposition that a vessel’s
speed is almost in the direct ratio to her length having once been
granted, that a class of vessels would come to be built that would be
too large to make use of the canal.
[159] ‘Edinburgh Review,’ vol. ciii. (January 1856).
[160] This seems an extraordinary assumption when we consider that
the canal saves in the journey to Bombay 41 per cent. of the voyage
by the Cape, and on the journey to Madras and Calcutta 32 to 35 per
cent.
[161] In 1887 the average duration of the passage through the canal
for the whole 3137 ships that made use of it was 34 hours 3 minutes.
Between 1870 and 1873 the passage was frequently effected in 12 to 15
hours.
[162] The shares rose from a middle price of 306 francs in 1867 to
664 in 1877, 1021 in 1880, 2710 in 1882, and fell to 1989 in 1884,
rising again to 2095 in 1886.
[163] The distance from Suedia to Kalah Jabar, a small Arab
settlement on the Euphrates, was put down at 100 to 150 miles, and
the river journey from Kalah Jabar to Bussora at 715 miles. From
Bussora to Kurrachee the distance is 1000 miles. The average time
occupied in descending the Tigris was taken at seven days, and that
of the ascent at twelve.
[164] M. Emile Ende, in a communication to the French Academy of
Sciences in 1886.
Reading Tips
Use arrow keys to navigate
Press 'N' for next chapter
Press 'P' for previous chapter